Tekmar Energy has signed a contract with Ørsted to provide Cable Protection Systems for the 1.4GW Hornsea Two offshore wind farm. Tekmar will provide their patented Tekmar Cable Protection System (CPS) TekLink® Mechanical Latch for the wind farm, which when constructed will become the world’s larges
Innogy has kicked off a recruitment drive for up to 22 roles at its new Triton Knoll operations & maintenance (O&M) base in Grimsby, UK. Adverts for the new roles go live from Wednesday, 31 July, as the developer seeks to identify local talent for a range of jobs. The open positions being advertised
HRH Prince Charles of Wales officially opened the 588MW Beatrice offshore wind farm in the Moray Firth, Scotland, on Monday, 29 July. Located 13 kilometres off the coast of Caithness in the North Sea, the 84-turbine Beatrice – the fourth largest offshore wind farm in the world – was completed in Jun
The Dutch PGGM Infrastructure Fund has increased its stake in the 367MW Walney offshore wind farm in the Irish Sea to 24.8 percent. The Dutch pension fund had had a 14.9 percent interest in the wind farm through the Offshore Partners Walney Holdco Limited (OPW) consortium with the Ampère Equity Fund
Work to construct a new offshore construction and operations base for Triton Knoll has officially started at Grimsby’s Royal Dock as UK based contractor Tolent gets started on site. Having been awarded the contract last month, Tolent has now begun work to construct control room, office and warehouse
Van Oord has installed the last jacket foundation on the East Anglia ONE offshore wind farm and delivered it to client ScottishPower Renewables. This marks the marine contractor’s completion of its work for this 714MW UK wind project. As the main contractor, Van Oord transported and installed all 10
The UK Planning Inspectorate has completed the examination of Vattenfall’s application for the Development Consent Order (DCO) for the Thanet Extension offshore wind farm. The Examining Authority informed that the findings, conclusions and recommendations from the examination will be sent to the Sec
Specialist Marine Consultants (SMC) has completed confined space and structural inspection works at the Gunfleet Sands Windfarm Offshore Substation. The inspection was carried out on behalf of Transmission Investment and TC Gunfleet Sands OFTO Ltd. SMC Operations Director, Dean Coates, said: “We wer
Siemens Gamesa has taken over operational control of the scheduled maintenance and troubleshooting of turbines at the Beatrice offshore wind farm in the UK, according to the project’s latest Weekly Notice of Operations. Siemens Gamesa has engaged crew transfer vessels (CTVs) Seacat Mischief and Seac
The 100th Siemens Gamesa 7MW turbine has been installed at the Hornsea Project One offshore wind farm in the UK. Fred. Olsen Windcarrier’s Bold Tern is in charge of installing 88 out of the project’s total 174 turbines, with A2SEA’s Sea Challenger responsible for installing the remaining 86 units. A
The UK Planning Inspectorate has accepted for examination the development consent order (DCO) application for the Norfolk Boreas offshore wind project. Vattenfall now expects hearings to follow late this year and in early 2020, with a decision expected in the summer next year. To remind, Norfolk Bor
Fred. Olsen Windcarrier’s jack-up vessel Bold Tern has completed the installation of 53 turbines at the Hornsea Project One offshore wind farm in the UK. Bold Tern is in charge of installing 88 out of the project’s total 174 turbines, with A2SEA’s Sea Challenger responsible for installing the remain
TFKable has installed the first sections of the 220kV onshore high-voltage cable system at the Moray East offshore wind farm in Scotland. Each of the sections includes three circuits of ducted cable, the company said, adding that the next phase of production is in progress. At the beginning of the y
Ørsted has placed an order with the Rostock-based EEW Special Pipe Constructions GmbH for 30 transition pieces for the 1,386MW Hornsea Two offshore wind project in the UK. The transition pieces will be manufactured at EEW Offshore Structures Britain (EEW OSB) in Teesside, the UK. Production will sta