The UK Energy Secretary is expected to decide on the Dogger Bank Teesside A&B offshore wind project on August 5. The UK Planning Inspectorate issued a report of recommendation to the Secretary of State on 5 May 2015. The Secretary of State then issues a decision within the following 3 months. The de
Siemens Energy Management and VBMS (UK) Ltd have been selected by the proposed Navitus Bay wind farm as the preferred electrical transmission system supplier. The two companies will come together to form a joint venture to deliver the project and will aim to use UK supply chain partners to maximise
Offshore WIND’s photo of the day: Westermeerwind wind farm components arrive in port of Amsterdam. SC Astrea, cargo ship, sailed from Esbjerg, Denmark on Monday carrying components for the installation at Westermeerwind. The vessel was loaded with towers, blades and hubs for the 144 MW project being
CWind is providing corrosion protection services to Ballast Nedam at Butendiek Offshore Wind Farm (OWF). The service, which extends to all WTG foundations, commenced in May and is expected to complete in August. Butendiek OWF, located 35 nautical miles west of the island of Sylt in the North Sea, co
ABB has commissioned and handed over the DolWin1 offshore wind grid connection to the Dutch-German transmission system operator TenneT. The 800 megawatts (MW) High Voltage Direct Current (HVDC) link connects offshore wind farms around 75 kilometers off the German coast in the DolWin cluster, with th
The first jacket foundation has been installed three miles (4.8 km) off the Block Island coast yesterday afternoon representing the first steel in the water for Deepwater Wind’s 30 MW project. According to CEO Jeff Grybowski, the 400 ton lift was conducted by the floating barge crane, Weeks 533, as
On Monday, July 27, U.S. Secretary of the Interior Sally Jewell and Bureau of Ocean Energy Management (BOEM) Director Abigail Ross Hopper will celebrate a historic “steel in the water” milestone to mark the start of construction for the nation’s first commercial offshore wind farm. Secretary Jewell
The rough sea is proving too much for what it is to be the US first offshore wind farm offshore Block Island. Due to the bad weather, which is expected to last longer than anticipated, Deepwater Wind has decided to dock the barge carrying turbine foundations off a pier in the Quonset Business Park t
Fukushima Offshore Wind Consortium plans to tow the 7 MW wind turbine from Onahama Port to its offshore site on July 31-August 1 and moor it in the following 20 days. Then, from August 20 to September 30, the developer plans to carry out the laying and burying of riser cable at the Fukushima Experim
Offshore WIND’s photo of the day: Full steam ahead at the Block Island offshore wind farm site. Deepwater Wind started building the first offshore wind farm in the U.S. yesterday, when the installation vessel Weeks 533 and a barge carrying wind turbine foundations met three miles (4.8 kilometres) of
Dominion Resources, the developer of an offshore wind project proposed to be installed off the coast of Virginia, USA, met with industry experts, academics, and others involved in the offshore wind sector to find a way to bring down the cost of its project, Richmond Times-Dispatch news site reported
Block Island Wind Farm, the U.S. first offshore wind project, has entered the offshore construction phase, according to Jeff Grybowski, Deepwater Wind’s CEO. “Heading offshore – ready to build,” Grybowski wrote on his social media page today. The main installation vessel, the Weeks 533, was mobilize
NIRAS has provided the technical background material on three of the six designated Danish areas for nearshore wind farms, which are currently on public consultation. The technical background material is provided though environmental impact assessments (EIAs). The EIAs ensure that all environmental
Carmanah Technologies Corporation’s (Carmanah) subsidiary Sabik GmbH (Sabik Offshore), which was acquired on July 2, 2015, has been awarded a contract to provide a marking system for the Nordergründe offshore wind project. The company will provide marine lights, monitoring and control for all 18 tur