Grid Connection

about 6 years ago

Hornsea Two Onshore Substation Gets ABB Shunt Reactors

ABB has delivered and installed three shunt reactors in the onshore substation of the Hornsea Project Two offshore wind farm in the UK. In April 2018, Ørsted and Balfour Beatty started the construction of the onshore substation in North Killingholme. The project’s 39km onshore cable route runs from

1 minutes read
Hornsea Two Onshore Substation Gets ABB Shunt Reactors
ABB

ABB has delivered and installed three shunt reactors in the onshore substation of the Hornsea Project Two offshore wind farm in the UK.

In April 2018, Ørsted and Balfour Beatty started the construction of the onshore substation in North Killingholme.

The project’s 39km onshore cable route runs from Horseshoe Point, east of Tetney, to the substation site which is adjacent to the Hornsea Project One onshore substation.

Hornsea Two will comprise 165 Siemens Gamesa 8 MW turbines mounted on monopile foundations some 89km north-east of Grimsby.

The 1.4 GW offshore wind project is scheduled to be commissioned in 2022.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.