Neart na Gaoithe Offshore Wind Limited, the developer of the 450MW Neart na Gaoithe wind farm offshore Scotland, has made an application to the UK Gas and Electricity Markets Authority for an electricity generation licence. The licence application will remain open for comments until 8 October. The E
Ørsted is merging the Borkum Riffgrund West 1 & 2 and OWP West offshore wind projects in Germany under the name Borkum Riffgrund 3, as well as the Gode Wind 3 and 4 under the name Gode Wind 3. Ørsted said the merger of the project companies has already been completed, while the German Federal Mariti
DEME Group’s jack-up vessel Apollo has installed 156 out of 309 pin piles at the Moray East offshore wind project in the UK, marking the halfway milestone. According to DEME, a pile installation template is being used, where three pin piles are stabbed into the seabed through the piling temple and t
The Formosa 1 Phase 2 offshore wind project in Taiwan has generated its first power. According to Ørsted, 10 out of 20 Siemens Gamesa 6MW turbines have been installed at the project site, while six units began generating power. Prior to commercial operation, each turbine goes through a power generat
Dutch-based Corrosion BV has won a contract to provide corrosion protection systems for the wind turbine foundations on the Yunlin offshore wind farm in Taiwan. Corrosion will deliver Impressed Current Cathodic Protection (ICCP) systems for the wind farm’s 80 monopile foundations. The systems will p
UK-based cable protection specialist Tekmar Energy has received an order from Jan De Nul to provide its patented Tekmar Cable Protection System (CPS) TekLink® Mechanical Latch for the Changhua offshore wind farm in Taiwan. Changhua is the second wind farm to be installed in Taiwan located along the
DEME Group’s jack-up vessel Innovation has arrived at Sif’s Maasvlakte terminal in Rotterdam to load the first monopiles for the SeaMade offshore wind project in Belgium. DEME is in charge of installing the 58 foundations, as well as the turbines, inter-array cables, export cables and two offshore s
Japan’s power company Tokyo Electric Power Company Holdings, Inc. (TEPCO) has revealed plans to build a 370MW wind farm offshore Choshi City in the Chiba prefecture. The wind farm would be built on an area of some 39km2 some 1.2 kilometres offshore, with water depths ranging between 8 and 30 metres.
MHI Vestas Offshore Wind has taken delivery of the ESVAGT Albert Betz service operation vessel (SOV) purpose-built for the 269MW Deutsche Bucht offshore wind farm. The vessel was christened on Wednesday, 4 September, at the Port of Eemshaven, the Netherlands. “With ‘ESVAGT Albert Betz’, MHI Vestas a
German offshore foundations manufacturer Steelwind Nordenham has started manufacturing monopiles and monopile sections for the 640MW Yunlin offshore wind farm in Taiwan. Steelwind rolled the first can at its facility in Nordenham on 11 July. High strength steel plate material is supplied by Steelwin
Ørsted has officially opened the Hornsea Two Offshore Construction Base (HTOCB) at Humberside Airport in Lincolnshire. The building, formerly a police station at the airport, will now house around 30 Ørsted employees who will be working around the clock to construct the 1.4GW wind farm. Hornsea Two,
Siemens Gamesa has commissioned 147 out of the 174 7MW wind turbines on the Hornsea Project One, reaching 1GW of operational capacity at the world’s largest wind farm. The wind turbines are being installed at the site some 120 kilometres offshore Yorkshire by Fred. Olsen Windcarrier’s jack-up vessel
Mayflower Wind Energy has issued the public version of its bids into Massachusetts’ second round of the offshore wind development procurement process. Mayflower Wind, a joint venture of Shell New Energies and EDPR Offshore North America, submitted three 800MW proposals as well as a 400MW proposal. M
The team behind Australia’s first offshore wind project, Star of the South, is holding a series of consultations with local communities in Gippsland ahead of the site investigation campaigns scheduled to start later this year. The project team will hold a number of information sessions from 12 Septe