Equinor has launched the community consultation period for the Sheringham Shoal and Dudgeon offshore wind extension projects off the North Norfolk coast in the UK. This first phase will run from 9 July to 20 August, and feedback is sought for the location of the onshore substation, the underground o

Steelwind Nordenham has dispatched the last batch of monopiles for the Yunlin offshore wind farm in Taiwan. The last four monopiles were loaded onto the Zhi Xian Zhi Xing vessel on 8 July and sent off from the foundation manufacturer’s site in Nordenham, Germany. Steelwind Nordenham has been selecte

A blade from one of SeaMade’s wind turbines collided with the gangway on DEME Group’s jack-up Apollo, after which the gangway detached from the vessel and fell into the sea. The accident happened on 2 July in the morning and no injuries were reported as there were no employees on the gangway at the

Statkraft has signed a long-term power purchase agreement (PPA) to purchase 50% of the output from the 1,075 MW Seagreen offshore wind project in Scotland. Statkraft said that the deal is the largest in its UK PPA portfolio, which now stands at 10TWhs. “As part of our project financing we required a

Taiwan-based TSMC signed a corporate power purchase agreement (CPPA) with Ørsted for the Greater Changhua 2b & 4 offshore wind farm on 8 July. TSMC will offtake the full production from the 920 MW wind farm, making this the largest-ever contract of its kind within renewable energy, according to Ørst

SSE Renewables is renaming its Seagreen 2 and 3 offshore wind projects to Berwick Bank wind farm and Marr Bank wind farm, respectively. The move to rename the projects is to distinguish the two standalone offshore wind farms from the neighboring Seagreen 1 project, SSE said. According to the company

The Thailand-based Gulf Energy Development Public Company has acquired a 50% interest in the Borkum Riffgrund 2 offshore wind farm in Germany. The company acquired 100% shares of Borkum Riffgrund 2 Investor Holding (BKR2) through its subsidiary Gulf International Holding (GIH) which entered into a s

The first jacket foundation is now in place at the Moray East offshore wind farm in Scotland. DEME Offshore, in charge of the installation works, is currently using the Seajacks Scylla jack-up vessel to install the jackets. The 950 MW offshore wind project will comprise 100 MHI Vestas 9.5 MW wind tu

Awel y Môr offshore wind farm has secured an Agreement for Lease with the Crown Estate for a 106-square-kilometre seabed area located to the west of the existing Gwynt y Môr offshore wind farm. Namely, in February 2017, the Crown Estate invited operators of the existing offshore wind farms in the UK

The Trianel Windpark Borkum II (TWB II) offshore wind farm is now fully commissioned. As of 30 June, all 32 Senvion 6.33 MW turbines have been spinning and the project was thus completed exactly two years after the start of construction. The inauguration of the 200 MW offshore wind farm, located som

Offshore wind developer Parkwind has signed a contract with Steelwind for the fabrication of the monopile foundations for the Arcadis Ost 1 offshore wind farm. The contract was signed at Steelwind’s headquarters in Nordenham, Germany. This signature follows Parkwind’s recent order of the wind farm’s

The termination and testing of the export and array cables at the Windfloat Atlantic project has been completed, JDR Cable Systems said via social media. The third and final floating wind turbine was towed to the project site at the end of May, with connection to mooring and electrical lines then le

The final phase of East Anglia One has started to receive payments under the project’s Contract for Difference (CfD), thus passing the milestone of Operational Conditions Precedent (OCP) to officially start generating electricity under the CfD scheme. The final, third phase of East Anglia One has an

Siemens Energy has shipped off the first of the three Offshore Transformer Modules (OTMs) to be installed on the 950 MW Moray East wind farm offshore Scotland. The first OTM began its journey from the fabricator to be installed at the offshore wind farm some 22 kilometres off the Aberdeenshire coast