Dominion Energy has revealed that 78 monopile foundations and four pin piles for one offshore substation were installed at the 2.6 GW Coastal Virginia Offshore Wind (CVOW) project in the US during the first installation season. Dominion Energy said that it achieved its initial goal of installing at

Cadeler heavy lift vessel Wind Orca is nearing completion of turbine installations at the Moray West offshore wind farm site in Scotland, with just six turbines remaining to be installed, according to the latest Notice to Mariners. Moray West, part of Ocean Winds’ 6 GW portfolio of secured offshore

German energy company RWE has secured construction and environmental permits to build a 100 MW electrolyzer in Eemshaven, the Netherlands. The electrolyzer is part of system integration solutions associated with OranjeWind, an offshore wind project RWE is jointly developing with TotalEnergies in the

The Danish Energy Agency (DEA) has granted RWE the offshore construction permit for its Thor offshore wind farm, enabling RWE to begin construction at sea in spring 2025. RWE said that good progress is already being made on land, with the laying of cables and the construction of an onshore substatio

Several new components for the wind turbines destined for the Les Eoliennes Flottantes du Golfe du Lion (EFGL) floating offshore wind farm have arrived at the wind terminal in Port-La Nouvelle, France. The towers and nacelles for the floating wind project’s Vestas V164-10.0 MW wind turbines have bee

Global investment firm Brookfield has bought minority stakes in four UK offshore wind farms owned and operated by Ørsted for around GBP 1.75 billion (approximately EUR 2.1 billion). The buy-in, which Brookfield is pursuing through Brookfield Infrastructure Fund V, will see the investment firm acquir

The DP3 installation vessel Orion, owned and operated by the Belgian offshore construction specialist DEME, is scheduled to begin installing the remaining monopile foundations at the Vineyard Wind 1 site in the US on or around 28 October, as disclosed in the project’s recent offshore wind mariner up

Dominion Energy has completed the purchase of the Kitty Hawk North offshore wind lease area from Avangrid, Iberdrola’s US subsidiary, for approximately USD 160 million. The agreement includes a lease acquisition payment of USD 117 million, approximately USD 3,000 per acre, along with a reimbursement

The first floating solars for the Hollandse Kust Noord (HKN) offshore solar farm have arrived at the Port of Amsterdam, set for installation at the Dutch CrossWind HKN offshore wind farm. Planned for a 2025 installation, the Hollandse Kust Noord solar farm is expected to be what the company describe

Van Oord’s new, next-generation cable-laying vessel (CLV) Calypso has begun installing cables at its first offshore wind project, marking its official debut. Calypso’s first project is RWE’s Sofia offshore wind farm, being constructed on Dogger Bank in the central North Sea, 195 kilometres from the

Following a July blade failure incident, GE Vernova plans to remove some blades and strengthen others at the Vineyard Wind 1 offshore wind farm in the US. The companies are implementing the incident and response action plan, which was announced in August. The plan outlined steps to safely remove the

Hengtong Group’s large-capacity wind installation jack-up has commenced its wind turbine installation works for the very first time in China. The Hengtong Haiyue jack-up is responsible for installing a total of twelve turbines at the Hainan Danzhou CZ3 offshore wind project in Hainan, China. Once fu

Dominion Energy has closed on a transaction to sell a 50 per cent noncontrolling interest in the 2.6 GW Coastal Virginia Offshore Wind (CVOW) project to Stonepeak. Dominion Energy will retain full operational control of the construction and operations of the offshore wind project, and Stonepeak will

The developers who entered their projects in New York’s fifth solicitation for offshore wind energy have submitted finalised proposals, with RWE and National Grid Ventures’ Community Wind offshore wind farm now proposed to have a generation capacity of up to 2.8 GW and to be built in two phases by 2