Search results for: Dudgeon

282 results

A list of search results

  • 9 July 2013
    Wind Farm Update

    Dudgeon Offshore Wind Limited, the developer of the  Dudgeon Offshore Wind Farm, has announced on its official website that a public exhibition for the North Norfolk Coastal Communities regarding its project will be held from noon to 7:00 pm on 10th July, at Merchants’ Place in Church Street, Cromer. The Dudgeon Offshore Wind team will […]

  • 28 June 2016
    Vessels

    Esvagt plans to deliver its Service Operation Vessel (SOV) for the Dudgeon offshore wind farm ahead of schedule, the company reported in its newsletter.  The company has made an agreement with Havyard Ship Technology in Leirvik to speed up the process and have the vessel ready a week earlier than initially planned. Given that the shipyard has already been […]

  • 22 November 2017
    Wind Farm Update

    Statoil, Masdar and Statkraft officially opened the 402MW Dudgeon offshore wind farm in Great Yarmouth, UK, on Wednesday, 22 November.

  • 24 November 2017
    Contracts & Tenders, Grid Connection, Operations & Maintenance, Wind Farm Update

    Ofgem has appointed Transmission Capital Partners as the preferred bidder to own and operate the high-voltage transmission link to the Dudgeon offshore wind farm for the next 20 years.

  • 20 October 2014
    Grid Connection

    Sembmarine SLP Limited (SLP), which is 70% owned by Sembcorp Marine, was awarded a contract to design and build the offshore substation platform for the Dudgeon Offshore Wind Farm. The contract was granted by Siemens Transmission & Distribution Limited, which was awarded the contract for the Electrical System Infrastructure by the wind farm’s developer Dudgeon […]

  • 8 August 2016
    Grid Connection, Vessels, Wind Farm Update

    Seaway Heavy Lifting (SHL) has completed its work on the 402MW Dudgeon offshore wind farm by installing the topside for the wind farm’s offshore substation on Sunday, 7 August. SHL utilised its crane vessel Oleg Strashnov to install the topside. Prior to that, Oleg Strashnov installed the wind farm’s 67 turbine foundations, while Stanislav Yudin […]

  • 11 May 2012
    Grid Connection

    Dudgeon Offshore Wind Limited (DOW), a subsidiary of Warwick Energy Limited, has selected ABB Limited (ABB) as the preferred supplier for the delivery of the electrical works for the Dudgeon Offshore Wind Farm (Dudgeon) project following a competitive tendering exercise. The formal contract for these services in not expected to be signed until 2013, dependent […]

  • 5 September 2017
    Vessels, Wind Farm Update

    A2SEA’s wind turbine installation vessel Sea Challenger has installed the last of the 67 Siemens 6MW wind turbines on the 402MW Dudgeon offshore wind farm.

  • 5 August 2014
    Business & Finance

    On July 3, Smulders Projects was awarded the contract for the supply of 67 Transition Pieces for the Dudgeon Offshore Wind Farm.  The Dudgeon Offshore Windfarm will be constructed on the coast of Norfolk, South East England. The wind farm comprises 67 monopile foundations on which 6 MW turbines will be placed. This large capacity […]

  • 12 March 2012
    Grid Connection

    North Norfolk District Council has approved a cable corridor that would connect the Dudgeon wind farm to the national grid, reported BBC. In January, Warwick Energy’s cable corridor proposal to lay 45km onshore cable running between the landfall point at Weybourne Hope (North Norfolk District) and Little Dunham (Breckland District) was rejected by the council. […]

  • 8 April 2016
    Business & Finance, Vessels, Wind Farm Update

    Rix Sea Shuttle has won a contract to supply two crew transfer vessels to the 402MW Dudgeon offshore wind farm, currently under construction off the coast of Norfolk. The contract, with Norwegian oil-major Statoil, will see the vessels the Rix Leopard and Rix Lion carry technicians to and from the Dudgeon situated around 20 miles offshore from Cromer. The value […]

  • 16 September 2016

    Boston Energy will support Siemens’ pre-assembly works for the 6MW Dudgeon offshore wind project at Alexandra Dock in Hull. Technicians from Boston Energy will commence operations on site from October 2016, backing the Siemens team on the dockside at Hull Pre-Assembly site. Adrian Yeaman, Operations Manager of Boston Energy, said: “It’s great news to be involved in the Pre-Assembly project […]

  • 8 November 2018
    Authorities, Contracts & Tenders, Grid Connection, Operations & Maintenance, Wind Farm Update

    Ofgem has granted a licence to TC Dudgeon OFTO plc to own and operate the GBP 297.9 million high-voltage transmission link to the Dudgeon offshore wind farm for the next 20 years.

  • 14 January 2014
    Technology, Wind Farm Update

    Statoil has awarded two contracts to Siemens plc for the engineering, supply, assembly, commissioning and service of 67 wind turbine generators for the Dudgeon Offshore Wind Farm project. The wind turbine generator (WTG) supply contract will cover engineering, procurement, assembly and offshore commissioning. Each turbine (6.0 MW) consists of a tower section, a nacelle and […]

  • 15 August 2016
    Grid Connection, Vessels, Wind Farm Update

    Statoil has shared a timelapse video of a heavy lift vessel Oleg Strashnov installing a 1,700-tonne topside onto a jacket on Dudgeon bank off Norfolk, UK. The topside and the jacket were built by Sembmarine SLP in Lowestoft and now form an offshore substation which once commissioned will collect and transform power generated at the 402MW Dudgeon offshore wind farm. The topside was […]

  • 19 June 2014
    Wind Farm Update

    During the 2014 summer months, Dudgeon Offshore Wind will start to prepare the site at Necton in readiness for the construction of the electricity substation needed for this important renewable energy project.   There will be a Dudgeon Offshore Wind public drop-in exhibition at Necton Village Hall on Tuns Road, Necton, Norfolk on Wednesday 25th […]

  • 9 January 2017
    Vessels, Wind Farm Update

    A2SEA’s wind farm installation vessel Sea Challenger has installed the first turbine on the 402MW Dudgeon offshore wind farm situated some 32 kilometres off North Norfolk, UK. The first out of the 67 Siemens 6MW turbines was installed on Saturday, 7 January. For the next months, the vessel will install the turbines being shipped from […]

  • 8 December 2014

    In August Dudgeon Offshore Wind Limited, a joint venture of Statoil and Statkraft, announced it had awarded a contract to Siemens for the supply of 67 turbines for their 402MW Dudgeon Offshore Wind Farm. Siemens will be providing their SWT-6.0-1 54 6MW turbine. This was soon after followed by thecontract for the grid connection. Siemens […]

  • 15 February 2018
    Business & Finance, Wind Farm Update

    Statkraft is expecting to close the divestment in the Dudgeon offshore wind farm in the first quarter of 2018, after which the company will have terminated its offshore wind engagement.

  • 5 June 2016

    Timelapse: Dudgeon Foundation Eased Into Place Statoil has shared a timelapse video of one of 67 foundations for the 402MW Dudgeon offshore wind farm being installed in the UK part of the North Sea. Sandbank Partners Streamlining Turbine Installation Process Vattenfall and Stadtwerke München (SWM), together with project partner Siemens, have developed an optimised concept […]

  • 4 January 2018
    Wind Farm Update

    The 402MW Dudgeon offshore wind farm, comprising 67 Siemens 6MW wind turbines installed off the coast of Norfolk in England, achieved a production of 1TWh during offshore installation and commissioning in 2017.

  • 19 December 2017
    Business & Finance, Wind Farm Update

    Statkraft has now divested all holdings in offshore wind with its stake in the Dudgeon offshore wind farm being acquired by a consortium led by China Resources (Holdings) Company Limited, who will buy Statkraft-owned 30% for GBP 555 million.

  • 19 December 2014
    Business & Finance, Operations & Maintenance, Vessels, Wind Farm Update

    Dudgeon Offshore Wind Limited has awarded a 5 year contract for the Service Operation Vessel to Esvagt AS.  The contracted Service Operation Vessel (SOV) for Dudgeon wind farm is of the Havyard-832 design with a length of 83.7 meters and a width of 17.6 meters. The SOV is a DP-2 Class operated vessel, accommodating 60 persons […]

  • 20 May 2015
    Grid Connection, Wind Farm Update

    The approval for Dudgeon in meeting the milestone requirements was confirmed by the Low Carbon Contracts Company (LCCC), the designated independent Counterparty to CFDs, last week. Dudgeon issued the milestone requirement notice on 7th May 2015, two days ahead of schedule. “This milestone fulfillment is very good news for the project, and it confirms that […]

  • 21 August 2014
    Business & Finance, Technology, Wind Farm Update

    Siemens Energy has received an order from the Norwegian energy utilities Statoil and Statkraft for the Dudgeon Offshore Wind Farm in the UK. Siemens will manufacture, deliver, install and commission 67 Siemens direct-drive wind turbines rated at 6 megawatts (MW) each and equipped with a 154-meter rotor. Installation will start in early 2017. The combined […]

  • 21 November 2013
    Operations & Maintenance, Wind Farm Update

    Dudgeon Offshore Wind Ltd has decided to go further with Great Yarmouth as the preferred harbour location for the operation and maintenance activities for the Dudgeon Offshore Wind Farm. Operations and maintenance of the wind farm will be performed by technicians taken to site either by smaller vessels on a daily basis or using a […]