207 results found for 'Horns Rev 3'

207 results found for 'Horns Rev 3'
Order results by

A list of search results

  • 31 May 2018
    Contracts & Tenders, Grid Connection, Wind Farm Update

    UK-based EDS HV Group has been appointed to act on behalf of Vattenfall at the Horns Rev 3 offshore wind project in Denmark as high voltage (HV) consultants.

  • 16 August 2018
    Ports & Logistics, Vessels, Wind Farm Update

    Eight out of 49 MHI Vestas 8.3MW wind turbines have so far been installed on Vattenfall’s Horns Rev 3 wind farm in the Danish North Sea.

  • 16 August 2015

    ABB Installs World’s Most Powerful Substation ABB has installed DolWin beta, the world’s most powerful offshore converter station in the North Sea. Vattenfall Hiring for Horns Rev 3 Installation Vattenfall, a Swedish power company, is seeking a contractor for the transport and installation of turbines at Horns Rev 3. First Gemini Foundations Grouted with MasterFlow […]

  • 3 May 2016
    Grid Connection, Wind Farm Update

    The installation works on the Horns Rev C transformer platform, the heart of the Horns Rev 3 offshore wind farm, have finished.  The components of the platform, 1,888 tonne topside and the 1,300 tonne jacket, have been lifted off the transport barges and put in place by the heavy-lifting vessel Stanislav Yudin. The works were delayed due to […]

  • 20 July 2018
    Vessels, Wind Farm Update

    The first MHI Vestas 8.3MW wind turbine has been installed on Vattenfall’s 406.7MW Horns Rev 3 wind farm in the Danish North Sea.

  • 10 August 2017
    Technology, Wind Farm Update

    GeoSea will use Houlder’s pile lifting tool on the Horns Rev 3 offshore wind farm in the Danish North Sea.

  • 8 June 2012

    Energinet is seeking a company to conduct feasibility studies, preparation of EIA report, related plan documents and draft environmental reports for offshore wind turbine project at Krieger’s Flak and Horns Rev 3. The wind farm is established at Krieger’s Flak, located in the Baltic Sea, approx. 20 km east of Mon. Landfall is expected in […]

  • 20 November 2017
    Business & Finance, Environment, Grid Connection, R&D, Technology

    VBMS and Kintech Energy Ltd. have jointly developed a resin-free hang-off solution for fixing and sealing subsea cables in offshore structures which could potentially be used on the Horns Rev 3 wind farm off Denmark. 

  • 12 July 2018
    Operations & Maintenance, Ports & Logistics

    Denmark-based marine contractor Peter Madsen Rederi A/S (PMR) has completed the construction of a new set of stone beds in the Port of Esbjerg for the load-out of turbines destined for the Horns Rev 3 offshore wind farm.

  • 1 February 2017
    Grid Connection, Technology

    UK-based unexploded ordnance (UXO) specialist Ordtek has expanded the geographic scope of its interactive online mapping service, Mine Map, to cover Danish waters. The online tool has already been used on the Horns Rev 3 and Kreigers Flak wind sites off Denmark and has helped identify three wartime mines on Horns Rev 3. The biggest […]

  • 14 March 2016
    Vessels, Wind Farm Update

    Horizon Geosciences has recently used its 200kN Seabed CPT system to complete a geotechnical site investigation for Vattenfall’s 400MW Horns Rev 3 offshore wind farm in the Danish part of the North Sea.   Horizon’s scope of work centered around turbine locations and infield cable routes. The programme of work included downhole sampling and CPT testing, seismic CPT […]

  • 12 April 2016
    Vessels, Wind Farm Update

    Blue Water Shipping (BWS) has delivered all three transformer units built for Vattenfall’s 400MW Horns Rev 3 offshore wind farm to the Port of Esbjerg. BWS is also in charge of storing the transformers, and their subsequent loading and transport to the installation site. Apart from taking care of the transformer units, the Danish transport and shipping company is acting […]

  • 7 December 2016

    A2SEA has contracted Aqualis Offshore to perform engineering consultancy services for wind turbine installation works at the Horns Rev 3 wind farm offshore Denmark. Aqualis Offshore’s London-office will provide structural site assessments at the locations where A2SEA’s SEA INSTALLER jack-up vessel will install 49 MHI Vestas 8.3MW wind turbines. “We have recently supported A2SEA and […]

  • 10 August 2015

    Vattenfall, a Swedish power company, is seeking a contractor for the transport and installation of turbines at Horns Rev 3. The scope of work, valued at around EUR 22 million, includes engineering of works, design, supply and installation of sea-fastening for all components including grillage for the blade stack, load out and the offshore transport. […]

  • 2 December 2014
    Authorities, R&D, Wind Farm Update

    The publishing of the dialogue paper on Danish offshore wind farm Kriegers Flak is slightly delayed, the Danish Energy Agency (DEA) notified on its website.  “We expect the paper to be published next week,” the DEA said. In order to ensure that potential tenderers can offer their views on these framework conditions and contribute to making […]

  • 6 June 2016
    Grid Connection, Vessels, Wind Farm Update

    Danish national transmission system operator Energinet.dk has started works to install a 33-kilometre subsea cable which will connect the offshore substation at the 400MW Horns Rev 3 offshore wind farm to the power grid on land. JD Contractor’s multipurpose offshore installation vessel Sima will install the 222kV cable from the Horns Rev C substation, to around 1,500 metres from […]

  • 21 September 2016
    Wind Farm Update

    Vattenfall has shared two videos of a WW2 mine with a 700kg explosive charge being unearthed from the seabed where Denmark’s 400MW Horns Rev 3 offshore wind farm will be constructed, and subsequently detonated. The mine had been identified during a geophysical survey of the specific area, which was conducted in 2015. The data collected was then analysed and […]

  • 9 December 2013
    Authorities, Contracts & Tenders, Wind Farm Update

    Danish Energy Agency has published the contract notice for the upcoming 400 MW Horns Rev 3 offshore wind-farm. The park, which will be able to supply the needs of some 400,000 households, is the first to be constructed as a result of the Energy Agreement of 2012. To enhance the competitiveness for bidding on the […]

  • 27 April 2014

    Dong Reviews Its Offshore Wind Plans for Germany Faced with reduced funds for German offshore wind energy, Dong Energy has been revising its plans in Germany, with a possibility of scaling them back, writes the German manager magazin online edition. Photo of the Day: Siemens’ Offshore Wind Infographic Offshore WIND’s photo of the day: Siemens’ […]

  • 24 October 2017
    Vessels, Wind Farm Update

    GeoSea’s offshore wind installation vessel Innovation has installed the second batch of monopile foundations at the Horns Rev 3 site and returned to Port of Esbjerg today to pick up the next four, a spokesperson from Vattenfall confirmed to Offshore WIND.

  • 31 January 2013
    Authorities, Contracts & Tenders, Wind Farm Update

    The Danish Energy Agency (DEA) has published details of the tender process and the provisional timetable for the planned 1,500 MW of offshore wind power to be set up by 2020. Since March 2012, it has been evident that Denmark should have two large offshore wind farms and several coastal offshore wind turbines to meet […]

  • 24 April 2014
    Authorities, Business & Finance, Wind Farm Update

    Danish Energy Agency (DEA) has received a total of four applications from companies that wish to prequalify for construction and operation of Horns Rev 3 offshore wind farm. The deadline for submission of applications expired yesterday at 1pm, and the Agency will now review the applications and expects to announce the shortlisted bidders within a […]

  • 7 February 2014
    Business & Finance

    Vattenfall has issued another call for Expression of Interest (EOI), this time for the supply and installation of foundations for the Horns Rev 3 project. The total scope of works includes the manufacturing, transport, supply and installation of foundations. Deadline for expression of interest is February 24. As the company intends to participate in the […]

  • 24 April 2012
    Authorities, Business & Finance

    Yesterday, Energy Minister Martin Lidegaard asked the state-owned company Energinet.dk to start feasibility studies for two proposed wind farms, 400MW Horns Rev 3 and 600MW Kriegers Flak. The work includes studies of marine mammals, birds and how parks could affect navigation. Energinet.dk will also explore the seabed in the area. At the same time, Energinet.dk […]

  • 10 November 2015
    Grid Connection, Wind Farm Update

    Energinet.dk has installed the last piece of the land cable which will connect the future Horns Rev 3 offshore wind farm to the national grid. The 220kV power cable has been installed between Endrup and Blåbjerg. In spring next year, a submarine cable will be connected with the land cable in Blåbjerg and the cable in Endrup will […]

  • 6 March 2015
    Business & Finance, Wind Farm Update

    Energinet.dk, the Danish power transmission company has appointed Hollandia Offshore with the procurement, fabrication, load out and transport of the Horns Rev C Jacket. The Jacket is to be installed in the Horns Rev 3 Offshore wind farm near the Danish Coast. The scheduled delivery date is April 2016. The Jacket is designed for a […]