Work on the onshore cable route for RWE’s offshore wind farm Thor has started near the onshore substation located south of Lemvig, Denmark. The activities, scheduled to be underway from mid-April until the end of October, are starting with horizontal directional drilling under the dune and a field i

EnBW and SHS – Stahl-Holding-Saar have signed a 15-year power purchase agreement (PPA) for 50 MW of generation capacity from the 960 MW He Dreiht offshore wind farm in Germany. SHS plans to use the green electricity produced by He Dreiht to power operations at the two major steel companies in the Ge

Offshore construction has started at the Hai Long offshore wind farm site in Taiwan with the vessel Green Jade installing pin piles for the project’s jacket foundations. The Hai Long Offshore Wind Project joint venture (Northland Power, Yushan Energy, Mitsui & Co., and Gentari) announced the officia

Ecowende, a joint venture between Shell and Eneco, and the Dutch company GBM Works have signed a contract for deploying GBM’s noise reduction technology for the installation of three monopiles at the offshore wind farm Ecowende will build at Hollandse Kust West (HKW) Site VI in the Netherlands. GBM

The installation of foundations is scheduled to kick off this month at the Sofia offshore wind farm site, located on Dogger Bank in the central North Sea, 195 kilometres from the nearest point on the UK’s northeast coast. Van Oord’s offshore wind installation vessel Aeolus and special service suppor

The joint venture company behind the 1 GW Gwynt Glas floating wind project is set to change ownership structure as EDF Renewables UK, which owns Gwynt Glas together with DP Energy, is entering into a partnership with Irish renewable energy developer ESB and UK-headquartered offshore wind investor Re

Equinor and Polenergia have applied for environmental approval for the connection infrastructure of the Bałtyk I offshore wind farm as the project is being prepared for auction in Poland in 2025. The Bałtyk I offshore wind farm is one of three projects jointly developed by Equinor and Polenergia in

PGE Baltica, a PGE Group company, has selected Gavin & Doherty Geosolutions (GDG) as a geotechnical and structural designer for the ground survey stage of the EWB1 development under the Baltica 1 Project in the offshore wind farm area and along the export cable route. The scope of activities under t

The installation of the offshore substation topside and monopile foundations is about to commence at Dogger Bank B offshore wind farm, the second of the three 1.2 GW phases of the 3.6 GW Dogger Bank Wind Farm in the UK. Installation vessels Saipem 7000 and Seaway Strashnov are expected to arrive at

Fred. Olsen Seawind and EDF Renewables have confirmed a 25 per cent reduction in the number of turbines required to deliver the 1,300 MW Codling offshore wind farm in Ireland. The project will now feature a maximum of 75 wind turbines, instead of the previously anticipated 100 units. The new details

Italy-headquartered Prysmian has concluded the installation of submarine and land power cables to connect the 450 MW Neart na Gaoithe offshore wind farm to the Scottish mainland power grid. The offshore wind project is now in the testing and commissioning phase and the system is scheduled to go live

The first 14 MW turbine nacelles have been loaded onto the roll-on/roll-off (Ro-Ro) vessel, Rotra Vente, at Siemens Gamesa’s Cuxhaven plant in Germany. They are destined for the Moray West offshore wind farm and are heading toward the Port of Nigg, Scotland, according to AIS data available online. T

The Green Volt floating offshore wind farm in Scotland, being developed by Flotation Energy and Vårgrønn, a joint venture between Plenitude (Eni) and HitecVision, has been granted full onshore planning approval. The developers of the floating offshore wind project submitted the offshore consent appl

The first steel has been cut for RWE’s Nordseecluster NC 2 offshore substation which is being built by Atlantique Offshore Energy, the marine energy business unit of French company Chantiers de l’Atlantique. The Nordseecluster will be constructed in two phases, Nordseecluster A and Nordseecluster B,