Delivery partners have completed the installation of over 328 kilometres of 66 kV inter-array cables for Dogger Bank A, the first phase of the UK’s Dogger Bank Wind Farm, marking the completion of all inter-array cable work for this phase. The 66 kV XLPE-insulated inter-array cables were manufacture

Two transformers for the 1.1 GW Inch Cape offshore wind farm have completed their overland and sea journey from Zagreb, Croatia. The transformers traveled via Rotterdam, Netherlands, before arriving at the Smulders yard in Wallsend, the UK. The 545 MVA transformers were manufactured by Koncar Power