Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Cables›All Inter-Array Cables In Place at First Dogger Bank Wind Farm Phase
Cables

July 24, 2024 · about 2 years ago

All Inter-Array Cables In Place at First Dogger Bank Wind Farm Phase

Delivery partners have completed the installation of over 328 kilometres of 66 kV inter-array cables for Dogger Bank A, the first phase of the UK’s Dogger Bank Wind Farm, marking the completion of all inter-array cable work for this phase. The 66 kV XLPE-insulated inter-array cables were manufacture

2 minutes read
  • LinkedIn
  • X
  • Email
DEME Dogger Bank A inter array
Photo: Viking Neptun working on Dogger Bank A. Image credit: DEME Offshore

Delivery partners have completed the installation of over 328 kilometres of 66 kV inter-array cables for Dogger Bank A, the first phase of the UK’s Dogger Bank Wind Farm, marking the completion of all inter-array cable work for this phase.

The 66 kV XLPE-insulated inter-array cables were manufactured by Hellenic Cables under a contract with Dogger Bank tier-one contractor DEME Offshore.

The Greek company and DEME Offshore are also responsible for the manufacture and installation of inter-array cables for the other two phases of Dogger Bank Wind Farm, namely the 1.2 GW Dogger Bank B and the 1.2 GW Dogger Bank C.

The first inter-array cable for Dogger Bank B is expected to be installed in autumn 2024.

Related Articles

Contracts & Tenders

DEME Places Entire Dogger Bank Array Cable Order with Hellenic Cables

2 min read

The cables for the Dogger Bank A were laid by DEME Offshore ‘s Viking Neptun , with burial works being completed by the company’s Living Stone vessel.

This work marks the completion of all inter-array cables on the first phase of the wind farm, the 1.2 GW Dogger Bank A, which began generating power in October 2023.

“With 277 cables to be installed in total, it’s by far the biggest inter-array cable installation programme undertaken to date in offshore wind,” said Alan Evans , Dogger Bank Wind Farm Marine Package Manager.

The laying of cables is carried out using a specialist cable-laying vessel that uses a carousel and tensioner device to deploy cable over the stern chute of the ship and onto the surface of the seabed. The second stage involves connecting the cable to the offshore platform as well as each wind turbine.

The network of 95 cables, in a multitude of lengths up to 8.6 miles (approximately 13.8 kilometres), will connect Dogger Bank A’s 95 Haliade-X 13 MW turbines to the project’s offshore converter station. From here, the electricity is converted into direct current for transmission to Dogger Bank A’s onshore converter station via a high-voltage direct current (HVDC) system.

Dogger Bank A was planned to enter commercial operation this year, however, SSE said in February that the 1.2 GW offshore wind farm may not be fully operational until 2025.

Related Articles

Fixed-Bottom

Wind Turbine Installation on Dogger Bank A to Resume in May, Voltaire Undergoing Scheduled Maintenance in Netherlands

2 min read

The delay is expected due to challenging weather conditions impacting wind turbine installation and vessel availability and supply chain delays further impacting progress, said SSE, which owns the wind farm together with Equinor and Vårgrønn.

The entire 3.6 GW Dogger Bank Wind Farm is scheduled to be completed in 2026.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

CablesFixed-BottomGrid ConnectionProject UpdatesWind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1US Wind Gives Up Sparrows Point Site as Offshore Wind Project Faces Delays
  2. 2Dogger Bank B Wind Turbine Installation Passes Halfway Mark
  3. 3GWEC Calls for Government Action to Accelerate Floating Wind Commercialisation
  4. 4France Energies Marines Launches Four Offshore Wind R&D Projects

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free