Specialist explosive ordnance disposal contractor Ramora UK is preparing to undertake a programme of disposal of items previously identified as unexploded wartime ordnance, found on the seabed where the 336MW Galloper wind farm will be built off the Suffolk coast. The bombs were identified during su
Adverse sea conditions have pushed back the installation of the 20-mile National Grid submarine cable from Narragansett, Rhode Island, to Block Island by one week. The cable laying barge Big Max was initially scheduled to install the cable last week, however, rough sea conditions postponed the works
TenneT Holding B.V. has launched and priced its second EUR 1 billion Green Bond issue to finance the transmission system operator’s offshore wind-related projects. The EUR 1bn dual tranche (10 and 20 year) bond issue, each sized at EUR 500 million with coupons of 1.000% and 1.875% respectively, has
VBMS has been awarded a contract by EDF Energy Renewables to provide the subsea connection between the offshore turbines and the onshore grid for the Blyth offshore wind farm. The scope of work for VBMS includes the supply and installation of a total of approximately 14 kilometres of export and inte
Danish national transmission system operator Energinet.dk has started works to install a 33-kilometre subsea cable which will connect the offshore substation at the 400MW Horns Rev 3 offshore wind farm to the power grid on land. JD Contractor’s multipurpose offshore installation vessel Sima will ins
Vattenfall is getting ready to inaugurate the 49.5MW Kentish Flats Extension offshore wind farm on the southern side of the Outer Thames Estuary at noon local time today. The wind farm comprises 15 MHI Vestas V112 3.3MW turbines and is located next to the 90MW Kentish Flats offshore wind farm which
UK-flagged cable laying vessel, Cable Enterprise, has today started installing a section of the 90-kilometre Ostwind 1 offshore cable system which will connect the 385MW Arkona and the 350MW Wikinger offshore wind farms in the German part of the Baltic Sea to an onshore substation in Lubmin, 50Hertz
Installation works on the 402MW Dudgeon offshore wind farm are progressing according to plan and the project is halfway to being completed, according to Dudgeon Offshore Windfarm Limited (DOWL). The wind farm’s export cables were laid and the jacket for the offshore substation was installed in May.
Tekmar Energy, a cable protection systems specialist (CPS) for offshore wind farms, has recently been awarded a contract with DONG Energy to supply 184 of its TekLink CPS on the 660MW Walney Extension offshore wind farm. This comes after Tekmar’s previous involvement in the Walney 1 and Walney 2 pro
Researchers at the Universitat Jaume I (UJI) have joined the PROMOTioN European project to reduce the costs of the development of the offshore wind farms by scaling down offshore electrical installations up to 50%. The Instituto de Automática e Informática Industrial (ai2 Institute) from the Polytec
Hollandia Offshore B.V. and the Danish transmission system operator, Energinet.dk, signed a contract for the engineering, procurement and commissioning of the Kriegers Flak substations on 31 May. The project comprises two unmanned substations which are due for delivery to the installation site in Ap
Transmission system operator TenneT will lay down its vision of a future large-scale European electricity infrastructure system in the North Sea in Hague on June 10. TenneT’s CEO Mel Kroon will explain the operator’s vision of a ‘North Sea Infrastructure’ system at a media event to be held in the Ni
Shell Setting Up ‘New Energies’ Unit. Oil & Gas Companies to Cause Clash of Giants in Offshore Wind? Shell has created a new division called New Energies, through which the oil and gas giant will invest in wind energy, along with its hydrogen, biofuels and electrical activities, according to The Gua
The Big Max cable laying barge will start installing the 20-mile submarine cable which will export the electricity produced by the the first US offshore wind farm, the 30MW Block Island, to the mainland later this week. The National Grid (Sea2Shore) subsea cable will connect Block Island, to Naragan