
Van Oord has awarded TKF with a contract to provide the inter-array cables for the Baltic Eagle offshore wind project in Germany. TKF is in charge of the production and delivery of approximately 79 kilometers of 66 kV inter-array cables and corresponding accessories. Van Oord’s cable-laying vessel N

Japanese company PowerX plans to design and build an automated Power Transfer Vessel to carry electricity from offshore wind farms to shore. The Power ARK 100 is a 100 TEU trimaran specially designed for transferring renewable energy in Japan’s coastal waters. Upon its completion in 2025, Power ARK

East Lothian Council planning officers have recommended for approval the Seagreen 1A onshore proposals at Cockenzie. The applications were submitted earlier this year to East Lothian Council for onshore works and Marine Scotland for offshore works. No local representations had been received against

Acteon has completed a cable survey at the Coastal Virginia Offshore Wind (CVOW) project in Virginia as part of a partnership with Siemens Gamesa. Acteon’s TerraSond performed the survey from Atlantic Endeavor, the project’s dedicated crew transfer vessel (CTV) that was specially modified for the wo

DEME has installed the first offshore substation (OSS) in France at the Saint-Nazaire wind farm off the Guérande peninsula. Weighing 2,100 tons, the OSS topside was installed at the site on August 18. The substation’s jacket foundation was installed earlier this week. The electrical substation was c

The Hornsea Two offshore substation (OSS) and the reactive compensation station (RCS) topsides have left the Sembcorp Marine Admiralty Yard in Singapore and are en route to the UK, Sembcorp Marine said. The two topsides departed on 15 August and are expected to reach their destination at the end of

The jacket foundation for the Saint-Nazaire offshore substation was installed off the coast of the Guérande peninsula in France over the weekend, DEME Group said. The 48-metre jacket will be held in place by four foundation piles installed in April 2021 by DEME Offshore using an in-house designed su

LS Cable & System has revealed the plan to buy the largest submarine cable laying barge in Korea to increase participation in domestic and overseas offshore wind projects. The company is planning to acquire its first submarine cable laying barge and prepare for offshore wind power generation project

The topsides for the Hornsea Two offshore substation and the reactive compensation station have been loaded onto Guangzhou Salvage’s vessel Hua Hai Long at Sembawang, Singapore. The topsides will soon be ready to start their journey to the UK, Guangzhou Salvage said. The topsides were manufactured b

Work is underway to pull cabling through 19.5 kilometres of underground ducts which will connect the GBP 3 billion Seagreen Wind Farm to the Scottish national grid. The cable pulling is the latest stage in the cable installation process and another milestone in the construction of the 1,075MW 114-tu

Van Oord’s underwater robot Deep Dig-It has returned to the Hollandse Kust Zuid wind farm to connect the HKZ Beta offshore platform to the mainland. TenneT is developing the Hollandse Kust Zuid offshore grid for the connection of the 1.5 GW wind farm. Four offshore cables will be buried in the North

Beatrice Offshore Wind Farm Limited has signed an agreement to sell the offshore transmission assets (OFTO) of the 588 MW Beatrice offshore wind farm to Transmission Capital Partners. The sale agreement follows the selection in December 2019 by Ofgem of Transmission Capital Partners, a consortium co

Atlantique Offshore Energy has signed long-term maintenance contracts for three offshore substations its parent company Chantiers de l’Atlantique is building for three offshore wind farms in France. Chantiers de l’Atlantique reported on 27 July that its Marine Energy Business Unit, Atlantique Offsho

German offshore wind farms generated 11.49 TWh of electricity in the first half of 2021, some 16.3 per cent less than during the same time last year, when offshore wind turbines off the country’s coasts produced 13.73 TWh of electricity. The wind energy transmitted from the German North Sea to shore