The last of the 90 transition pieces for the Triton Knoll offshore wind farm has been transported from Smulders’ Hoboken yard to the collection port. To remind, in September 2017, the Sif-Smulders joint venture secured a contract to manufacture the monopiles and transition pieces, as well as two fou

Fugro’s vessels Brasilis and Enterprise are set to mobilise for geophysical surveys at New Jersey’s Atlantic Shores offshore wind site on 1 May. The vessels will carry out surveys within the Atlantic Shores lease area and along potential export cable routes, according to the developer’s Notice to Ma

ABB has delivered and installed three shunt reactors in the onshore substation of the Hornsea Project Two offshore wind farm in the UK. In April 2018, Ørsted and Balfour Beatty started the construction of the onshore substation in North Killingholme. The project’s 39km onshore cable route runs from

Iberdrola has received bids from wind turbine suppliers and started activities to purchase electrical components for its East Anglia Hub offshore wind project. ScottishPower Renewables, Iberdrola’s UK company, has combined the East Anglia 1 North, East Anglia 2 and East Anglia 3 projects into one 3.

The 102nd and final wind turbine has been installed at the East Anglia ONE wind farm. DEME’s Sea Installer and Sea Challenger vessels have been installing the Siemens Gamesa 7 MW offshore wind turbines at the project site, located 43 kilometres off Suffolk, since June 2019. Wind turbine components w

The Horns Rev 3 offshore wind farm has driven up the figures in Vattenfall’s wind business unit’s results for the first quarter of 2020. Namely, the company has reported an increase in net sales and underlying operating profit for its Wind Business Area. The significant Q1 earnings improvement is a

Ørsted has revealed its plans to submit a bid in the 760 MW Holland Coast North (Hollandse Kust (Noord)) tender in the Netherlands. The zero-subsidy round of the tender started on 2 April and will close on 30 April. “The Netherlands has ambitious climate targets for both the energy and industrial se

Ørsted’s offshore wind development projects in the US are moving forward at a slower pace than originally expected, the company’s CEO and President Henrik Poulsen said. The delays are due to a combination of the Bureau of Ocean Energy Management’s (BOEM) prolonged analysis of the cumulative impacts

The first inter-array cables at the SeaMade offshore wind farm have been connected to the Mermaid offshore substation (OSS). Cable burial works will commence in the coming days, Otary states on social media. DEME’s cable installation vessel Living Stone started the inter-array works in mid-April. Th

Ørsted’s Borssele 1 & 2 offshore wind farm has delivered first power to the Dutch grid. According to the Danish company, the first Siemens Gamesa 8 MW turbine began producing electricity on 28 April. “This is a big milestone for Borssele 1 & 2. Ørsted is doing its utmost to allow the construction of

China’s first 8 MW wind turbine has been installed at the Xinghua Bay Project Phase II off Fujian, the wind turbine maker Goldwind said. The GW175-8.0 unit was installed at the site on Tuesday, 28 April. According to Goldwind, it is the latest generation of large-capacity offshore wind turbines with

German offshore wind developer wpd has signed an agreement with Taiwan Green Power (TGP) to jointly develop a 600 MW offshore wind project in Taiwan. The wind farm site No. 28 is expected to be part of the third tender round in Taiwan, wpd said. The project is located off the coast of Changhua in [&

Van Oord has installed a Slip Joint foundation at the Borssele Wind Farm Site V offshore the Netherlands. It is the first time anywhere that a submerged Slip Joint was used on a full-sized offshore wind turbine on a fully commercial basis, Van Oord said. After years of developing the system in coope

The first pin piles fabricated in South Korea for the Taiwan Power Company Offshore Windfarm Phase 1 Project – Demonstration have been loaded out for transport to Taiwan. As previously reported, Edgen Murray, in collaboration with South Korea’s SeAH, completed the manufacturing of 80 pin piles for t