On 28 August, the 72nd and final foundation including a monopile and a transition piece was installed at the Kriegers Flak offshore wind site in the Danish part of the Baltic Sea. The monopile foundations, installed by Van Oord’s havy lift vessel Svanen, were manufactured by EEW SPC in Germany, whil

The first shipment of wind turbine blades for the Windpark Fryslân project has been unloaded at the TMA Terminal in the Port of Amsterdam, TMA Logistics said. Located in the IJsselmeer Lake and some six kilometres off the Frisian coast, the 382.7MW Windpark Fryslân will comprise 89 Siemens Gamesa 4.

Nordic renewable energy company Cloudberry Clean Energy AS has offered to acquire 100 % of the shares in Scanvind2 AS. Scanvind2 is developing the Rewind Vänern wind power project in the shallow waters of Vänern, the largest lake in Sweden. The current development plan includes 16-17 turbines with a

Vattenfall has issued a tender for installation works on two wind farms in the Danish North Sea – Vesterhav Syd and Vesterhav Nord. The tender is divided into three lots and covers the installation of the foundations, the cables, and the wind turbines. The contracts are scheduled to run from July 20

Smulders has completed the fabrication of transition pieces (TPs) for the Taiwanese Yunlin offshore wind project. The company loaded out the last two of the total 40 TPs on 31 August, thus marking the final step in its part of the project. Currently, the final batch of nine transition pieces is stan

Van Oord has installed all 72 monopiles at Vattenfall’s 605 MW wind farm in the Danish Baltic Sea. The last monopile was en-route to the installation site, after completion at EEW Special Pipe Constructions GmbH in Rostock, on 24 August, the German company said. Van Oord’s heavy lift installation ve

Jack-up vessel Seajacks Scylla has installed 25 out of the 100 wind turbine jacket foundations at the 950 MW Moray East wind farm offshore Scotland. Chartered by DEME Group, Seajacks Scylla installed the 25th jacket foundation at the site some 22 kilometres off the Aberdeenshire coast on 29th August

The jacket foundation for the third offshore transformer module (OTM) for Moray East offshore wind farm has been installed at the site off the Scottish coast. According to the project’s latest Notice of Operations, the jack-up vessel Seajacks Scylla installed the OSP1 jacket on 30 August. Meanwhile,

DEME’s vessels Neptune, D’Artagnan, and Bonny River have been deployed on the Saint-Nazaire offshore wind project, with some of the work now underway at the site located some 12 kilometres off the coast of the Guérande peninsula in France. The company’s cutter suction dredger D’Artagnan and trailing

Global Tech I Offshore Wind GmbH has issued a contract notice for repairs to the anti-corrosion coating on the offshore substation at the Global Tech I (GTI) wind farm. The contract will have a duration of 24 months, with a possibility for two one-year renewals. The tender will remain open until 25

Fred. Olsen Windcarrier is planning to use its jack-up vessel Brave Tern for the transport and installation of turbines at the Guanyin offshore wind project in Taiwan. As reported earlier, Fred. Olsen Windcarrier secured a conditional contract with Liwei Wind Power, owned by wpd, for the transport a

Wpd has signed several supply agreements for the 350 MW Guanyin offshore wind farm in Taiwan. MHI Vestas will supply 36 of its V164-type wind turbines, for which CS Wind Taiwan will manufacture the towers. Fred. Olsen Windcarrier will be in charge of the wind turbine installation. Taiwanese companie

All turbine foundations and export cables have been installed at the Triton Knoll offshore wind farm in the UK. According to project developer RWE, the installation of the 90 monopile foundations and two lengths of 50km export cable was completed this week. Seaway 7’s Seaway Strashnov and DEME’s Inn

Ningbo Orient Cable (NBO) has won a contract to provide subsea cables for the Yangjiang Qingzhou III offshore wind farm in China. Under the circa EUR 160 million contract, NBO will provide 75km of 220kV and 142km of 35kV XLPE subsea cables for the 500 MW wind farm. The first batch of cables is expec