The UK Secretary of State for Business, Energy and Industrial Strategy (BEIS) has postponed the decision deadline for a Development Consent Order (DCO) related to Vattenfall’s 1.8GW Norfolk Vanguard offshore wind project. The Secretary of State originally had until 10 December to issue a DCO decisio
K2 Management is working as Lender’s Technical Advisor (LTA) on the Dogger Bank Creyke Beck A and B Wind Farms, two of the three projects which make up the Dogger Bank development. In September, all three wind farms, which make up the Dogger Bank development, were selected in the Contracts for Diffe
Staffing and recruitment specialist Bureau UK has secured a framework agreement to provide resourcing to support the quality assurance, quality control, and surveillance activities across the Triton Knoll offshore wind project. Bureau UK is sourcing engineers to undertake work around Quality and Pro
The East Anglia One offshore wind project has reached the halfway turbine installation milestone with the 51st Siemens Gamesa turbine put in place. DEME Group’s vessel Sea Installer completed the installation of 51 out od 102 Siemens Gamesa 7MW turbines at the project site 43km off the Suffolk coast
EEW Offshore Structures (Britain) has carried out the final Test on Completion for Ørsted’s Borssele contract. The Teesside-based company was tasked with manufacturing and delivering a total of 35 transition pieces for the 752MW Borssele 1 + 2 wind farm in the Dutch North Sea. ALE Heavy Lift is prov
SAL Heavy Lift’s multi-purpose cargo ship Svenja has arrived at the Redcar Bulk Terminal, the UK, to pick up the third batch of transition pieces for the Borssele 1+2 offshore wind project. Svenja is picking up six transition pieces, which were produced by EEW Offshore Structures Britain (OSB) and b
Equinor and SSE have submitted an application to use bigger wind turbines on, and to remove the 1.2GW capacity cap from the Dogger Bank Teesside A offshore wind project. By submitting the application for a non-material change to the Dogger Bank Teesside A Development Consent Order (DCO), the develop
Offshore Heavy Transport (OHT) has been selected as the preferred supplier for the installation of foundations at the Dogger Bank offshore wind project in the UK. OHT’s new semi-submersible wind farm foundation installation vessel Alfa Lift will be used for the transport and installation of monopile
Following the start of construction on the Neart na Gaoithe offshore wind farm in Scotland, EDF Renewables has revealed some of the tier one contractors for the 450MW project. Siemens Gamesa will provide 54 of its 8MW turbines, which will be transported to the site and installed by Fred Olsen Windca
The EDF Group has launched the construction of the Scottish Neart na Gaoithe (NnG) offshore wind farm project along with the new partners, the Irish electricity company ESB, which is taking a 50% stake in the project. The 450MW Neart na Gaoithe will consist of 54 turbines and will be located in the
ScottishPower Renewables is planning to combine the East Anglia One North, East Anglia Two and East Anglia Three offshore wind projects into one single delivery program known as the East Anglia Hub. The three projects will produce 3.1GW of renewable energy and will be procured together to leverage t
The UK Planning Inspectorate has accepted applications for orders granting development consent submitted by ScottishPower Renewables for the East Anglia ONE North and the East Anglia TWO offshore wind farms. The UK Secretary of State has decided to accept these applications for examination. Scottish
Equinor and SSE Renewables have signed an agreement with NKT for an Engineering, Procurement, Construction and Installation (EPCI) contract for high-voltage DC on- and offshore export cable systems to be installed on the Dogger Bank Wind Farms Creyke Beck A/B. With a combined capacity of 2,400MW, th
The Rampion wind farm offshore Sussex, UK has been shut down due to a fault on the wind farm’s high voltage electrical distribution system, a spokesperson from the Rampion Offshore Wind Farm confirmed to Offshore WIND. According to BBC, the 400MW wind farm has been shut since 26 October. ”We are in