TenneT and Mitsubishi Corporation officially closed their partnership with respect to two German offshore high-voltage cable projects, BorWin1 and BorWin2. Mitsubishi’s voting interest will be 49% with aggregate maximum equity commitment of EUR 240 million. At the same time both partners signed a co
Mainstream Renewable Power, the global renewable energy company that is proposing to develop the Neart na Gaoithe offshore wind farm off the coast of Fife, has submitted a planning application to East Lothian Council for the onshore works required to connect the wind farm to the National Grid. The p
Vos Prodect Innovations secures a new contract from Cofely Fabricom sa/nv, for the supply of sealed cable hang-off systems of E.ON’s Amrumbank OWF. The Amrumbank West offshore wind farm is located around 35 km north of the island of Helgoland. It will consist of 80 Siemens wind turbines with a rated
Developers of offshore renewable energy in Scotland are worried over delay in power connection between Orkney and Shetland Islands and the mainland, which was announced by SSE’s Scottish Hydro Electric Transmission(SHE) on December 20, Bloomberg informs. Richard Yemm, founder and director of Pelamis
Public Accounts Committee (PAC) publishes report on offshore electricity transmission – a new model for infrastructure. “Not only is it unlikely that this new licensing system for bringing electricity from offshore wind farms onto the national grid will deliver any savings for consumers, it could we
A planning application for the European Offshore Wind Deployment Centre (EOWDC), regarding onshore works related to the project, has been submitted by the developers to Aberdeenshire Council. The submitted application is for a cable route and substation compound to the south-east of Blackdog village
Global renewable energy company Mainstream Renewable Power has finalised negotiations with UK’s National Grid for 5,000MW of “firm” access to be delivered to the UK National Grid from 2017 to 2020. The company’s Board today approved the second payment at a meeting of its Risk and Investment Committe
RTE France is seeking for contractors who will undertake geotechnical and geophysical studies of the seabed prior to the installation of high voltage subsea cables connecting offshore wind farms to land. This includes seabed geotechnical studies to a depth up to about 5-6 m. Works could require geot
Following the announcement that the cable upgrade from Orkney to Caithness will be delayed until 2018, Orkney Islands Council has called for urgent talks with ministers. Besides the problems in securing planning consents and land acquisition, SSE said they are also facing problems in the global supp
Part of the SSE energy group, Scottish Hydro Electric Transmission, announced that they will delay the grid connection between Orkney and Shetland until 2018, reports BBC. This announcement raises questions over the Scottish government’s Saltire Prize which was created to accelerate the commercial d
The small and highly specialized high-voltage submarine cable market is expected to see significant growth in the coming years. National governments and regional organizations are accelerating efforts to build offshore renewable power generation facilities, link remote landmasses, and interconnect t
Fred. Olsen Renewables Ltd. has confirmed that it has signed a grid connection offer of 1GW for Codling Wind Park, with co-owners Hazel Shore Ltd satisfying the typical power requirements of more than 160,000 homes. The Irish Waters project, which is situated in shallow waters, currently consented f
Offshore wind farm RIFFGAT, the joint project of Ewe and Enova, is under construction since May 2012. These days, the export cable has been laid for the future substation. With this cable, generated energy will be transported to the mainland. Project manager, Wilfried Hube, said that the cable will
On 6 July 2012, Nexans started connecting the connecting cables which the vessels Stemat 82 and Toisa Wave were laying on the seabed between the substation and the 111 foundations during summer 2012. Only six months after – on 5 December 2012 – Nexans had completed the work after having connected th