ABB has launched a “step change” program in its Power Systems division to thoroughly transform the business that faced a loss in the first quarter of 2014, the company said today as it released Q1 results. ABB’s operational EBITDA in Q1 is 13% down, compared to the same period of last year, mainly d
Siemens has installed the BorWin2 offshore platform in the North Sea northwest of the island of Borkum. This marks Siemens’ achievement of the second crucial milestone in the German grid connection projects under contract with the German-Dutch network operator TenneT. Siemens had already erected its
SHIP operator Rix Sea Shuttle has netted a contract at one of Europe’s largest offshore wind farms. The company was awarded the work by Reef Subsea to support their two cable installation vessels at the RWE Innogy Gwynt y Môr development. Gwynt y Môr is one of the largest offshore wind farms current
6 Alpha Associates, the strategic advisor for managing high risk offshore initiatives, has signed a long-term framework contract with TenneT, the European grid operator responsible for connecting offshore wind projects to the German electricity network. The agreement will see 6 Alpha Associates prov
OceanWind, based in the Netherlands, has been awarded a long term contract to supply Prysmian Powerlink SRL with storage of energy cables and additional preparation services. At its cable facilities in Velsen Noord, The Netherlands OceanWind will execute the cable handling and provide cable handling
Offshore WIND’s photo of the day: Sylwin Alpha jacket leaving Eemshaven on Eide Barge 33. The Sylwin Alpha jacket will be installed by Seaway Heavy Lifting’s vessel Oleg Strashnov. The jacket structure is a part of the Sylwin Alpha transformer platform, which will transform and transmit up to 864 MW
Cabling specialist VSMC, a joint VolkerWessels and Boskalis company has been awarded a contract by EPC contractor Van Oord Offshore Wind Projects bv to install and bury a 25km long export cable for the Eneco Luchterduinen Offshore Wind Farm. The Eneco Luchterduinen Offshore Wind Farm, to be built by
The Dolwin Beta project is now entering its final phase of construction at the Drydocks World yard in Dubai, with 2.5 million man hours without lost time incidents. This outstanding HSE result has been celebrated at Aibel’s subcontractor Drydocks World. “Behind the result is a lot of hard work. But
After the installation of the subsea structure of the converter platform BorWin beta 125km off the coast in 40 meters water depth in 2013, the topside with a weight of app. 12,000 tons followed today. The tow with BorWin beta had reached the construction site on April 22 after about 24 hours of tran
UK Subsea Cable Specialists Engineering Technology Applications Ltd have received a Queen’s Award for Enterprise in the International Trade category for their global success, particularly in relation to offshore renewables. The award recognises that in the last three years ETA has seen an increase o
Reef Subsea has announced a re-organization to create three independent companies: Reef Subsea, X-Subsea and Technocean Subsea, all with separate management and independent strategies. The existing senior management will continue to lead the three new entities, delivering consistent expertise in the
Nick Winser, president of ENTSO-E and Executive Director of National Grid will join panel of executive experts at DNV GL’s (formerly DNV KEMA) Utility of the Future Leadership Forum, to identify how utilities, regulators, and customers should prepare for the grid challenges ahead. The forum will be
The Iv-Consult has begun making the workshop drawings of two topsides of converter platforms, each approximately 1250 tons, for the Gode Wind 1 and 2 offshore wind projects. This project is for Iemants Steel Constructions N.V. in Belgium. Gode Wind 1 and 2 are offshore wind farm projects located nor
Siem Offshore Contractors GmbH (SOC), a wholly owned subsidiary of Siem Offshore Inc., announced today that SOC has been awarded the contract for the turnkey supply and installation package of the inner array grid cable system for the Nordsee One Offshore Wind Farm, a project developed by RWE Innogy