385 results found for 'BorWin6'

385 results found for 'BorWin6'
Order results by

A list of search results

  • 23 March 2026
    Fixed-Bottom, Foundations, Grid Connection, Offshore Platforms, Supply Chain, Vessels

    Heerema Marine Contractors’ semi-submersible crane vessel (SSCV), Sleipnir, has installed the jacket foundation for the BorWin kappa platform, part of TenneT’s BorWin6 offshore grid connection in the German North Sea. Heerema carried out the work on behalf of McDermott International, which was awarded the engineering, procurement, construction and installation (EPCI) scope for the BorWin kappa topside and […]

  • 18 February 2026
    Grid Connection, Manufacturing, Offshore Platforms, Project Updates, Supply Chain

    McDermott has cut first steel for the offshore converter platform for TenneT’s LanWin1 offshore grid connection in Germany. The LanWin1 project will include an offshore converter station in the North Sea and an onshore converter station in the region of Wesermarsch. The platform will be delivered under a contract GE Vernova and McDermott International signed with the […]

  • 9 February 2026
    Grid Connection, Offshore Platforms, Project Updates

    Mammoet has completed the transport, load-out and mooring of the jacket foundation for the BorWin kappa offshore converter platform at McDermott’s yard in Dubai, UAE. BorWin kappa is part of TenneT’s 980 MW BorWin6 offshore wind grid connection in the German North Sea. The Dutch company has been selected as a subcontractor to provide jacking, […]

  • 30 March 2026
    Cables, Contracts & Tenders, Fixed-Bottom, Grid Connection, Supply Chain

    Jan De Nul has contracted CRP Subsea to supply protection systems for inter-array cables at Vattenfall’s Nordlicht I offshore wind farm in the German North Sea. CRP Subsea will deliver 141 NjordGuard cable protection systems (CPS), with three NjordGuard CPS designs to be engineered to meet the specific installation requirements for both monopile and J-tube […]

  • 25 March 2026
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Vessels, Wind Farm Update

    Heerema Marine Contractors has installed the jacket foundation for the first Hornsea 3 offshore substation using its semi-submersible crane vessel (SSCV) Sleipnir. According to a Notice to Mariners issued by the project on 20 March, Sleipnir commenced the work at the construction site offshore the UK on 19 March. The notice states that the vessel […]

  • 25 February 2026
    Vessels

    Allseas’ new cargo barge Braveheart, built by the CIMC Changhong Shipyard, which held a keel-laying ceremony for the new vessel in April 2025, has now departed China for the Netherlands. Braveheart was purpose-built to fit precisely within Pioneering Spirit‘s bow slot to enable seamless transfer of offshore structures, from decommissioned platforms heading ashore to newly […]

  • 30 April 2026
    Business & Finance, Vessels

    North Star and Norwind Offshore have completed acquisitions of vessels from Edda Wind, finalising the split of the company’s service operation vessel (SOV) and commissioning service operation vessel (CSOV) fleet. The two transactions follow Edda Wind’s announcement in March that it had entered into agreements to divest its SOV and CSOV fleet to two buyers, […]

  • 31 July 2026
    Contracts & Tenders, Fixed-Bottom, Foundations, Grid Connection, Manufacturing, Offshore Platforms, Supply Chain

    South Korean offshore wind foundation manufacturer SK oceanplant has secured a contract from Seatrium to manufacture and supply the jacket foundation and piles for TenneT’s BalWin5 high-voltage direct current (HVDC) offshore converter platform in the German North Sea. The contract will see SK oceanplant carrying out construction engineering, procurement, fabrication and load-out of one jacket […]

  • 4 March 2026
    Business & Finance, Vessels

    Edda Wind has entered into agreements for the potential sale of its fleet of service operation vessels (SOVs) and commissioning SOVs (CSOVs), including newbuilds, with two buyers amongst which the fleet will be split: North Star and an affiliate of Navigare Capital Partners. The vessel operator said on 4 March that additional information would be […]

  • 21 January 2026
    Fixed-Bottom, Operations & Maintenance, Project Updates, Vessels, Wind Farm Update

    Vard has delivered a new vessel built for Norwind Offshore, Norwind Maestro, which will be deployed on a German offshore wind farm. The new commissioning service operations vessel (CSOV) is built to the VARD 4 19 design and constructed at Vard Shipyards Romania, with final outfitting, commissioning, and completion carried out at Vard Søviknes in […]

  • 15 December 2025
    Cables, Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    Jan De Nul has installed three HVAC subsea cables, delivered by Hellenic Cables, between TenneT’s offshore converter station DolWin kappa and Nordseecluster 1 and 2 sites in the German North Sea. The two locations make up the 660 MW Nordseecluster A offshore wind farm, which itself is part of a bigger, two-phased Nordseecluster project. With […]

  • 12 December 2025
    Business & Finance, Innovation, Supply Chain

    The Crown Estate, through its Supply Chain Accelerator programme, has awarded GBP 13 million (nearly EUR 15 million) to 16 UK offshore wind supply chain projects in the early stage of development to help de-risk them and accelerate their path to the market. The second round of the Supply Chain Accelerator, which is awarding nearly […]

  • 4 June 2021
    Contracts & Tenders, Grid Connection

    TenneT has awarded several companies and consortia with contracts for consultative engineering and construction services for the offshore transformer stations that will be part of the BorWin5 and BorWin6 offshore grid connections in Germany. A consortium between Fichtner and SeaRenergy will deliver the services for both platforms, while DNV GL, Lloyd’s Register and TÜV Rheinland […]

  • 15 December 2021
    Contracts & Tenders, Grid Connection

    TenneT has opened a tender for ground investigation work to be performed offshore Germany, where the transmission system operator (TSO) will install the BorWin kappa offshore converter platform as part of the BorWin6 offshore grid connection. The TSO is looking to award a contract for the execution of main ground investigation for a specific type of […]

  • 6 July 2022
    Contracts & Tenders, Grid Connection

    Nexans has won the contract for cabling work on the BorWin6 offshore grid connection in Germany, which TenneT awarded following a tendering process. Under the contract with TenneT, awarded through a tendering process, Nexans is responsible for the production and laying of cables, including the sea, tidal flat, and land cables.  The cable laying work […]

  • 5 July 2023
    Grid Connection

    The construction work has begun on the BorWin6 High-Voltage Direct Current (HVDC) project which will be delivered by TenneT to link 980 MW of offshore wind capacity to the German grid. Through a consortium with Global Energy Interconnection Research Institute and C-EPRI Electric Power Engineering (GEIRI/CEPRI), McDermott is providing engineering, procurement, construction, installation, and commissioning […]

  • 30 October 2025
    Authorities, Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    Vattenfall has received the green light from Germany’s Federal Maritime and Hydrographic Agency (BSH) for the construction and operation of the Nordlicht 2 offshore wind farm in the North Sea. On 29 October, BSH granted planning approval for Vattenfall’s 630 MW Nordlicht 2, which will be built in area N-6.6, located more than 84 kilometres […]

  • 27 March 2023
    Contracts & Tenders, Grid Connection

    Bohlen & Doyen, a subsidiary of the German energy infrastructure construction company Friedrich Vorwerk Group, has signed a contract with French cable manufacturer Nexans to build the onshore cable connection for the BorWin6 offshore wind grid in Germany. The total volume of the order is in the mid-two-digit million range, according to a press release […]

  • 12 March 2021
    Contracts & Tenders, Grid Connection

    TenneT has issued a periodic indicative notice to carry out the market investigation on the planned procurement of the BorWin6 HVDC cable system. All potential and interested market participants are invited to express their interest in the market investigation and to provide an overview of the current status of the planning documents. Located in the […]

  • 28 March 2022
    Contracts & Tenders, Grid Connection

    VCE Vienna Consulting Engineers ZT has been awarded a contract to install Structural Health Monitoring (SHM) systems on twelve TenneT’s HVDC platforms in Germany. On nine platforms, which are in operation, the installation of the SHM systems will be carried out offshore during operation, while for the three platforms which are under construction or in […]

  • 21 September 2021
    Contracts & Tenders, Grid Connection

    TenneT has issued a call for tenders for Structural Health Monitoring systems (SHM systems) and their installation on twelve offshore HVDC platforms, including both existing and platforms yet to be installed offshore. Under a five-year, EUR 3.25 million contract, the tender winner will develop and install a monitoring concept for the support structures of the […]

  • 4 December 2020
    Contracts & Tenders, Grid Connection

    TenneT TSO GmbH has issued a tender notice for the design, manufacture, installation, and commissioning of the BorWin6 converter platforms. Located in the North Sea Cluster 7, the 900 MW BorWin6 is scheduled to be commissioned by 2027. The offshore grid connection will collect the three-phase electric power generated at an offshore wind farm to […]

  • 25 March 2020
    Grid Connection

    TenneT Offshore GmbH has issued a tender for the technical planning of an onshore cable route as part of the planning approval process for the BorWin6 offshore grid connection in the German North Sea. The tender includes the technical planning of the country route of the BorWin6 cable system, which lands in Neuenkoog (Büsum) and […]

  • 22 January 2024
    Authorities, Grid Connection, Offshore Platforms, Planning & Permitting

    Germany’s Federal Maritime and Hydrographic Agency (BSH) has approved the offshore grid connection system for TenneT’s BorWin5 and BorWin epsilon project in the German North Sea. This marks the last project to be implemented based on the specifications of the Federal Offshore Plan 2017 for the North Sea. The area development plan, which has been […]

  • 2 June 2021
    Contracts & Tenders, Grid Connection

    Transmission system operator TenneT has issued a notice for a turnkey contract covering the cable system needed to connect the BorWin6 offshore platform to the German grid. With the 930 MW BorWin6 project, TenneT is planning a direct current connection in the North Sea Cluster 7. Scheduled to be commissioned by 2027, the BorWin6 offshore […]

  • 15 February 2022
    Contracts & Tenders, Grid Connection

    A consortium comprising McDermott and Global Energy Interconnection Research Institute and C-EPRI Electric Power Engineering (GEIRI / C-EPRI) has been awarded a contract for offshore and onshore converter stations for the German BorWin6 offshore grid connection which will be delivered by TenneT to link 980 MW of offshore wind capacity to the German grid. “With […]