PGE Group has obtained grid connection terms for the 896 MW Baltica 1 offshore wind project in the Polish part of the Baltic Sea. Polish transmission system operator Polskie Sieci Elektroenergetyczne issued the terms concerning the technical connection conditions, including the connection capacity a

Eversendai Offshore cut the first steel for the Hollandse Kust Zuid (HKZ) Beta offshore substation platform on 28 May. The United Arab Emirates-based company, and a wholly-owned subsidiary of Malaysia’s Eversendai Corporation Berhad, is in charge of manufacturing athe jacket foundation and accompany

ENGIE Fabricom and Iemants have started engineering work on the Hollandse Kust Noord (HKN) offshore transformer station, with construction work for the topside and the jacket scheduled to start in October. As previously reported, TenneT TSO selected the ENGIE Fabricom – Iemants joint venture to cons

Walney Extension Limited has signed an agreement for the sale of its transmission assets to Diamond Transmission Partners Walney Extension. The transmission assets hold an asset value of GBP 447 million. The assets include the onshore substation, export cables, and the offshore substations at the 65

The project team working on the jacket foundation for the Hollandse Kust Zuid Alpha offshore substation has completed all the major lifts for the jacket, Petrofac said. The jacket is now getting ready to depart the United Arab Emirates and head to the Dutch North Sea. In September 2019, Eversendai O

Petrofac has awarded the Dubai-based Eversendai Offshore with two substantial contracts for the offshore wind-related projects in the Netherlands and in Scotland, UK. Eversendai Offshore, a wholly-owned subsidiary of Malaysia’s Eversendai Corporation Berhad, will fabricate and construct a jacket fou

The 252 MW Seastar offshore wind farm in Belgium has been connected to Elia’s Modular Offshore Grid (MOG). Seastar is part of the 487 MW SeaMade project which comprises 58 Siemens Gamesa 8.4 MW turbines. The connection of the wind farm marks the completion of the MOG located 40km off Belgium’s coast

Dubai-based Drydocks World has held a steel-cutting ceremony for the Hollandse Kust Zuid Beta offshore substation topside. This is the third topside that Drydocks World will be constructing for Petrofac and end-client TenneT, and the second project for the Hollandse Kust Zuid zone. The 700 MW High V

TenneT has selected the consortium of ENGIE Fabricom and Iemants to design, engineer, produce, deliver, transport, and install a 700 MW offshore substation for the Hollandse Kust Noord offshore wind farm. The contract also includes the options for identical work on the Hollandse Kust West Alpha and

SSE Renewables has reached a voluntary land agreement for the development of the underground cable route for the Seagreen offshore wind project in Scotland. The deal was reached with Angus Council, Carnoustie Golf Links Management Committee (CGLMC), and other key landowners to allow the development

The Netherlands intends to extend the licences for new offshore wind projects from 30 to 40 years, according to Eric Wiebes, the country’s Minister for Economic Affairs and Climate Policy. In a letter sent to the Dutch Parliament, Minister Wiebes said that the extended licences will allow the develo

DEME Group has completed inter-array cable laying works at the SeaMade offshore wind farm in Belgium. DEME’s DP3 cable installation vessel Living Stone laid 64 inter-array cables with a total length of 71.2km. According to the company, the vessel operated at peak production levels, laying up to thre

Tekmar Group has revealed the involvement of its operating companies in the 12 MW Coastal Virginia Offshore Wind (CVOW) project in the U.S. Tekmar Energy supplied Seaway 7 with TekLink cable protection systems and TekDuct cable crossing protection for the construction phase of the project. AgileTek

DEME Offshore and Hellenic Cables have completed the testing and energization of the export cable connections at the SeaMade offshore wind project in Belgium. DEME said it is currently carrying out the inter-array cable installation and preparing for the turbine installation campaign, set to begin i