Siemens Energy Service has completed an upgrade on the offshore substation of the Baltic 1 offshore wind farm in Germany. The work, completed in July, included an upgrade on the existing gas-insulated switchgear to improve and safeguard the energy transmission. The pre-campaign started in March when

The first of the three Offshore Transformer Modules (OTMs), ME OSP 3, has been installed at the 950 MW Moray East wind farm offshore Scotland. Siemens Energy shipped out the wind farm’s first OTM, ME OSP 2, for offshore installation on 30 June. This OTM will be installed later this week, a spokesper

A multi-user, planned transmission system for offshore wind in New York could result in electric grid cost savings of over USD 500 million and significantly reduce environmental impacts and project risks, according to a new report prepared by The Brattle Group for Anbaric. The Offshore Wind Transmis

Jan De Nul has completed the installation of four subsea export cables and the upgrade of the onshore substation of Taiwan Power Company’s Changhua Phase 1 offshore wind project. The company’s cable-laying vessel Willem de Vlamingh installed the four cables from the site 10km off the coast to the sh

TenneT will raise its investment in renewable energy connections to EUR 4 to 5 billion per year, the transmission system operator (TSO) said in a press release from 31 July, also reporting a 30% increase in its investment agenda in the first half of 2020. The TSO, operating in Germany and the Nether

UK Gas and Electricity Markets Authority (GEMA) has granted Diamond Transmission Partners Walney Extension with the offshore transmission license for the Walney Extension wind farm in the Irish Sea. In addition to being granted the 20-year license, Diamond Transmission Partners has been required to

The 700 MW Borssele Beta high voltage offshore platform is ready for use, the Dutch offshore transmission system operator TenneT said. The platform connecting offshore wind farms Borssele III & IV, and Borssele V to the Dutch grid was completed within budget and on schedule, according to TenneT. Bla

More than 8,000 tonnes of high voltage cables for the connection of the Hollandse Kust Zuid (HKZ) Alpha offshore platform to the onshore grid arrived at the Port Rotterdam on 19 July. The cables, which Hellenic Cables sent from Greece at the beginning of July, were transported by Acta Marine’s CC At

The boulder picking operations have begun at the export cable route of the Moray East offshore wind project in Scotland. The boulder picking work started on 24 July using Olympic Triton, while the export cable laying and trenching operations are set to begin circa 28 July. NKT Victoria will be layin

Iv-Offshore & Energy has signed the early works contract with Sembcorp Marine for the engineering of the Sofia high voltage direct current (HVDC) platform. As previously reported, GE Renewable Energy’s Grid Solutions and Sembcorp Marine will provide the electrical transmission system for RWE’s 1.4 G

German offshore wind farms produced 13.73 terawatt hours (TWh) in the first half of 2020, almost 18 per cent more than in the same period last year (11.64 TWh). Of this, TenneT transmitted 11.51 TWh of offshore wind energy from the North Sea to the onshore grid, marking a 21.1 per cent increase comp

ScottishPower Renewables has applied for a non-material change to the East Anglia THREE Offshore Wind Farm Order 2017 which would allow the project to take advantage of advancing technologies and deliver a reduction in levelised energy costs. The application, submitted by East Anglia Three Limited,

The 25 MW WindFloat Atlantic floating offshore wind farm is now fully operational and supplying electricity to Portugal’s electrical grid. The WindFloat Atlantic project features three MHI Vestas 8.4 MW turbines mounted on Principle Power’s semi-submersible floating foundations. Following the connec

The UK Government has proposed to exempt Beatrice, Hornsea One, Rampion, and East Anglia One offshore wind farms from the requirement to hold a licence to transmit electricity, due to COVID-19-related delays in transferring their transmission assets. The four offshore wind farms, involved in the fif