PGE Polska Grupa Energetyczna (PGE) and Ørsted have signed a contract with Grupa Przemysłowa Baltic for the production and delivery of additional secondary steel structures for the Baltica 2 foundations that will be installed in the Polish Baltic Sea. Grupa Przemysłowa Baltic will manufacture the pl

Heavy lift vessel (HLV) Seaway Alfa Lift, which recently completed the installation of transition pieces (TPs) at Dogger Bank B, has started the same work at the Dogger Bank C offshore wind site in the UK. According to the latest Notice of Operations for Dogger Bank C from Dogger Bank Wind Farm, the

Ireland’s offshore wind energy ambitions are in jeopardy unless the government takes immediate and decisive action, Wind Energy Ireland (WEI) has warned. The industry organisation issued the warning at the launch of its new Offshore Wind Action Plan on 27 May, at the start of its annual Offshore Win

The second scour protection campaign at the 496 MW Dieppe Le Tréport offshore wind farm in France has been completed. The next step is the installation of the offshore substation, which is scheduled to take place in June. DEME’s Rollingstone vessel, mobilised since the beginning of March, has finali

Fugro will carry out an offshore geotechnical survey at the Morgan and Mona offshore wind sites in the UK, starting on or around 2 June. Using its geotechnical drilling vessel Fugro Synergy, the company will be drilling, sampling and coring boreholes throughout the array areas, with the works estima

ZTT’s flagship monopile installation vessel Zhongtian 39 has completed the foundation piling for China Resources Power’s Cangnan No.1 Phase II offshore wind farm expansion project. The 215-metre-long Zhongtian 39 has installed all 13 foundation piles for the 204 MW Cangnan No.1 Phase II offshore win

Navantia Seanergies has delivered the substation jacket for Ocean Winds’ 496 MW Dieppe le Tréport offshore wind farm in France. The jacket departed from the south dock of the Puerto Real shipyard in Spain and is heading to its destination on France’s Atlantic Coast. The offshore wind farm site is lo

Equinor and Polenergia have reached financial close for the Bałtyk 2 and Bałtyk 3 offshore wind farms in Poland, for which the joint venture partners secured two project financing packages of over EUR 3 billion for each wind farm, including ancillary facilities. The finance packages will fund the ca


All suction bucket jacket (SBJ) foundations have been installed at the Greater Changhua 2b offshore wind farm in Taiwan, being developed by Ørsted. All 24 SBJ foundations have been installed by heavy-lift vessel Aegir from Heerema Marine Contractors at the 337.1 MW Greater Changhua 2b offshore wind

The 96 MW Jeonnam 1 offshore wind project, owned by a joint venture between Copenhagen Infrastructure Partners (CIP) and SK Innovation E&S, has officially commenced commercial operation in South Korea. Copenhagen Offshore Partners, exclusive offshore wind development partner to CIP, has co-led proje

The news about the US government rescinding the order to halt Empire Wind 1 construction activities has been welcomed by the offshore wind industry and New York state agencies. With more than 1,500 construction workers involved in the project and its supply chain spanning multiple US states, Oceanti

Equinor and Polenergia have taken a final investment decision for the Bałtyk 2 and Bałtyk 3 offshore wind farms, which will have 1.44 GW of installed capacity in Poland. The total investment of the project is approximately PLN 27 billion (approximately EUR 6.28 billion) in the construction, excludin

The US Department of the Interior’s Bureau of Ocean Energy Management (BOEM) has notified Equinor that the stop-work order for the Empire Wind 1 offshore wind project, issued on 16 April, has been lifted. Equinor said on 19 May that the company will now resume construction work on what will be the f