
The high-voltage direct current (HVDC) offshore converter platform (OCP) has been installed at the Sofia offshore wind farm site in the UK. The installation was carried out by Heerema Marine Contractors, using its Sleipnir heavy-lift vessel as a subcontractor to the GE Vernova/Seatrium consortium re

Heerema Marine Contractors’ crane vessel, Thialf, has installed all 64 foundations at EnBW’s 960 MW He Dreiht offshore wind farm in the German North Sea. Heerema Marine Contractors, headquartered in the Netherlands, was contracted by EnBW in April 2022 to install monopiles and transition pieces at t

This article was updated at 10:15 CET on 28 August 2024 after a response from Hai Long Offshore Wind. The CO2 leak that hospitalised 17 people working at the Hai Long onshore substation site in Changhua, Taiwan, on 20 August has claimed at least one life. On 27 August, the Hai Long Offshore Wind con

This article was updated at 15:05 CET on 23 August 2024 with a statement from GE Vernova. One of the already installed wind turbine blades at Dogger Bank A offshore wind farm, currently under construction in the UK, has sustained damage and failed. The blade failure occurred on the morning of 22 Aug

All transition pieces (TPs) have been installed at the 640 MW Yunlin offshore wind farm in Taiwan. With all 80 monopiles and 68 wind turbines now in place – 52 of which are already feeding clean electricity into the grid – the project has moved into its final installation phase. Major offshore const

Polenergia and Equinor have received offshore and onshore construction permits for the Bałtyk 2 and Bałtyk 3 offshore wind farms the two companies will build together in Poland. The two projects, set to be built in the Polish sector of the Baltic Sea, approximately 37 and 22 kilometres from the coas

The 31st and last Vestas V174-9.5 MW wind turbine has been installed at the 300 MW Zhong Neng offshore wind project in Taiwan. Full production of the wind farm is expected later this year, according to a social media post by Joris Hol, CEO of Zhong Neng and Fengmiao Phase I offshore wind farms at [&

Seventeen people working on the Hai Long Changhua onshore substation, part of the Hai Long offshore wind project in Taiwan, were hospitalised on 20 August after a carbon dioxide leak at the substation. First reported by Taiwanese media citing information provided by Changhua County Fire Department,

The three-phased Hai Long offshore wind farm in Taiwan has reached several key offshore construction milestones over the past few months, including the installation of the jacket foundation for the offshore substation at Hai Long 3. There are now also 108 pin piles installed at 36 wind turbine locat

Geotechnical survey work is set to start this month at the West of Orkney Windfarm site offshore Scotland. The survey to ascertain sub-seabed characteristics at the project site will be carried out by Geo using the survey vessel Connector, starting on or around 30 August. The campaign will take appr

Ørsted’s 704 MW Revolution Wind offshore wind farm in the US will not go into full commercial operation next year but in 2026, according to the developer. In a comment to Ørsted’s interim report for the first half year 2024, Mads Nipper, the company’s group president and CEO, explained the postponem

The US Bureau of Safety and Environmental Enforcement (BSEE) has allowed Vineyard Wind to resume certain limited additional activities at the Vineyard Wind 1 offshore wind farm site. These include the installation of towers and nacelles but not (yet) the installation of the wind turbine blades. BSEE

RWE plans to participate in one of the upcoming offshore wind solicitations in New York with its 1,314 MW Community Offshore Wind project, one of the three cancelled earlier this year as GE Vernova dropped plans for the 18 MW Haliade-X wind turbine which was planned to be used in the projects. Commu

Vineyard Wind and GE Vernova have set out an action plan covering several main tasks following the blade incident at Vineyard Wind 1 offshore wind farm. The plan includes removing the remainder of the damaged blade on the turbine AW-38, continuing the collection of any debris, and resuming turbine i