Tokyo-based JFE Engineering Corporation has produced what it says is Japan’s first domestically manufactured monopile for an offshore wind farm. The monopile is destined for the 315 MW Oga–Katagami–Akita project, owned by a consortium consisting of JERA Nex BP, Electric Power Development (J-POWER),

Taiwan’s Energy Administration is processing the termination of the administrative contract for the 700 MW Youde offshore wind project, developed by Shinfox Energy. According to Taiwan’s Central News Agency (CNA), the Energy Administration confirmed on 24 August that the developer had not completed

Tokyo Electric Power Company Renewable Power (TEPCO RP) has begun the environmental assessment process for a planned offshore wind farm of up to 420 MW off Choshi, Chiba Prefecture, one of the areas included in Japan’s first fixed-bottom offshore wind auction round, which was originally secured by a

The State Government of Victoria has launched Australia’s first offshore wind auction, opening a Request for Proposal (RFP) process for the state’s first 2 GW of offshore wind capacity. Developers can now bid for contracts for projects off the Gippsland coast, with projects to be assessed on value f

Norwegian company Glamox has secured a contract to supply marine lighting for 35 wind turbine foundations at the Formosa 4 offshore wind farm in Taiwan. The company will provide more than 900 marine luminaires for the transition pieces of the turbines under an agreement with ProCon Taiwan and SK oce

Ørsted, on behalf of the joint venture with PGE Polska Grupa Energetyczna, which is building the 1.5 GW Baltica 2 offshore wind farm in the Polish Baltic Sea, has selected Northern Helicopter for the provision of medevac services during the project’s construction. The contract, valued at a little ov

The Norwegian Ministry of Energy has granted Ventyr, a consortium of JERA Nex BP and Ingka Investments, a twelve-month extension of the deadline for submitting a license application for the Sørlige Nordsjø II (Southern North Sea II) project, Norway’s first commercial offshore wind farm. Ventyr submi

A fire was reported on a wind turbine at Ørsted’s Greater Changhua 4 offshore wind farm in Taiwan on 8 August after the turbine’s system detected an abnormal condition and automatically stopped its operation. Ørsted said the wind farm team observed the fire shortly after the automatic trip and ext

Jan De Nul has installed all 23 foundation elements for the Princess Elisabeth Island, the world’s first artificial energy island, being built 45 kilometres off the Belgian coast. The project is now entering the next phase of construction, according to the company. Developed by Belgium grid operator

Van Oord has completed the installation of all 111 monopile foundations at the 1.5 GW Baltica 2 offshore wind farm in the Polish Baltic Sea. The foundation installation campaign, which started in May, covered 107 monopiles for the project’s wind turbines and four foundations for the offshore substat

Danish utility SONFOR is seeking a new partner to take the project forward at the 165 MW Lillebælt Syd offshore wind farm after TotalEnergies decided to withdraw from the development. SONFOR is taking over the majority stake in Lillebælt Vind A/S, the company behind the project, and will use the com

Ørsted expects three of its offshore wind farms currently under construction to reach full commissioning in the second half of 2026, with Borkum Riffgrund 3 in Germany, Greater Changhua 2b and 4 in Taiwan, and Revolution Wind in the US all approaching completion. The updates were provided by Ørsted

Pacifico Energy Korea has been selected as the sole developer of the 2.13 GW Jindo Offshore Wind Integrated Cluster Phase 2 in South Korea, the US-based renewable energy company said on 20 August. The cluster will comprise Pacifico’s Manho and Jindo Baram offshore wind projects. The selection follow

Sif has loaded out the final monopiles for Bałtyk 2 and 3 offshore wind farms, currently under construction in the Polish sector of the Baltic Sea. Located approximately 37 and 22 kilometres from the coastline near Ustka and Łeba, the two sites will together comprise 100 Siemens Gamesa SG 14-236 DD