Innovative Yoke for Safe Wind Turbine Blade Lifting

Most mechanical constructions that are 14 meters long, 8 meters tall and weigh 78 metric tons are not described as fast or flexible. Especially when the thing it lifts is 75 meters long and weighs 25 metric tons.

Then again, the new B75 lifting yoke from the Siemens Wind Power Division is no average construction. And Siemens is taking out the patents to prove it.

As wind turbines develop – and especially grow in size – new equipment related to all aspects of them also need to be developed. Whether in design, manufacturing, transportation or installation, safety must come first, with quality and cost-efficiency following. Meeting these requirements when related to installing 75 meter rotor blades when out to sea at the same time clearly required a new solution.

For large-scale installations of these enormous wind turbine blades, the R&D team at the Wind Power Division identified this need years ago.

“Rotor blades are installed on what are known as hubs to form a rotor. The rotor is itself attached to the nacelle, the large section of the turbine at the top of the tower. This takes place at heights often between 60 – 90 meters, depending on the prevalent wind resources. There are two ways to install them: in a single-blade lift, meaning one at a time onto the hub which has already been installed on the nacelle, or in a full rotor lift, where the three blades and hub have been preassembled on the ground,” informs Kenneth Helligsø Svinth, who headed the project. He continues:

“Each method has its pros and cons. For the large-scale installations of our 75-meter blades, it was decided to develop a new single-blade installation tool. The size of the blade, along with the challenges of aligning the hub of the SWT-6.0 nacelle, made this the better solution.”

Innovative Yoke for Safer Wind Turbine Blade Lifting (2)Three patent applications submitted

It will be the world’s largest lifting yoke for offshore installation of a series-produced wind turbine. It can install blades in winds of up to 14 meters per second, and is fully automatic. Three patent applications have been submitted.

Recently the Siemens Wind Power project team for the Westermost Rough offshore wind power project, customer DONG Energy and installation vessel crew from partner A2SEA received an introduction to the lifting yoke. Mounted on a crane in Østerild, Denmark, functions were demonstrated and lifts were performed.

Automatic sling connection

In traditional single-blade lifts, a crane lifts the blade hanging from secured slings. A great deal of manual work is required to attach and release the slings, some of it needing to take place at heights far above the ground or surface of the water.

A key function of the B75 lifting yoke is the automatic sling connection. This ensures that no technician is working at heights doing the rigging or operation of the yoke. Remotely controlled, a highly-trained Siemens yoke operator does so from the safety of the deck of the installation vessel. Furthermore, a reduction of shackles where possible was also implemented to avoid manual handling.

Flexibility in focus

The active yaw function allows adjustments at height that are not possible with existing single-blade lifting solutions. Flexibility is indeed in focus in the B75 lifting yoke. Numerous adjustment functions have been integrated, according to Moeller.

“We are able to actively tilt and pitch the blade several degrees, as well as turn, or yaw it, as we say, allowing us to make adjustments at height that simply are not possible with existing single-blade lifting solutions. This new yaw feature will allow us to keep full tension in the taglines connected to the crane boom while we simultaneously instruct the crane operator to yaw the crane for positioning the blade. We can easily adjust the alignment between the hub and blade without needing to adjust tagline tension. This allows us to install blades more safely and efficiently, the latter which helps us reach our goal of lowering the cost of wind energy,” he states.

The B75 lifting yoke will be employed during the installation of the 210 MW Westermost Rough offshore wind power plant in the UK beginning in summer 2014. A total of 35 Siemens SWT-6.0-154 wind turbines with 105 B75 rotor blades will be installed. This is the first offshore installation of the 75-meter blades on the Siemens 6 MW machine.

“It has been very important for me during the development of this yoke that we have taken all the lessons learned from the previous yoke into consideration. Also, a key stakeholder during development was a ‘super user operator’ from the existing yoke solution. In that way, we ensured that the technicians receive a tool that they can operate safely and effectively in the field from Day One,” Svinth concludes.

 

Press Release, June 26, 2014; Image: siemens

 

Share this article

Follow Offshore Wind

Leave a Reply

Events>

<< May 2017 >>
MTWTFSS
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31 1 2 3 4

6th ANNUAL ADVANCED SUBMARINE POWER CABLE AND INTERCONNECTION FORUM

The event will cover such topics as:
* FAB Link Interconnector – Development Update…

read more >

2nd ANNUAL OFFSHORE WIND OPERATIONS AND MAINTENANCE FORUM

The Forum will give the full update on the O&M effective practices and their perspectives, providing industry developers new tools…

read more >

International Conference Wind Farm Lifecycle Management

The only networking event discussing aging of turbines and related lifecycle strategies!…

read more >

Nacelle Engineering: Wind Energy Power Conversion Summit 2017

Innovation of nacelle components is the very key to the reduction of LCoE and thus to make wind energy competitive…

read more >

Jobs>

Project Manager Shiprepair Dunkerque

The project departments within the Damen Shiprepair & Conversion yards are managed by a Head of Projects or directly by the MD of the yard ...

apply

Network Support Engineer

As Network Support Engineer you will be responsible for the installation / configuration, operation and maintenance of the infrastructural network ...

apply

Offshore wind jobs at Shell Netherlands BV

Commercial Lead New Energies, Offshore Wind Operations Lead and Wind Turbine Engineer.

apply

Vessels>