Alstom has commissioned an AC offshore substation in the wind farm EnBW Baltic 2, Germany’s second offshore wind farm in the Baltic Sea. The wind farm hosts 80 wind turbines feeding up to 288 MW into the grid, providing power to 340,000 households. The offshore substation transmits the electrical en
Offshore Wind Consultants Limited (OWC), part of the Aqualis Offshore group, has completed the supervision and management of the onshore and overwater cable route site investigation for the East Anglia ONE offshore windfarm off the east coast of the UK. The investigation was carried out over the sum
Joulz has won a contract for the management and maintenance of Eneco Luchterduinen OHVS (offshore high-voltage station). Joulz will also take on the responsibility for keeping the wind farm operational, by taking over responsibility for the installation and maintaining a 24/7 emergency service, amon
DeepOcean 1 UK Ltd, a subsidiary of DeepOcean Group Holding BV, has won a contract for the provision of cable installation and trenching work for DONG Energy’s Race Bank offshore wind farm. Offshore work will be undertaken in 2016/2017 with DeepOcean’s in-house fleet of dedicated cable installation
TenneT has signed a contract with the engineering consultancy Witteveen + Bos in consortium with Mott MacDonald, and Altenburg & Wymenga and IMARES Wageningen UR as subcontractors, for the preparation of the Environmental Impact Assessment (EIA) for the connection of wind farms planned off the south
Energinet.dk has located the part of the Horns Rev 2 subsea cable which caused the offshore wind farm’s connection to go out of service on Monday. The transmission system operator (TSO) reported that the error has been found approximately 800 meters from Energinet.dk’s platform at sea, which collect
A subsea cable that runs from the Horns Rev 2 offshore wind farm to the onshore grid is out of operation, Energinet.dk reported. After an error occurred on the cable at 01:56 last night, Energinet.dk went to the site to locate the faulty part and will start the repair work if necessary. It is still
Siemens has introduced a new solution for connecting offshore wind turbines to the grid. Presented at the National Maritime Conference in Bremerhaven, the direct-current technology enables a cost-efficient and simplified connection of offshore wind power plants far from the coast, Siemens said. The
DeepOcean will provide installation and trenching works for DONG Energy’s Walney Extension offshore wind project in the Irish Sea. Offshore works are expected to commence in the first quarter of 2017, subject to DONG Energy taking a final investment decision to proceed with the project. The works wi
The replacement of two sections of the cable that connects the Anholt offshore wind farm to the grid is expected to take place between 26 October and 23 November, depending on weather conditions, Energinet.dk informed. While the work is on, the island of Anholt will be powered from the its own diese
TenneT has started investigating the soil along the export cable route of the planned wind farms in the Borssele zone off the coast of Walcheren. The condition of the soil and the identification of possible obstacles such as unexploded ordnance or shipwrecks is important in building an offshore grid
Friends of the Supergrid (FOSG) teamed up with EASE, ECI, ESTELA, EWEA, and E3G to comment in a joint letter on key elements of the European Commission’s public consultation on the new electricity market design. These leading associations, NGOs and industry groups from Europe’s energy sector share t
The European Commission has granted the revised technical layout for the “Kriegers Flak – Combined Grid Solution” interconnection, planned by two transmission system operators, Energinet.dk from Denmark and 50Hertz from Germany. The project will receive funding of up to EUR 150 million from the Euro
Atlantis has completed the laying of four subsea cables at MeyGen. The four cables are housed in individual bore holes of approximately 0.5km each, drilled earlier this year, which run from the foreshore into the Inner Sound of the Pentland Firth and down to the seabed. From the exit of the borehole