German offshore wind developer wpd has signed a share purchase agreement with Starwind Offshore GmbH to sell a 27% stake in the 640MW Yunlin offshore wind project in Taiwan. Starwind Offshore GmbH is a German holding company established jointly between the Japanese companies Sojitz; JXTG Nippon Oil
Heavy lift vessel Seaway Strashnov has installed the jacket foundation and the substation topside on the 269MW Deutsche Bucht offshore wind farm in the German North Sea. “With the installation of the offshore substation completed, we have once more accomplished another milestone on schedule,” said J
Pondera Consult has won a contract to carry out an Environmental Impact Assessment (EIA) for lots VI and VII in the Hollandse Kust (west) offshore wind energy area in the Dutch North Sea. Pondera will manage the environmental impact assessment, the appropriate assessment, and the assessment for the
Teesside-based EEW Offshore Structures Britain has rolled out the first of the 35 transition pieces (TPs) built for Ørsted’s Borssele 1 + 2 offshore wind farm in the Dutch North Sea. The first TP was photographed on its way to the blast shed, EEW OSB said. EEW SPC, the parent company of EEW OSB, is
Grimsby’s Royal Dock has been confirmed as the home for Triton Knoll’s offshore construction and operations and maintenance facility after the project signed a port lease with ABP in Grimsby. A new construction and longer-term Operations and Maintenance base will be constructed across nearly four ac
Dutch high voltage offshore wind specialist Visser & Smit Hanab has been awarded the contract to perform all array cable terminations and testing work at the East Anglia One wind farm. The scope of the work entails the 66kV array cable terminations in all 102 turbines, as well as the installation of
Italy’s Renexia SpA has awarded Spain’s Haizea Wind Group with a contract to manufacture ten monopiles for what will be the first offshore wind farm in the Mediterranean Sea. Renexia has also awarded Italy-based Nautilus Srl with a contract ”to install and deploy the 30kV medium tension network as w
DNV GL is set to undertake a third-party verification study of Equinor’s Hywind Tampen floating wind farm in Norway, the world’s first expected to power oil platforms. The independent verification study will ensure that the wind turbines comply with the applicable codes and standards for floating of
MHI Vestas Offshore Wind has confirmed a firm order to provide five V164-9.5 MW turbines for the Kincardine floating wind project in Scotland. The order was signed in 2018 with Cobra Wind International Limited (CWIL), the UK offshore division of Spain’s Cobra Group. The turbines will be installed in
Ørsted has awarded Belgium’s G-tec with contracts to provide geotechnical engineering services on two offshore wind farms in the German Bight. Under the two individual contracts, G-tec will in 2019 carry out geotechnical investigations and laboratory analysis of samples taken from the seabed in vari
Vattenfall has delayed the construction of the Vesterhav Syd and Vesterhav Nord offshore wind projects in Denmark by three years. According to turbine supplier Siemens Gamesa, the beginning of installation has been postponed to 2023, instead of 2020 as originally agreed. The Danish Energy Agency rec
The Australian Government has approved a deed of licence to allow Offshore Energy Pty Ltd (OEPL) to undertake resource exploration for the Star of the South, the country’s first offshore wind farm. The licence will allow the developer to undertake exploration in Commonwealth waters about eight to 13
The first wind turbine nacelles built by Senvion for the Trianel Windpark Borkum II wind farm have started their journey to the Buss Terminal Eemshaven in the Netherlands. The first of the 32 Senvion 6.2M152 wind turbines are expected to be installed at the site some 40 kilometres north of the islan
The heavy-lift jack-up vessels Pacific Osprey and Innovation have transported and installed the offshore substation topside on the EnBW Albatros offshore wind farm in the German North Sea. Pacific Osprey had loaded the topside in Rotterdam. In the construction area, the Innovation lifted the topside