Search results for: Dudgeon

686 results

A list of search results

  • 14 January 2014
    Technology, Wind Farm Update

    Statoil has awarded two contracts to Siemens plc for the engineering, supply, assembly, commissioning and service of 67 wind turbine generators for the Dudgeon Offshore Wind Farm project. The wind turbine generator (WTG) supply contract will cover engineering, procurement, assembly and offshore commissioning. Each turbine (6.0 MW) consists of a tower section, a nacelle and […]

  • 15 August 2016
    Grid Connection, Vessels, Wind Farm Update

    Statoil has shared a timelapse video of a heavy lift vessel Oleg Strashnov installing a 1,700-tonne topside onto a jacket on Dudgeon bank off Norfolk, UK. The topside and the jacket were built by Sembmarine SLP in Lowestoft and now form an offshore substation which once commissioned will collect and transform power generated at the 402MW Dudgeon offshore wind farm. The topside was […]

  • 21 August 2014
    Business & Finance, Technology, Wind Farm Update

    Siemens Energy has received an order from the Norwegian energy utilities Statoil and Statkraft for the Dudgeon Offshore Wind Farm in the UK. Siemens will manufacture, deliver, install and commission 67 Siemens direct-drive wind turbines rated at 6 megawatts (MW) each and equipped with a 154-meter rotor. Installation will start in early 2017. The combined […]

  • 11 July 2016

    Offshore WIND’s photo of the day: Seaway Heavy Lifting’s Oleg Strashnov carrying monopiles and transition pieces to the Dudgeon offshore wind site.  The photo was taken by the Superintendent of the Oleg Strashnov, during works at the Dudgeon offshore wind farm in the UK. The first foundations at the wind farm site were installed in early April and […]

  • 26 June 2012
    Grid Connection

    Dudgeon Offshore Wind Limited (DOW), a subsidiary of Warwick Energy Limited, has received the planning permissions needed to construct and operate the onshore cables for the proposed Dudgeon Offshore Wind Farm (Dudgeon) project. The permission received from the Planning Inspectorate covers the northern 28km section of the buried cable system needed to allow the electricity […]

  • 1 October 2012
    Authorities, Grid Connection

    Dudgeon Offshore Wind Limited (DOW), a subsidiary of Warwick Energy Limited, has today received planning permission from Breckland Council to build and operate an onshore substation near Necton, Norfolk, together with an associated buried cable route spur. The substation is needed to connect the Dudgeon Offshore Wind Farm (Dudgeon) project to the national electrical transmission […]

  • 22 November 2017
    Wind Farm Update

    Statoil, Masdar and Statkraft officially opened the 402MW Dudgeon offshore wind farm in Great Yarmouth, UK, on Wednesday, 22 November.

  • 24 September 2014
    Authorities, Business & Finance, Wind Farm Update

    Abu Dhabi-owned green energy giant Masdar has confirmed that it will invest £525 million for a 35% stake in the planned Dudgeon offshore wind farm, alongside Norweigan partners Statoil and Stakraft. Earlier this summer, the Dudgeon project passed a final investment decision. In conjunction with this a new partner acquired a 35 percent stake from […]

  • 4 July 2014

    The Dudgeon Wind Farm Limited has awarded the contract for the Monopile Foundation Fabrication for its Dudgeon Offshore Wind Farm to Sif Group B.V. The contract covers the procurement, fabrication and assembly of 67 monopiles (MPs) and 67 transition pieces (TPs), including transportation to the Dudgeon Offshore Wind Farm storage site from where the monopile […]

  • 5 August 2014
    Business & Finance

    On July 3, Smulders Projects was awarded the contract for the supply of 67 Transition Pieces for the Dudgeon Offshore Wind Farm.  The Dudgeon Offshore Windfarm will be constructed on the coast of Norfolk, South East England. The wind farm comprises 67 monopile foundations on which 6 MW turbines will be placed. This large capacity […]

  • 7 September 2017
    Operations & Maintenance, Wind Farm Update

    All 67 Siemens 6MW turbines on the 402MW Dudgeon wind farm off Norfolk are now producing electricity, according to Statoil, the operator and part owner of the offshore wind farm.

  • 17 January 2012

    North Norfolk District Council (NNDC) rejected plans to place offshore wind farm power cables throughout the countryside, reports BBC. The 45km onshore cable running between the landfall point at Weybourne Hope (North Norfolk District) and Little Dunham (Breckland District) would connect the Dudgeon offshore wind farm to the grid. Even though Development Committee stated in […]

  • 3 July 2014
    Grid Connection

    VSMC has been awarded a EUR 110 million contract by Dudgeon Offshore Wind Limited, owned by Norwegian companies Statoil and Statkraft, for the export and inter-array cabling for the Dudgeon Offshore Wind Farm. VSMC will start in 2015 by performing two 1,100-metre horizontal directional drillings at the landfall, followed by the installation of two 42-km […]

  • 19 June 2014
    Wind Farm Update

    During the 2014 summer months, Dudgeon Offshore Wind will start to prepare the site at Necton in readiness for the construction of the electricity substation needed for this important renewable energy project.   There will be a Dudgeon Offshore Wind public drop-in exhibition at Necton Village Hall on Tuns Road, Necton, Norfolk on Wednesday 25th […]

  • 15 July 2016

    Dudgeon offshore wind farm’s substation topside is getting ready to sail, according to Siemens’ social media pages.  The four-deck topside has been built by Sembmarine SLP, and will go through weighing and load out this month before it sails away from the yard  in August. The jacket for the substation was also built by Sembmarine and loaded onto […]

  • 5 August 2016
    Grid Connection, Wind Farm Update

    The 1,700-ton topside built by Sembmarine SLP for the offshore substation of the 402MW Dudgeon offshore wind farm has sailed out of the port of Lowestoft, UK. The four-deck topside will be installed on a 1,500-tonne steel jacket which was put in place some 32 kilometres off Cromer, Norfolk, at the beginning of June. The jacket structure […]

  • 5 April 2016
    Wind Farm Update

    The crane vessel Oleg Strashnov has installed the first monopile at the Dudgeon offshore wind farm, located off Norfolk, England. “Our team and suppliers have worked hard to prepare for the exciting installation phase and we are pleased to progress according to plan,” said Olav-Bernt Haga, project director for the Dudgeon project. In total, 67 turbines, as well […]

  • 9 February 2017
    Grid Connection, Wind Farm Update

    Up to 6,000 homes in UK are now receiving electricity from the first producing wind turbine on the 402MW Dudgeon offshore wind farm, Statoil reports.

  • 21 April 2015
    Jobs & Recruitment, Operations & Maintenance, Wind Farm Update

    The first seven employment opportunities for managers and engineers to be based from the Dudgeon Offshore Wind Farm O&M base in Great Yarmouth, Norfolk have been posted on the Statoil website, Statoil being the operator for both the construction and operational phases of this 402MW offshore power plant. To date, the O&M team has consisted […]

  • 19 December 2014
    Business & Finance, Operations & Maintenance, Vessels, Wind Farm Update

    Dudgeon Offshore Wind Limited has awarded a 5 year contract for the Service Operation Vessel to Esvagt AS.  The contracted Service Operation Vessel (SOV) for Dudgeon wind farm is of the Havyard-832 design with a length of 83.7 meters and a width of 17.6 meters. The SOV is a DP-2 Class operated vessel, accommodating 60 persons […]

  • 8 December 2014

    In August Dudgeon Offshore Wind Limited, a joint venture of Statoil and Statkraft, announced it had awarded a contract to Siemens for the supply of 67 turbines for their 402MW Dudgeon Offshore Wind Farm. Siemens will be providing their SWT-6.0-1 54 6MW turbine. This was soon after followed by thecontract for the grid connection. Siemens […]

  • 15 February 2018
    Business & Finance, Wind Farm Update

    Statkraft is expecting to close the divestment in the Dudgeon offshore wind farm in the first quarter of 2018, after which the company will have terminated its offshore wind engagement.

  • 19 April 2016
    Environment, R&D, Technology, Wind Farm Update

    Statoil has selected Partrac to provide real-time wave and current measurement services for the 402MW Dudgeon offshore wind farm. Partrac has been contracted to manage the deployment and maintenance of the equipment and the delivery of real-time waves and current data over the duration of the construction phase of the development. Partrac selected a Triaxys […]

  • 1 July 2014
    Wind Farm Update

    Statoil and Statkraft have decided to start building the Dudgeon offshore wind farm off the coast of Norfolk, UK. The project aims for full production in late 2017. When completed, Dudgeon will provide renewable energy for up to 410,000 households in the UK. The Dudgeon development will now move into a new phase, starting with […]

  • 8 November 2018
    Authorities, Contracts & Tenders, Grid Connection, Operations & Maintenance, Wind Farm Update

    Ofgem has granted a licence to TC Dudgeon OFTO plc to own and operate the GBP 297.9 million high-voltage transmission link to the Dudgeon offshore wind farm for the next 20 years.

  • 6 July 2012
    Wind Farm Update

    Dudgeon Offshore Wind Limited (DOW), a subsidiary of Warwick Energy Limited, has today received all necessary consents required to build and operate the offshore works needed for the Dudgeon Offshore Wind Farm (Dudgeon) project.  The consents were issued by the Department of Energy and Climate Change, under section 36 of the Electricity Act 1990, in […]