offshoreWIND.biz
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
offshoreWIND.biz logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Contracts & Tenders›Ørsted Sees Increased Risk of Delays on Two Offshore Wind Projects
Contracts & Tenders

August 12, 2020 · about 6 years ago

Ørsted Sees Increased Risk of Delays on Two Offshore Wind Projects

Ørsted could face delays on two offshore wind projects due to the effects of the COVID-19 pandemic. The construction of offshore substation topsides for the two projects, the 1.4 GW Hornsea Project Two in the UK and the 900 MW Greater Changhua 1 & 2a in Taiwan, was paused after the Singaporean shipy

1 minutes read
  • LinkedIn
  • X
  • Email
Ørsted Sees Increased Risk of Delays on Two Offshore Wind Projects
Illustration/Ørsted

Ørsted could face delays on two offshore wind projects due to the effects of the COVID-19 pandemic.

The construction of offshore substation topsides for the two projects, the 1.4 GW Hornsea Project Two in the UK and the 900 MW Greater Changhua 1 & 2a in Taiwan, was paused after the Singaporean shipyards where they are being built were closed down for two months due to COVID-19, according to Henrik Poulsen, Ørsted’s President and CEO.

The two shipyards began opening up in June.

”The shipyards have now begun to slowly ramp-up again. Although we still expect to be able to complete both projects within our budget and time schedule, we see increased risk of delays; especially at Hornsea 2. We expect any delays to have a limited overall impact on project economics,” Poulsen said.

The two offshore substation topsides for the Hornsea Two wind farm are being constructed by Sembcorp Marine. The delivery of the topsides is scheduled for the first quarter of 2021.

Keppel FELS Ltd, a wholly-owned subsidiary of Keppel Offshore & Marine Ltd, is constructing the two topsides for the Greater Changhua 1 and 2a project. The work scope of Keppel FELS is slated for completion in the third quarter of 2021.

Ørsted still expects to commission both wind farms in 2022, as initially planned.

Reach the offshoreWIND.biz industry in one go!

offshoreWIND.biz is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow offshoreWIND.biz on:

Filed under

Contracts & TendersGrid ConnectionWind Farm Update

Daily offshore wind news in your mailbox.

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1DWT Returns to Riffgat Offshore Wind Farm
  2. 2Formosa 6 Offshore Wind Farm and Star Trade Enter Corporate Power Purchase Agreement
  3. 3TetraSpar Floater Completes Five-Year Testing Campaign Offshore Norway
  4. 4Standardization and Industrialization Could Cut Offshore Wind Costs in North Sea by 28% - Study

Daily offshore wind news in your mailbox.

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free