Scottish offshore wind farm Neart na Gaoithe (NnG) has entered the first phase of offshore construction. Saipem’s vessel S7000 set to start installing pile casings at the site some 15 kilometres off the Fife coast. The 197.5-metre semi-submersible crane vessel will also prepare the seabed for the ja

78 out of 94 Siemens Gamesa 8 MW turbines have been installed at the Borssele 1 & 2 offshore wind project in the Netherlands. DEME’s jack-up tandem Sea Installer and Sea Challenger are in charge of installing the turbines at the site located 22km off the coast of the province of Zeeland. According t

Ørsted could face delays on two offshore wind projects due to the effects of the COVID-19 pandemic. The construction of offshore substation topsides for the two projects, the 1.4 GW Hornsea Project Two in the UK and the 900 MW Greater Changhua 1 & 2a in Taiwan, was paused after the Singaporean shipy

MingYang Smart Energy now has 1,000 MW in installed offshore wind turbines, according to the company’s social media post from 11 August. The company reached the milestone with the Yangjiang Nanpeng Island offshore wind farm, owned by China General Nuclear Power Group (CGN), which will feature 73 MyS

Prysmian has started installing the export cables which will connect the 480 MW Saint-Nazaire offshore wind farm to the French grid. The Italian cable manufacturer deployed its cable-laying vessel Cable Enterprise on the project. The cable pull-in operations started off the Courance beach on Sunday,

The first export power cable for the 950 MW Moray East offshore wind project has made landfall at Inverboyndie, Scotland, Moray Offshore Windfarm (East) Ltd said. The installation of the offshore export cables is being undertaken by NKT. To minimise environmental impact, the cable was pulled through

Blue Gem Wind has awarded Rovco with a contract to carry out survey work at the site of the proposed 96 MW Erebus floating wind farm in the Celtic Sea. The million-pound contract will see Rovco carry out detailed geophysical and environmental site investigations to assess the seabed and sub-surface

Horizon Geosciences has started geotechnical investigations at the Kitty Hawk offshore wind project off North Carolina, U.S. The six-week work will be carried out by Kommandor Susan and will consist of geotechnical borehole drilling and sampling. In May 2017, Avangrid Renewables secured the rights t

The first of the three Offshore Transformer Modules (OTMs), ME OSP 3, has been installed at the 950 MW Moray East wind farm offshore Scotland. Siemens Energy shipped out the wind farm’s first OTM, ME OSP 2, for offshore installation on 30 June. This OTM will be installed later this week, a spokesper

ABPmer has been commissioned to complete the physical process impact assessment in support of the Development Consent Order Application for the Erebus floating wind farm offshore Wales. Blue Gem Wind, the joint venture between Simply Blue Energy and Total, is developing floating offshore wind sites

The Borssele III & IV offshore wind farm produced first power early in the morning on 7 August, the Blauwwind consortium informs. “This marks a key milestone in the construction of the project as the first turbine is now generating power and delivering renewable electricity into the Dutch grid”, the

Dogger Bank Wind Farm has signed a contract with Jan De Nul Group for the transport and installation of GE Haliade-X offshore wind turbines at Dogger Bank A and Dogger Bank B. The installation of the 12 MW units at the site some 130 kilometres off the Yorkshire coast will start in 2023. Turbine tran

Sixteen out of 58 Siemens Gamesa 8.4 MW turbines have been installed at the SeaMade offshore wind project in Belgium. According to Otary CEO Mathias Verkest, the 9th turbine load-out is currently being prepared at the Port of Oostende. DEME’s Apollo installed the first turbine at the project site lo

Bladt Industries has rolled out the first cans of the transition pieces and monopiles destined for the Kaskasi offshore wind project in Germany. The Danish company will deliver 39 monopiles, 38 transition pieces for the turbines and one specially designed transition piece for the offshore substation