Jiangsu Hengtong Power Cable Co., Ltd has won a contract from China General Nuclear Power Group (CGN) to provide high voltage subsea cables for the 150MW Rudong offshore wind demonstration project. The contract, worth CNY 32.05 million (approx. EUR 4.8 million), covers the delivery of a 55km long 35
With the first days of April, Van Oord’s Aeolus arrived in Esbjerg, Denmark, to pick up parts of the first turbines for Eneco Luchterduinen offshore wind farm. On Saturday, all components of the first turbines were loaded onto the vessel, the developer said on its social pages. Eneco Luchterduinen,
The Swedish energy company, Vattenfall, is inviting tenders for a job at Horns Rev 3 in Denmark. Following the winning bid for the offshore wind farm outside the Danish west coast Vattenfall is seeking a contractor for geotechnical site investigation works. The tender covers seabed CPTs to minimum 5
Siemens AG has awarded Fred. Olsen Windcarrier the contract for the transport and installation of 67 Siemens 6MW wind turbines at the Veja Mate 400MW wind farm. Construction is expected to start in early 2017. Martin Degen, Commercial Manager for Fred. Olsen Windcarrier said: “We are delighted to be
A joint venture comprising VolkerInfra and VBMS has been appointed by DONG Energy to execute the export cable landfall installation for Burbo Bank Extension offshore wind farm in Liverpool Bay. The works consist of two 600 meter duct installations, both intertidal and onshore, between Rhyl and Prest
DEME Concessions has entered into a partnership with Nordsee Offshore MEG I GmbH to co-develop the MEG I offshore wind farm in the German North Sea last Thursday. MEG I will be one of Germany’s largest offshore wind farms and is located in the German Bight, circa 45 km north of Borkum. This 400MW pr
Multi purpose support vessel, Stril Explorer, is set to arrive at Gwynt y Môr wind farm over the Easter weekend. The vessel is scheduled to undertake the removal of the 3 FLIDAR moorings on the seabed used as part of Carbon Trust’s Offshore Wind Accelerator (OWA) programme. Since September 2012, Car
The last of the 35 turbines was lifted into position by A2SEA’s specialist jack-up vessel Sea Challenger at the Westermost Rough offshore wind farm on Friday, March 27. Westermost Rough, located off the UK’s East Coast, is the first offshore wind farm to make commercial use of the Siemens 6MW wind t
The U.S. Trade and Development Agency has awarded a grant to the Cong Ly Construction-Trade-Tourism Company Ltd. to develop a 300-megawatt (MW) wind power project in Vietnam. The feasibility study grant will assist Cong Ly Ltd., a private sector firm that operates the only offshore wind project in V
Members of the Dutch House of Representatives have given the green light to three offshore wind farms proposed to be built 18 to 22 kilometers off North Holland, South Holland and (Borssele) Zeeland, Dutch news site NOS reports. The plan was proposed last year by the Minister of Economic Affairs Hen
RXPE has won another multi-million GBP turnkey contract from DONG Energy for equipment to support compliance with the UK Grid Code. DONG Energy selected RXPE through a competitive tender process. The power electronics specialist will provide two market-leading utility grade STATCOMs for DONG Energy’
Siemens has signed a long-term agreement with Rhyl Flats Wind Farm Ltd., 50.1% owned by RWE AG, to continue providing service and maintenance at the Rhyl Flats wind farm off the coast of North Wales for the next 15 years. Siemens has been providing service and maintenance for the 25 SWT-3.6-107 turb
Work has commenced in Norfolk to install the underground cables and construct the substations that will enable electricity produced by the Dudgeon Offshore Wind Farm to be distributed into the UK National Grid electricity network. Two underground cables will run from Weybourne on the North Norfolk c
Anholt offshore wind farm has been turned back on just over four weeks after faulty cable forced it to shut down. The wind farm went offline on 21 February after which NKT and JD Contractors worked to replace the faulty cable section. “It is a mammoth task to find the fault and replace the broken [&