The installation of the Ostwind 1 offshore cable system that will link the 385MW Arkona and the 350MW Wikinger offshore wind farms in the German part of the Baltic Sea to an onshore substation in Lubmin is progressing as planned, 50Hertz Transmission GmbH reports. The UK-flagged cable lay vessel Cab
DONG Energy’s 580MW Race Bank offshore wind farm got the first of two of its offshore substations last week, Smulders reports. The topside and the jacket of the Race Bank 02 substation, loaded out back in June, were successfully installed at the site off Norfolk, UK, by Seaway Heavy Lifting. Iemants
The 4,550-tonne offshore substation built for the 350MW Wikinger wind farm departed last weekend from Cadiz in Southern Spain and is now en route to the installation site in the German part of the Baltic Sea. The journey is expected to last for around three weeks, according to ScottishPower Renewabl
The Nordic transmission system operators (TSOs), Svenska kraftnät, Statnett, Fingrid and Energinet.dk, have launched a report on challenges and opportunities affecting the Nordic power system in the period leading up to 2025. The main drivers of the changes are climate policy, which stimulates the d
Statoil has shared a timelapse video of a heavy lift vessel Oleg Strashnov installing a 1,700-tonne topside onto a jacket on Dudgeon bank off Norfolk, UK. The topside and the jacket were built by Sembmarine SLP in Lowestoft and now form an offshore substation which once commissioned will collect and
Denmark’s Energinet.dk and Germany’s 50Hertz Transmission GmbH have awarded Scaldis Salvage and Marine Contractors NV with a contract to install two offshore substation topsides for the 600MW Kriegers Flak offshore wind farm in the Danish sector of the Baltic Sea. The contract includes the topsides
Aberdeen-based ROV operator ROVOP has won several contracts across the offshore wind and oil and gas sectors with a combined value of USD 4 million (EUR 3.6 million). The contracts are with new clients and include construction support, cable lay and protection, survey, and inspection repair and main
Dutch Sif Holding N.V. has been awarded a contract for the production of all tubular components for the jacket of the BorWin gamma platform. The contract includes the production of legs, bracings, pile sleeves and pin piles for the jacket. The project is being undertaken by Petrofac in consortium wi
Massachusetts Governor Charlie Baker signed the new energy legislation which calls for development of 1,600MW of offshore wind capacity by 2027 into law on Monday, 8 August. An Act Relative to Energy Diversity (H. 4568) requires utilities to competitively solicit and contract for approximately 2,800
Iberdrola, 50Hertz Transmission GmbH, and Navantia hosted the delivery ceremony of the substation built for the 350MW Wikinger offshore wind farm at Navantia’s premises in Cadiz, on Monday, 8 August. The substation was christened as Andalucía and was built by Navantia entirely at the company’s Puert
Seaway Heavy Lifting (SHL) has completed its work on the 402MW Dudgeon offshore wind farm by installing the topside for the wind farm’s offshore substation on Sunday, 7 August. SHL utilised its crane vessel Oleg Strashnov to install the topside. Prior to that, Oleg Strashnov installed the wind farm’
Siem Offshore’s recent additions to the fleet, the installation support vessel Siem Moxie and the cable lay vessel Siem Aimery, are expected to install all of the 59 inter-array grid cables for the 332MW Nordsee One offshore wind farm by the end of August. Siem Offshore Contractors GmbH (SOC), a who
Massachusetts Governor Charlie Baker is expected to sign the state’s landmark energy bill which calls for public utilities to buy 1,600 MW of power generated from offshore wind farms over the coming decade on Monday, 8 August. The legislation directs companies engaging in the distribution of electri
Breaking: First US Offshore Wind Turbine Stands Tall Deepwater Wind’s CEO Jeffrey Grybowski has shared images of the the jack-up installation vessel Brave Tern as it attaches the final blade and completes the installation of the first offshore wind turbine in US waters, and the first of five wind tu