707 results found for 'Dudgeon'

707 results found for 'Dudgeon'
Order results by

A list of search results

  • 3 June 2016
    Grid Connection, Vessels, Wind Farm Update

    Installation works on the 402MW Dudgeon offshore wind farm are progressing according to plan and the project is halfway to being completed, according to Dudgeon Offshore Windfarm Limited (DOWL). The wind farm’s export cables were laid and the jacket for the offshore substation was installed in May. The crane vessel Oleg Strashnov has installed half of […]

  • 11 May 2012
    Grid Connection

    Dudgeon Offshore Wind Limited (DOW), a subsidiary of Warwick Energy Limited, has selected ABB Limited (ABB) as the preferred supplier for the delivery of the electrical works for the Dudgeon Offshore Wind Farm (Dudgeon) project following a competitive tendering exercise. The formal contract for these services in not expected to be signed until 2013, dependent […]

  • 26 March 2015
    Grid Connection, Wind Farm Update

    Work has commenced in Norfolk to install the underground cables and construct the substations that will enable electricity produced by the Dudgeon Offshore Wind Farm to be distributed into the UK National Grid electricity network. Two underground cables will run from Weybourne on the North Norfolk coast to Necton, near Swaffham where the new electricity […]

  • 15 July 2016

    Dudgeon offshore wind farm’s substation topside is getting ready to sail, according to Siemens’ social media pages.  The four-deck topside has been built by Sembmarine SLP, and will go through weighing and load out this month before it sails away from the yard  in August. The jacket for the substation was also built by Sembmarine and loaded onto […]

  • 21 November 2017
    Wind Farm Update

    Statoil, Masdar and Statkraft are ready to officially open their Dudgeon offshore wind farm in the UK tomorrow, 22 November.

  • 24 September 2014
    Authorities, Business & Finance, Wind Farm Update

    Abu Dhabi-owned green energy giant Masdar has confirmed that it will invest £525 million for a 35% stake in the planned Dudgeon offshore wind farm, alongside Norweigan partners Statoil and Stakraft. Earlier this summer, the Dudgeon project passed a final investment decision. In conjunction with this a new partner acquired a 35 percent stake from […]

  • 8 September 2021
    Operations & Maintenance, Wind Farm Update

    Equinor will combine operations of the Dudgeon and Sheringham Shoal offshore wind farms off the Norfolk coast into one hub in Great Yarmouth. The Sheringham Shoal and Dudgeon offshore wind farms are currently operated from separate bases in Egmere and Great Yarmouth, respectively.  The new setup will be in place by the end of September […]

  • 5 June 2016

    Timelapse: Dudgeon Foundation Eased Into Place Statoil has shared a timelapse video of one of 67 foundations for the 402MW Dudgeon offshore wind farm being installed in the UK part of the North Sea. Sandbank Partners Streamlining Turbine Installation Process Vattenfall and Stadtwerke München (SWM), together with project partner Siemens, have developed an optimised concept […]

  • 17 January 2012

    North Norfolk District Council (NNDC) rejected plans to place offshore wind farm power cables throughout the countryside, reports BBC. The 45km onshore cable running between the landfall point at Weybourne Hope (North Norfolk District) and Little Dunham (Breckland District) would connect the Dudgeon offshore wind farm to the grid. Even though Development Committee stated in […]

  • 4 July 2014

    The Dudgeon Wind Farm Limited has awarded the contract for the Monopile Foundation Fabrication for its Dudgeon Offshore Wind Farm to Sif Group B.V. The contract covers the procurement, fabrication and assembly of 67 monopiles (MPs) and 67 transition pieces (TPs), including transportation to the Dudgeon Offshore Wind Farm storage site from where the monopile […]

  • 29 August 2017
    Vessels, Wind Farm Update

    A2SEA’s wind turbine installation vessel Sea Challenger has loaded the final set of wind turbine components for the 402MW Dudgeon offshore wind farm project at the Port of Hull.

  • 5 January 2017
    Vessels, Wind Farm Update

    A2SEA’s wind farm installation vessel Sea Challenger is preparing to sail out of the port of Hull with the first load of turbine components to be installed at the 402MW Dudgeon offshore wind farm. Sea Challenger was loaded with components of four Siemens 6MW turbines on Wednesday, 4 January. The vessel will make 17 runs […]

  • 8 November 2018
    Authorities, Contracts & Tenders, Grid Connection, Operations & Maintenance, Wind Farm Update

    Ofgem has granted a licence to TC Dudgeon OFTO plc to own and operate the GBP 297.9 million high-voltage transmission link to the Dudgeon offshore wind farm for the next 20 years.

  • 19 June 2014
    Wind Farm Update

    During the 2014 summer months, Dudgeon Offshore Wind will start to prepare the site at Necton in readiness for the construction of the electricity substation needed for this important renewable energy project.   There will be a Dudgeon Offshore Wind public drop-in exhibition at Necton Village Hall on Tuns Road, Necton, Norfolk on Wednesday 25th […]

  • 9 January 2017
    Vessels, Wind Farm Update

    A2SEA’s wind farm installation vessel Sea Challenger has installed the first turbine on the 402MW Dudgeon offshore wind farm situated some 32 kilometres off North Norfolk, UK. The first out of the 67 Siemens 6MW turbines was installed on Saturday, 7 January. For the next months, the vessel will install the turbines being shipped from […]

  • 26 June 2012
    Grid Connection

    Dudgeon Offshore Wind Limited (DOW), a subsidiary of Warwick Energy Limited, has received the planning permissions needed to construct and operate the onshore cables for the proposed Dudgeon Offshore Wind Farm (Dudgeon) project. The permission received from the Planning Inspectorate covers the northern 28km section of the buried cable system needed to allow the electricity […]

  • 20 May 2015
    Grid Connection, Wind Farm Update

    The approval for Dudgeon in meeting the milestone requirements was confirmed by the Low Carbon Contracts Company (LCCC), the designated independent Counterparty to CFDs, last week. Dudgeon issued the milestone requirement notice on 7th May 2015, two days ahead of schedule. “This milestone fulfillment is very good news for the project, and it confirms that […]

  • 19 December 2014
    Business & Finance, Operations & Maintenance, Vessels, Wind Farm Update

    Dudgeon Offshore Wind Limited has awarded a 5 year contract for the Service Operation Vessel to Esvagt AS.  The contracted Service Operation Vessel (SOV) for Dudgeon wind farm is of the Havyard-832 design with a length of 83.7 meters and a width of 17.6 meters. The SOV is a DP-2 Class operated vessel, accommodating 60 persons […]

  • 5 August 2014
    Business & Finance

    On July 3, Smulders Projects was awarded the contract for the supply of 67 Transition Pieces for the Dudgeon Offshore Wind Farm.  The Dudgeon Offshore Windfarm will be constructed on the coast of Norfolk, South East England. The wind farm comprises 67 monopile foundations on which 6 MW turbines will be placed. This large capacity […]

  • 5 September 2017
    Vessels, Wind Farm Update

    A2SEA’s wind turbine installation vessel Sea Challenger has installed the last of the 67 Siemens 6MW wind turbines on the 402MW Dudgeon offshore wind farm.

  • 27 April 2015
    Business & Finance

    Sembmarine SLP has awarded a contract to Manchester-based Granada Material Handling Ltd (GMH) to manufacture, deliver and commission two davit crane units for Siemens’ Transmission and Distribution Platform at the Dudgeon offshore wind farm. Each of the Granada ‘Python’ crane units have been specifically designed for the Dudgeon offshore wind farm and the challenging marine environment […]

  • 3 September 2014
    Grid Connection

    Dudgeon Offshore Wind Limited has awarded the contract for the Electrical System Infrastructure for its Dudgeon Offshore Wind Farm to Siemens Transmission and Distribution Ltd. The contract covers engineering, procurement, construction and offshore hook-up of one onshore substation and one offshore substation including jacket foundation. Siemens will have the overall system responsibility to connect the […]

  • 13 December 2018
    Business & Finance, Wind Farm Update

    Equinor, Masdar and China Resources Group, the owners of the Dudgeon wind farm, have signed a hybrid refinancing of GBP 1.4 billion (EUR 1.55 billion).

  • 19 April 2016
    Environment, R&D, Technology, Wind Farm Update

    Statoil has selected Partrac to provide real-time wave and current measurement services for the 402MW Dudgeon offshore wind farm. Partrac has been contracted to manage the deployment and maintenance of the equipment and the delivery of real-time waves and current data over the duration of the construction phase of the development. Partrac selected a Triaxys […]

  • 3 July 2014
    Grid Connection

    VSMC has been awarded a EUR 110 million contract by Dudgeon Offshore Wind Limited, owned by Norwegian companies Statoil and Statkraft, for the export and inter-array cabling for the Dudgeon Offshore Wind Farm. VSMC will start in 2015 by performing two 1,100-metre horizontal directional drillings at the landfall, followed by the installation of two 42-km […]

  • 1 July 2014
    Wind Farm Update

    Statoil and Statkraft have decided to start building the Dudgeon offshore wind farm off the coast of Norfolk, UK. The project aims for full production in late 2017. When completed, Dudgeon will provide renewable energy for up to 410,000 households in the UK. The Dudgeon development will now move into a new phase, starting with […]