The repairs on the cable linking the 309 MW Rentel offshore wind farm to mainland Belgium have been completed about four months after it failed. The fault was located just below the Rentel transformer platform, said the Belgian transmission system operator (TSO) Elia. A new section of the cable, app

The California Independent System Operator (CAISO) has approved the 2023-2024 Transmission Plan that identifies and plans for key upgrades to California’s transmission system to deliver power from offshore wind turbines to the state’s homes and businesses. CAISO unveiled its draft 2023-2024 Transmis

Atlantic Shores Offshore Wind (Atlantic Shores), a joint venture between Shell New Energies US and EDF-RE Offshore Development, has selected Creamer-Jingoli to engineer and design the full onshore underground cable route for Atlantic Shores Project 1, located in New Jersey. The early works contract

Dutch company HSM Offshore Energy has entered into a long-term lease agreement with its compatriot Hollandia to use its Stormpolder yard in Krimpen aan den IJssel. The move is part of HSM Offshore Energy’s expansion plans and the growing order book, according to the company, which has several offsho

Heerema Marine Contractors’ crane vessel, Sleipnir, has installed the jacket foundation for TenneT’s Hollandse Kust (west Beta) offshore substation in the Netherlands. On 16 May, the jacket foundation sailed on a floating pontoon from the Port of Vlissingen to its final destination about 53 kilometr

US energy and electric distribution company Eversource has completed the first phase of the Cape Cod Solution, one of two transmission projects currently under construction in New England that will allow for the interconnection of offshore wind. The other project is Revolution Wind, for which Everso

The first of two export cables for TenneT’s Hollandse Kust (west Beta) offshore grid connection has been pulled underneath the dunes at Velsen, the Netherlands. In the coming days, the consortium between Boskalis and Orient Cable will bury this 220 kV AC cable into the seabed. Boskalis’ cable-laying

The jacket foundation for the Hollandse Kust West Beta substation has left the Smulders yard in Vlissingen, the Netherlands, and is now being transported to the offshore wind farm site, approximately 53 kilometres off the coast of Egmond aan Zee. On 16 May, the 49-metres-high jacket left the yard in

The first offshore substation (OSS) topside has been installed at the Hai Long offshore wind farm by CSBC-DEME Wind Engineering’s (CDWE) Green Jade vessel in Taiwan. The 1,022 MW Hai Long comprises two offshore wind farms, the 532 MW Hai Long 2 and the 512 MW Hai Long 3 and is being developed in thr

Jan De Nul has ordered a new XL cable-laying vessel (CLV), identical to the Fleeming Jenkin ordered at a Chinese shipyard last year. With a cable-carrying capacity of 28,000 tonnes, the vessels are said to be the largest capacity CLVs in the world. Like Fleeming Jenkin, the new vessel will be 215 me

Japan-headquartered Sumitomo Electric has kicked off the construction of its subsea cable factory in Scotland, set to supply critical elements for the reinforcement of the UK electricity transmission grid and for connecting renewable energy production facilities to the grid. Sumitomo Electric held t

The Danish Energy Agency (DEA) has revealed its Plan for Program Bornholm Energy Island, outlining the framework for the future energy island at Bornholm and the adjacent coastal areas. The project is planned to consist of an offshore wind farm south of Bornholm with a 3.8 GW capacity as well as hig

Finland’s transmission system operator (TSO) Fingrid Oyj has identified five preliminary areas along the country’s west coast where offshore wind farms could be connected to the mainland grid by the 2030s. Now, the TSO is seeking feedback from stakeholders on defining the connection points more prec

The new cable factory Twentsche Kabelfabriek (TKF) built in Eemshaven is preparing for full operation as the company completed a type test run in March, producing a three power core-type test cable, and with the vertical lay-up machine (VLM) delivered by PASSER now commissioned and undergoing final