Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›News›Denmark: Continuous Hectic Activity in Anholt Offshore Wind Farm
News

June 10, 2013 · about 13 years ago

Denmark: Continuous Hectic Activity in Anholt Offshore Wind Farm

Even though the last wind turbine has been installed at the Anholt offshore wind farm, there is still hectic activity completing the commissioning and performing the one-year service on the wind turbines. A total of approximately 250 people work in the offshore wind farm on a daily basis, and the ho

1 minutes read
  • LinkedIn
  • X
  • Email

Even though the last wind turbine has been installed at the Anholt offshore wind farm, there is still hectic activity completing the commissioning and performing the one-year service on the wind turbines.

A total of approximately 250 people work in the offshore wind farm on a daily basis, and the hotel vessel, Wind Perfection, is expected to stay at the wind farm until mid-July to support efficient logistics.

At the end of May 2013, 91 of the 111 wind turbines have been connected to the grid and produced electricity.

During the summer, there will be a painting campaign to make sure that the paint protection is intact and can provide efficient corrosion protection. In addition, stones will be laid out to protect the cables on the distances where it has not been possible to sufficiently flush down the cable.

On shore in Grenaa, Siemens is re-establishing the area which has been used as pre-assembly site in connection with the wind turbine installation. At the same time, the marine coordination manning has been changed from being open 24 hours to manning between 05:00 and 22:00 with telephone duty outside opening hours.

However, the installation area will still be monitored from the guard vessel, Guard 1, which is permanently moored in the offshore wind farm and helps ensure that yachts and other vessels do not sail into the working area.

[mappress]

Press release, June 10, 2013; Image: dongenergy

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

News

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Ørsted and Nuveen Inaugurate 913 MW Offshore Wind Farm in Germany
  2. 2Stillstrom Signs Semco Maritime to Build Offshore Charging Equipment
  3. 3SLPE Secures Foundation Engineering Work on EnBW’s 1 GW Dreekant Offshore Wind Farm
  4. 4DeepOcean and TFKable Plan JV for Inter-Array Cable Projects with Dedicated Vessel

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free