OEG has secured a contract to provide a subsea corrosion protection system for the 976.5 MW Gennaker offshore wind farm in the German Baltic Sea, developed by Skyborn Renewables. The company will supply an Impressed Current Cathodic Protection (ICCP) system for the wind turbine foundations and is re

EnBW expects to soon complete the installation of all wind turbines at the 960 MW He Dreiht offshore wind farm, according to information the company provided in its half-year results. As reported in July, a section of a damaged rotor blade from one of the wind turbines at He Dreiht offshore wind far

Installation of all 54 transition pieces for the monopile foundations at the 1.1 GW Inch Cape offshore wind farm in Scotland has been completed. Seaway7’s heavy lift crane vessel Seaway Alfa Lift transported the transition pieces from the marshalling yard at Forth Port’s Leith facility and installed

China National Offshore Oil Corporation (CNOOC) has started operating its 16 MW Haiyou Anlan floating wind platform in the South China Sea, with the unit now supplying electricity to the Lufeng oilfield grid, according to Chinese media. CNOOC had previously reported that Haiyou Anlan was under devel

Spain-based floating LiDAR specialist EOLOS has partnered with Vietnamese marine services company Enviros to provide wind resource and metocean measurement services for offshore wind projects in Vietnam, with the first deployments planned from September 2026. Under the agreement, EOLOS will combine

Elektrownia Wiatrowa Baltica – 2, the project company developing the 1.5 GW Baltica 2 offshore wind farm, has awarded contracts for two walk-to-work (W2W) accommodation vessels that will support construction and offshore operations at the project in the Polish Baltic Sea. The contracts were awarded

Vattenfall has launched a tender seeking contractors to provide remotely operated vehicle (ROV) inspections and seabed survey services across its offshore wind portfolio in Denmark, Sweden, the Netherlands and the UK from 2027. According to a contract notice from 4 August, the company is looking to

Haizea Wind Group has delivered what it says are the largest monopiles ever manufactured in Southern Europe for the Hornsea 3 offshore wind farm in the UK. Produced at the company’s facility at the Port of Bilbao, the monopiles measure over 105 metres in length, have a diameter of 11 metres, and wei

Two offshore construction milestones have been completed at the 495 MW Fengmiao 1 offshore wind farm in Taiwan, with Jan De Nul finalising the export cable connection to the offshore substation and CDWE completing the installation of the offshore substation and its foundation. Jan De Nul said on 5 A

Steelwind Nordenham has completed the delivery of all monopiles under its contract for the 1.5 GW Baltica 2 offshore wind farm in the Polish Baltic Sea, with the final two foundations shipped from the company’s port facility. Under its scope, Steelwind manufactured and delivered 34 monopiles for the

Danish construction company Per Aarsleff A/S has been awarded a design-and-build contract by Energinet for the onshore infrastructure of Denmark’s Bornholm Energy Island project, which will connect future offshore wind farms in the Baltic Sea to the Danish and German electricity grids. The contract,

Dajin Heavy Industry has started fabrication of 63 transition pieces (TPs) for the 976.5 MW Gennaker offshore wind farm in the German Baltic Sea, following a first steel cutting ceremony held at the company’s Penglai manufacturing base in China on 30 July. The transition pieces are being manufacture

Following the installation of the first monopile at the beginning of July, the first transition piece (TP) has now also been installed at Vattenfall’s Nordlicht I offshore wind farm in the German North Sea. DEME is handling the transport and installation of the monopiles and TPs under a contract awa

Decommissioning work has started on the TetraSpar Demonstrator floating wind project at the Marine Energy Test Centre (METCentre) site off Karmøy, Norway, with the dynamic export cable disconnected and placed in wet storage, clearing the site for the next demonstrator project. The decommissioning ca