Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Grid Connection›Siem Clears Caithness-Moray Subsea Route
Grid Connection

March 14, 2017 · about 9 years ago

Siem Clears Caithness-Moray Subsea Route

Siem Offshore’s Anchor Handling Tug Supply Vessel (AHTS) Siem Ruby has cleared rocks and boulders along the proposed subsea cable route for the 1.2GW Caithness-Moray transmission project in Scotland.

1 minutes read
  • LinkedIn
  • X
  • Email

Siem Offshore’s Anchor Handling Tug Supply Vessel (AHTS) Siem Ruby has cleared rocks and boulders along the proposed subsea cable route for the 1.2GW Caithness-Moray transmission project in Scotland.

This is the first in a series of major offshore activities throughout 2017 that will allow the installation of two high voltage direct current (HVDC) cables that will be capable of carrying renewable electricity between Caithness and Moray, according to Scottish & Southern Electricity Networks (SSEN).

Siem Ruby used a specialist subsea boulder clearance plough to clear the route along the seabed.

The same vessel will subsequently be used to create a trench to lay the cables within it. The cables will then be installed from a purpose-built cable laying vessel in two campaigns – the first from Noss to the midpoint of the cable route and the second from Portgordon to the end of the previously laid cable.

Following the installation of the cables the plough will be brought back and reconfigured to backfill the trench using the seabed material previously excavated during the trenching operation.

The GBP 1.1 billion Caithness-Moray project is on schedule for completion in 2018.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Grid ConnectionVessels

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Canada Pledges CAD 100 Million to Advance Nova Scotia’s Offshore Wind
  2. 2ScottishPower Renewables Completes ‘Record-Breaking’ Cable Landfall Operation for East Anglia Two
  3. 3Bidding Period Closes for 10 GW French Offshore Wind Tender
  4. 4DEME to Install Wind Turbines at Vattenfall and CIP’s 1 GW Dutch Offshore Wind Farm

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free