The grid connection for Hollandse Kust (west) Alpha is ready for commissioning after receiving the grid readiness certificate three months ahead of schedule. Now that Hollandse Kust (west) Alpha has received the certificate, the wind farm operator Ecowende, a joint venture of Shell and Eneco, can co

The installation of transition pieces (TPs) at Scotland’s Moray West offshore wind farm is expected to start on or around 23 January. The TPs will be installed by DEME’s installation vessel Apollo and the company’s vessel Orion will later also arrive at the site to undertake monopile installation. L

RWE has released the official name of its floating wind project in California and revealed that the company will open an office in the city of Eureka in early 2024. The project, named Canopy Offshore Wind Farm (Canopy), is being developed at a site located 45 kilometres (28 miles) off the coast of H

OX2 and its partner Ingka Investments have signed a cooperation agreement with the Swedish electric power distribution company, Ellevio, and submitted applications for connection of the Galene offshore wind farm in Sweden. The 400 MW Galene, the northern part of the 1.7 GW Galatea-Galene project, wi

Vattenfall has commissioned all wind turbines at the offshore wind farm Vesterhav Syd in Denmark, which is now fully operational and feeding power into the Danish grid. Vesterhav Syd (South) is part of Vattenfall’s 344 MW Vesterhav duo, whose Vesterhav Nord (North) wind farm the company expects to c

Bourbon Subsea Services installed a floating electrical hub (FEH) at the EolMed pilot floating wind farm site in France in Autumn 2023, the company revealed on 9 January. The FEH will be connected to the project’s three floating wind turbines on one side and to the export cable on the other to enabl

[This article was last updated on 10 January following a statement received from RWE.] A part of a blade from one of the wind turbines at the Humber Gateway offshore wind farm in the UK has broken off after the wind turbine blade sustained damage. According to information in a Notice to Mariners fro

Wood Thilsted is starting ground modelling and foundation concept design work for the first offshore wind farm in Lithuania, on behalf of Ignitis Renewables. The work, taking place this year, consists of developing a site ground model, support to the geotechnical campaign and a variety of foundation

Great Lakes Dredge & Dock (GLDD), together with its consortium partner Van Oord, has been informed by Empire Offshore Wind, a joint venture between BP and Equinor, of the termination of the rock installation contract for the Empire Wind 2 offshore wind project which was set to commence in 2026. In 2

The Dutch offshore wind foundation manufacturer, Sif, has received a notice of termination of its Empire Wind 2 monopile contract from the joint venture owned by BP and Equinor, who have just terminated their Offshore Wind Renewable Energy Certificate (OREC) agreement for the 1,260 MW project with t

With the termination of the Offshore Wind Renewable Energy Certificate (OREC) agreement for the Empire Wind 2 offshore wind project, BP and Equinor have cancelled the contract for the project’s offshore substation (OSS) with the Singapore-based company Seatrium. As reported earlier today, 4 January,

On 1 January 2024, the 112 MW Ishikari Bay New Port offshore wind farm in Japan began commercial operations, which is owned by JERA and Green power Investment Corporation, through a special-purpose corporation, Green Power Ishikari GK. The construction of the Ishikari Bay New Port Offshore Wind Farm

The US joint venture between BP and Equinor has agreed with the New York State Energy Research and Development Authority (NYSERDA) to terminate the Offshore Wind Renewable Energy Certificate (OREC) agreement for the 1,260 MW Empire Wind 2 offshore wind project that recently obtained federal approval

Vineyard Wind offshore wind project, being developed by Avangrid and Copenhagen Infrastructure Partners (CIP), has delivered its first power to the New England grid in Massachusetts. As part of the initial commissioning process, on Tuesday 2 January 2024, one turbine delivered approximately 5 MW of