495 results found for 'Hornsea Project Two'

495 results found for 'Hornsea Project Two'
Order results by

A list of search results

  • 4 December 2017
    Contracts & Tenders, Wind Farm Update

    Ørsted has hired Semco Maritime as Electrical Engineering Consultant (EEC) to develop electrical and mechanical basic engineering design of the 1.4GW offshore substation and the reactive compensation station for Hornsea Project Two.

  • 4 May 2018
    Authorities, Grid Connection, Wind Farm Update

    The UK Secretary of State for Business, Energy and Industrial Strategy (BEIS) has approved Ørsted’s application to reduce the number of offshore substations and increase the size of the topsides on the Hornsea Project Two offshore wind project.

  • 10 May 2019
    Business & Finance

    Ørsted has secured nominal GBP 900 million through the issuance of green senior bonds, to finance its green growth ambition towards 2025 including the investment in the 1,386MW Hornsea Project Two offshore wind farm in the United Kingdom. Ørsted has completed the pricing of new unsecured green senior bonds comprising a GBP 350 million fixed-rate […]

  • 19 October 2018
    Authorities, Contracts & Tenders, Wind Farm Update

    The three offshore wind projects selected in the UK’s second Contracts for Difference (CfD) allocation round have passed their 12-month milestone requirement, Low Carbon Contracts Company (LCCC) said.

  • 28 March 2018
    Authorities, Environment, Grid Connection, Wind Farm Update

    UK governmental agencies, conservation organisations and companies have responded positively to Ørsted’s application to reduce the number of offshore substations and increase the size of the topsides on the Hornsea Project Two offshore wind project.

  • 5 December 2018

    Semco Maritime and ISC Consulting Engineers have completed the design of the offshore substation and the Reactive Compensation Station (RCS) for the Hornsea Project Two offshore wind farm.

  • 12 September 2018
    Business & Finance

    Ørsted is holding a supply chain event for the Hornsea Project Two offshore wind project in the UK North Sea.

  • 4 May 2016
    Authorities, Business & Finance, Environment, Grid Connection, Wind Farm Update

    DONG Energy is starting consultation as part of the planning process for the Hornsea Project Three offshore wind farm, which has a maximum capacity of 2.4 GW. Hornsea Project Three is now seeking to enter the planning process, with a consent application expected to be submitted in 2018. If this is successful, construction of the […]

  • 6 July 2018
    Wind Farm Update

    Fugro has commenced marine site characterisation work at the Hornsea Project Two offshore wind farm site under a contract with Ørsted for geotechnical site investigation, which follows earlier contracts for geophysical investigation services at the site.

  • 31 December 2019
    Contracts & Tenders, Jobs & Recruitment

    EEW Offshore Structures Britain (EEW OSB) has appointed the UK-based professional personnel leasing specialist RTS Wind Recruitment as the main supplier. RTS has partnered with EEW-OSB for a number of years throughout the Hornsea Project One and has recruited for various different positions all working towards the completion of the transition pieces. The next project […]

  • 1 October 2018
    Business & Finance, Grid Connection, Wind Farm Update

    Ørsted has awarded the South Korean LS Cable & System with a contract to supply the onshore cable for the Hornsea Project Two offshore wind farm.

  • 15 February 2018
    Authorities, Business & Finance, Grid Connection, Wind Farm Update

    Ørsted has sent an application to the UK’s Planning Inspectorate to reduce the maximum number of offshore HVAC collector substations permitted under the Hornsea Project Two Development Consent Order (DCO).

  • 10 August 2018
    Contracts & Tenders, Grid Connection, Wind Farm Update

    The UK founded infrastructure group Balfour Beatty has secured a contract to build the onshore substation for Ørsted’s Hornsea Project Two offshore wind project on the East coast of England.

  • 20 November 2018
    Business & Finance

    Ørsted has held a supply chain event for the Hornsea Project Two offshore wind farm allowing UK companies to find out how they can get involved in the project.

  • 11 April 2018
    Contracts & Tenders, Grid Connection, Operations & Maintenance, Wind Farm Update

    Ørsted and Balfour Beatty have broken ground on the onshore substation for the Hornsea Project Two offshore wind farm. Balfour Beatty is in charge of enabling works for the wind farm’s onshore substation to ensure the site preparation is underway in good time, avoiding future schedule pressures, a spokesperson from Ørsted told OffshoreWIND. The main contract for […]

  • 16 April 2018
    Operations & Maintenance, Vessels, Wind Farm Update

    Louis Dreyfus Armateurs’ (LDA) new service operations vessel (SOV) will service Ørsted’s Hornsea Project Two offshore wind farm once delivered in 2021.

  • 17 August 2020
    Wind Farm Update

    EEW Offshore Structures Britain (EEW OSB) has loaded out its first batch of transition pieces (TPs) for the Hornsea Project Two offshore wind farm in the UK. The company will deliver 30 transition pieces for the project. Hornsea Two will comprise 165 Siemens Gamesa 8 MW turbines on monopile foundations, and an offshore substation and a reactive […]

  • 24 July 2019
    Contracts & Tenders, Grid Connection

    Seaway 7, a unit of Subsea 7, has won a contract for the installation of the inter-array grid cable system at the Hornsea Project Two offshore wind farm in the UK. In addition to the submarine cable installation works, Seaway 7 will undertake a pre-installation submarine cable route survey, perform pre-installation boulder clearance activities and […]

  • 11 July 2018
    Business & Finance, Contracts & Tenders, Wind Farm Update

    Ørsted has placed an order with EEW Special Pipe Constructions (SPC) for 165 monopiles for the 1.4GW Hornsea Project Two offshore wind farm in the UK.

  • 28 November 2019
    Training & Education

    Ørsted has partnered with safety innovators Active Training Team Ltd (ATT) to build a learning center which will serve a number of industries across the Humber, the UK. The facility, to be designed by ATT and located at MODAL’s training complex in Immingham, will start off hosting an induction day developed for the construction team […]

  • 21 August 2016

    BREAKING: USA Just Got Its First Offshore Wind Farm “The Block Island Wind Farm is now fully constructed,” Jeff Grybowski, Deepwater Wind’s CEO, informed via social media. Timelapse: Dudgeon OSS Topside Lowered into Place Statoil has shared a timelapse video of a heavy lift vessel Oleg Strashnov installing a 1,700-tonne topside onto a jacket on […]

  • 30 April 2020
    Grid Connection, Wind Farm Update

    ABB has delivered and installed three shunt reactors in the onshore substation of the Hornsea Project Two offshore wind farm in the UK. In April 2018, Ørsted and Balfour Beatty started the construction of the onshore substation in North Killingholme. The project’s 39km onshore cable route runs from Horseshoe Point, east of Tetney, to the […]

  • 20 February 2015
    Authorities, Wind Farm Update

    SMart Wind’s application for Hornsea Project Two has been accepted for examination by the UK Planning Inspectorate. The Inspectorate now has approximately three months to prepare for the examination, during which residents will be able to register to become an interested party on the application. The Hornsea 2 offshore wind project has been proposed for an area approximately 89km […]

  • 18 January 2019
    Business & Finance

    Ørsted is holding a series of community information events about the onshore cable route for the Hornsea Project Two offshore wind project in the UK. According to the Danish company, the aim of the events is that local people in North East Lincolnshire and East Lindsey find our more about the onshore cabling works for the […]

  • 17 December 2015
    Authorities, Wind Farm Update

    The UK Planning Inspectorate closed the examination period for the Hornsea Two offshore wind project yesterday. The Examining Authority now has 3 months to consider the project and make a recommendation to the Secretary of State, who will then have further 3 months to make the decision. Hornsea Project Two, located approximately 89km off the Yorkshire coast, will […]

  • 16 July 2025
    Contracts & Tenders, Fixed-Bottom, Ports & Logistics, Project Updates, Supply Chain, Wind Farm Update

    Ørsted has selected Steel River Quay on the Teesworks site on the south bank of the River Tees in the northeast of England as the construction base for the Hornsea 3 offshore wind farm. Ørsted signed a lease agreement for up to 300,000 square metres at Steel River Quay, which will be used to collect […]