Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Dominion Energy Files COP for 2.6 GW Virginia Offshore Wind Project
Business & Finance

December 21, 2020 · about 5 years ago

Dominion Energy Files COP for 2.6 GW Virginia Offshore Wind Project

Dominion Energy has submitted a Construction and Operations Plan (COP) to the U.S. Bureau of Ocean Energy Management (BOEM) for the 2.6 GW Coastal Virginia Offshore Wind (CVOW) project. The COP includes information about the construction, operations and conceptual decommissioning plans for the wind

1 minutes read
  • LinkedIn
  • X
  • Email
Dominion Energy Files COP for 2.6 GW Virginia Offshore Wind Project
Dominion Energy

Dominion Energy has submitted a Construction and Operations Plan (COP) to the U.S. Bureau of Ocean Energy Management (BOEM) for the 2.6 GW Coastal Virginia Offshore Wind (CVOW) project.

The COP includes information about the construction, operations and conceptual decommissioning plans for the wind farm to be installed within a 112,800ha area located 27 miles off the coast of Virginia Beach, as well as about onshore and support facilities.

BOEM will now review the COP for approximately two years.

Pending approval by the State Corporation Commission, the CVOW commercial project is on track to commence construction in 2024 and be completed in 2026.

Earlier this year, Dominion Energy completed the construction of CVOW’s first phase – the two-turbine pilot project located adjacent to the commercial lease area.

Located some 43 km off the coast, the 12 GW project is meant to provide the operational, weather, and environmental experience needed for the 2.6 GW development.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Business & FinanceWind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Offshore Substations for Gennaker Wind Farm En Route to Baltic Sea (VIDEO)
  2. 2US Wind Gives Up Sparrows Point Site as Offshore Wind Project Faces Delays
  3. 3Dogger Bank B Wind Turbine Installation Passes Halfway Mark
  4. 4GWEC Calls for Government Action to Accelerate Floating Wind Commercialisation

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free