448 results found for 'Vineyard Wind '

448 results found for 'Vineyard Wind '
Order results by

A list of search results

  • 18 July 2024
    Project Updates, Wind Farm Update

    The US Bureau of Safety and Environmental Enforcement (BSEE) has issued an order instructing Vineyard Wind to halt electricity production from all wind turbines following a blade failure incident on 13 July. The 800 MW Vineyard Wind offshore wind farm is planned to feature 62 GE Vernova’s Haliade-X 13 MW wind turbines, each with a […]

  • 16 July 2024
    Project Updates, Wind Farm Update

    NOTE: The article was updated on 19 July with more information about the GE Vernova turbine blade incident at the Vineyard Wind project.  A turbine blade at the Vineyard Wind 1 offshore wind farm in the US has been damaged, leading to an investigation by the blade’s manufacturer, GE Vernova. Vineyard Wind, a joint venture […]

  • 26 June 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    The Vineyard Wind 1 project is now delivering more than 136 MW to the electric grid in Massachusetts, making it the largest operating offshore wind project in the US. Vineyard Wind 1, the first large-scale offshore wind project in the US, now has ten turbines in operation totalling approximately 136 MW, enough to power 64,000 […]

  • 23 February 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    Vineyard Wind 1, America’s first large-scale offshore wind farm, has begun delivering energy to the New England grid from five of its planned 62 GE Haliade-X 13 MW wind turbines. The units are currently generating 68 MW of energy, enough to power 30,000 homes in Massachusetts, according to the developers of the project, Avangrid and […]

  • 17 July 2024
    Fixed-Bottom, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    Following a blade damage incident that took place on 13 July at its 800 MW offshore wind project in Massachusetts, Vineyard Wind has revealed that it is mobilising debris recovery teams on Nantucket. Vineyard Wind, a joint venture between Iberdrola’s US subsidiary Avangrid and Denmark’s Copenhagen Infrastructure Partners (CIP), announced on 16 July that it […]

  • 25 July 2024
    Business & Finance, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    The breakage of the blade on one of GE Vernova’s Haliade-X wind turbines at the Vineyard Wind 1 offshore wind farm in the US was caused by a manufacturing deviation, the company’s CEO Scott Strazik revealed during an earnings call on 24 July. Strazik also pointed out that a blade event that happened on a […]

  • 28 March 2024
    Authorities, Business development, Planning & Permitting, Research & Development

    Four developers have submitted their bids in response to the combined Connecticut-Massachusetts-Rhode Island offshore wind solicitation with the tenders totalling 6.8 GW. The proposals were made by Avangrid Renewables, Ørsted, SouthCoast Wind Energy, and Vineyard Offshore. In October 2023, the three states signed a Memorandum of Understanding (MoU) to collaborate on offshore wind procurement, although […]

  • 30 April 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    The installation of transition pieces (TPs) is about to commence at Vineyard Wind 1, America’s first large-scale offshore wind farm. Beginning next month, DEME Group’s jack-up vessel Sea Challenger will begin placing TPs at 17 monopile locations in lease area OCS-A 0501. The campaign will continue through June 2024. The units are being manufactured by […]

  • 18 July 2024
    Business & Finance, Business development, Collaboration, Outlook & Strategy, Research & Development

    EDF Renewables and Repsol have signed an exclusivity agreement to collaborate on future offshore wind tenders in Spain and Portugal. According to the press release, this collaboration combines Repsol’s commitment to multi-energy growth and its knowledge of the Spanish and Portuguese markets with EDF Renewables’ technological experience. Repsol said that it expects to have 9,000 […]

  • 6 June 2024
    Business & Finance, Contracts & Tenders, Supply Chain

    Dutch offshore access provider, Ampelmann, has received an order from Seaway7 to supply an E5000 gangway, which will support the construction of a major US coast offshore wind project. The order not only marks the first collaboration of Seaway7 and Ampelmann in the Americas but will also see the first tour of duty of the […]

  • 10 July 2024
    Business & Finance, Industry, Market Outlooks, Outlook & Strategy, Supply Chain

    The American Clean Power Association (ACP) has projected there will be approximately 14 GW of offshore wind capacity deployed by 2030, falling short of the 30 GW goal set by the Biden Administration in 2021. ACP’s recent report also outlines USD 65 billion (approximately EUR 60 billion) in investments and 56,000 jobs in the US […]

  • 26 June 2024
    Business & Finance, Contracts & Tenders, Floating Wind, Supply Chain, Wind Turbines

    Denmark’s Floating Power Plant has purchased a wind turbine from Siemens Gamesa Renewable Energy for its flagship demonstrator project located off the coast of Gran Canaria. According to the company, the selected wind turbine, a 4.3 MW SWT-DD-120 from Siemens Gamesa, fits Floating Power Plant’s requirements for a well-established technology. The wind turbine generator will […]

  • 26 July 2024
    Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    More than a quarter of wind turbines at Dogger Bank A, the first phase of the UK’s 3.6 GW Dogger Bank Wind Farm, have been installed. So far, 27 of the 95 GE Haliade-X 13 MW wind turbines that Dogger Bank A will comprise are in place, according to information in Equinor’s results for the […]

  • 18 July 2024
    Business & Finance, Business development, Ports & Logistics, Research & Development

    NIRAS has been selected by the Asian Development Bank (ADB) to prepare pre-feasibility studies to assess the expansion of several ports for use as offshore wind ports. The Denmark-headquartered consultancy company has been commissioned by ADB on behalf of the Philippine government. Under the contract, NIRAS will prepare the pre-feasibility studies for the expansion of […]

  • 16 July 2024
    Business & Finance, Business development, Research & Development

    Energy and marine consultancy ABL has been selected by Germany’s Federal Maritime and Hydrographic Agency (BSH) to conduct a navigational risk assessment of offshore wind farm sites in the N-10 identified area of interest in the German North Sea. ABL’s scope of work is to provide a comprehensive navigational risk assessment, including recommendations for risk […]

  • 19 July 2024
    Contracts & Tenders, Grid Connection, Offshore Platforms, Onshore Infrastructure, Supply Chain

    The transmission system operator (TSO) 50Hertz has awarded the consortium comprising Dragados Offshore, a subsidiary of Cobra IS, and Siemens Energy a EUR 2.9 billion contract to design, build, and install two electrical conversion stations. The consortium’s scope of work consists of supplying an offshore converter for the LanWin3 grid connection project in the North […]

  • 27 February 2024
    Authorities, Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    The US Bureau of Ocean Energy Management (BOEM) has completed its environmental review of the 2.6 GW New England Wind offshore wind project, proposed to be built in a lease area off Massachusetts, Rhode Island, and New York. BOEM has now published a final environmental impact statement (FEIS) for the project and expects to issue […]

  • 2 July 2024
    Authorities, Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    Avangrid, a US renewable energy company majority-owned by Spanish Iberdrola, has received the authorisation to build and operate its New England Wind offshore wind farms from the Bureau of Ocean Energy Management (BOEM). This is the final approval needed from BOEM for the two projects offshore Massachusetts totalling 2.6 GW, following the federal agency’s Record […]

  • 26 July 2024
    Authorities, Business & Finance, Business development, Floating Wind, Planning & Permitting, R&D, Research & Development

    The US Department of Energy’s (DOE’s) Wind Energy Technologies Office (WETO) has launched the Offshore Wind National and Regional Research and Development Funding Opportunity, allocating USD 48.6 million to projects designed to address several key needs in offshore wind development. The areas include accelerating research and development of floating offshore wind platforms; exploring innovations for […]

  • 15 April 2024
    Fixed-Bottom, Project Updates, Vessels, Wind Farm Update

    Read the latest news on CVOW here: 2.6 GW US Project Receives Final Federal Permit, Monopile Installation to Start in May The DP3 installation vessel Orion, owned and operated by the Belgian offshore construction specialist DEME, has sailed out of Invergordon in Scotland and is now en route to the United States, where it will […]

  • 8 March 2024
    Business & Finance

    Spanish renewable energy giant Iberdrola, which owns around 81.6 per cent of its US subsidiary Avangrid, has launched an offer to acquire the remaining 18.4 per cent in the Connecticut-headquartered company for USD 2.48 billion (EUR 2.28 billion). Iberdrola says it wants to increase exposure to the networks business in the US and grow in markets […]

  • 3 January 2024
    Project Updates, Wind Farm Update

    Vineyard Wind offshore wind project, being developed by Avangrid and Copenhagen Infrastructure Partners (CIP), has delivered its first power to the New England grid in Massachusetts. As part of the initial commissioning process, on Tuesday 2 January 2024, one turbine delivered approximately 5 MW of power, with additional testing expected to happen both on and […]

  • 9 July 2024
    Business & Finance, Fixed-Bottom, Project Updates, Wind Farm Update

    Iberdrola, through its US subsidiary Avangrid, and Virginia Electric and Power Company, a wholly-owned subsidiary of Dominion Energy, have signed an agreement under which Dominion will acquire the Kitty Hawk North Wind offshore wind lease area. The site, located some 40 kilometres north of the under-construction Coastal Virginia Offshore Wind (CVOW) project, would be renamed CVOW-South, […]

  • 25 March 2024
    Authorities, Business development, Fixed-Bottom, Planning & Permitting, Project Updates, Research & Development, Wind Farm Update

    The US Bureau of Ocean Energy Management (BOEM) has issued a Notice of Intent (NOI) to prepare an Environmental Impact Assessment (EIS) for the Construction and Operations Plan (COP) for Vineyard Northeast’s proposed offshore wind project, located offshore Nantucket, Massachusetts. The publication of the NOI in the Federal Register opened a 45-day public comment period […]

  • 28 December 2023
    Business & Finance, Fixed-Bottom, Jobs & Recruitment

    Vineyard Wind 1, the 806 MW offshore wind farm that Copenhagen Infrastructure Partners (CIP) and Avangrid are building off Massachusetts, has created 937 union jobs during the two years of the project’s construction. With more jobs coming in 2024, Vineyard Wind 1 will have created more than 1,000 union jobs by the time the construction […]

  • 21 March 2024
    Business & Finance, Project Updates, Wind Farm Update

    Shell New Energies, a subsidiary of Shell, has sold its 50 per cent equity share in SouthCoast Wind Energy, established in 2018 to develop wind projects off the coast of Massachusetts, to its joint venture partner Ocean Winds North America for an undisclosed sum. According to Shell, the deal with Ocean Winds was structured to […]