A consortium comprising DHI, Ørsted, Siemens Gamesa, Stiesdal Offshore, Stromning and Technical University of Denmark (DTU) will establish a test lab for floating wind turbines in the 20 MW class. The project, named FloatLab and supported with DKK 15.3 million (approximately EUR 2 million) from Inno

The International Marine Contractors Association (IMCA) has issued a new Code of Practice with the aim of improving subsea power cable installation in offshore wind by preventing cable failure and thus enabling savings for the offshore wind industry. The Code of Practice for Offshore Cable Laying in

3E, a Belgium-based technology and SaaS company for the wind, solar and energy storage industries, has been awarded a contract for a strike price study for the offshore wind tender(s) in the Princess Elisabeth zone. Under the contract signed on 20 October, 3E will analyse both the maximum strike pri

The first batch of transition pieces (TPs) for the Moray West offshore wind farm have sailed out of Lamprell’s Hamriyah yard in UAE and are on their way to a marshalling harbour in the UK. “I want to congratulate the project team and thank our client for their trust in Lamprell as we underwent both

French transmission system operator RTE Réseau de Transport d’Electricité has commissioned Dorsalys to build an onshore substation which will enable the Dieppe-Le Tréport offshore wind farm to be connected to its grid. The transformer station, located on land three kilometres from the subsea cable l

The New York State Energy Research and Development Authority (NYSERDA) has selected Attentive Energy One, Community Offshore Wind, and Excelsior Wind projects, totalling 4,032 MW in generation capacity, in the state’s third offshore wind solicitation round. In this article: The three offshore wind p

Seaway7, part of the Subsea7 Group, has been awarded a contract by Equinor and Polenergia for the inter-array cables of the MFW Bałtyk II and MFW Bałtyk III offshore wind projects in the Polish part of the Baltic Sea. Seaway7’s scope of work includes the engineering, procurement, construction, and i

Eneti has unveiled that Seajacks UK, a wholly-owned subsidiary of the company, signed a contract with an undisclosed client to transport and install turbines. With mobilization commencing in the second quarter of 2027, the contract will be performed by one of Eneti’s two NG16000X wind turbine instal

The consortium consisting of Semco Maritime and PTSC Mechanical & Construction (PTSC M&C) has been awarded an engineering, procurement, and construction (EPC) contract for a 500 MW offshore substation in the Feng Miao (Fengmiao) offshore wind farm project in Taiwan. Owned and developed by Copenhagen

Vattenfall and France-based Air Liquide have signed a power purchase agreement (PPA) covering 115 MW of capacity of the 1.5 GW Hollandse Kust Zuid, one of the largest offshore wind farms in the world. Contracted over a 15-year period beginning in 2026, the PPA will bring the overall renewable power

Following the launch of its HexDefence scour protection solution for monopile foundations earlier this year, Balmoral has now launched a HexDefence system specifically designed for offshore wind jacket foundations. At the beginning of this year, the Scottish engineering company introduced HexDefence

Industry experts convene at Clarksons HQ to address challenges and explore opportunities amid turbulent times. Clarksons Securities, Clarksons Offshore & Renewables, and Green Giraffe Advisory jointly hosted the “Offshore Wind Investment: Mind The Gap” seminar at Clarksons’ headquarters in London. T

The first monopile foundations have arrived at the Port of Virginia for Dominion Energy’s Coastal Virginia Offshore Wind (CVOW) project in the US. In September, the first eight monopile foundations, which are single vertical, steel cylinder, set sail from EEW SPC’s factory in Rostock, Germany, to th

The 69th and final Siemens Gamesa SG 11.0-200 DD wind turbine was installed at the 759 MW Hollandse Kust Noord wind farm in the Dutch North Sea on Thursday, 19 October, CrossWind, the owner and developer of the wind farm said. The final turbine’s three 97-metre long blades were lifted into position