BorWin Gamma Unites with Its Jacket

The BorWin gamma topside has been installed onto its jacket foundation at the offshore site in the German North Sea.

Source: TenneT

According to TenneT, the installation was completed today, 11 October, around noon through a float-over process.

The fabrication of the topside for TenneT’s 900MW BorWin3 HVDC platform was completed at the end of August at Drydocks World – Dubai.

Shortly after, the structure began its journey from the United Arab Emirates to the installation site some 130km off the German coast, at which it arrived on 7 October.

The BorwWin3 grid connection is scheduled to be fully commissioned in 2019 when it will start to deliver the power generated by offshore wind farms to the German grid.

Related news

List of related news articles

Posted: 6 months ago

BorWin Gamma Arrives Home

The BorWin gamma topside has completed its journey from Dubai to the installation site in the German...

Categories:
  • Grid Connection
Posted: 6 months ago
Posted: 6 months ago

BorWin Gamma Preps for Installation

The BorWin gamma topside is currently being prepared for installation onto its jacket foundation in ...

Categories:
  • Grid Connection
Posted: 6 months ago
Posted: 6 months ago

Innogy to Reallocate Green Bond Proceeds from Wind to Grid

Innogy’s Green Bond Committee has decided to reallocate proceeds of its inaugural Green Bond from re...

Categories:
  • Business & Finance
Posted: 6 months ago
Posted: 6 months ago

Kriegers Flak CGS Commissioning Rescheduled

The commissioning of the Kriegers Flak Combined Grid Solution (CGS) between Germany and Denmark has ...

Categories:
  • Grid Connection
Posted: 6 months ago