
Siemens Energy has shipped off the first of the three Offshore Transformer Modules (OTMs) to be installed on the 950 MW Moray East wind farm offshore Scotland. The first OTM began its journey from the fabricator to be installed at the offshore wind farm some 22 kilometres off the Aberdeenshire coast

The UK’s Secretary of State for Business, Energy, and Industrial Strategy (BEIS) has awarded development consent for Vattenfall’s application to build the 1.8 GW Norfolk Vanguard offshore wind farm. ”This decision justifies the confidence that we have in the offshore wind sector in Britain, and we’r

Fugro has commenced the final phase of the pre-construction site investigation at innogy’s Sofia offshore wind project in the UK. Jack-up vessel Haven Seariser 2 will work in the nearshore area between Redcar and Marske-by-the-Sea from this week to conclude the six-month offshore site investigation.

The Seajacks Scylla jack-up vessel will start installing jacket foundations at the Moray East offshore wind farm in July, according to a document listing vessels involved in the construction on Moray East project’s website, updated on 18 June. The vessel’s AIS data shows that Seajacks Scylla arrived

Smulders has loaded the first two jacket foundations for the Moray East offshore wind farm onto a barge and dispatched them from its facility in Newcastle upon Tyne. The foundations are being sent to the Port of Nigg, from where DEME Offshore will transport them to the Moray East site and install th

Siemens Gamesa has signed a preferred supplier agreement with innogy to deliver 100 of its new SG 14-222 DD turbines for the Sofia offshore wind project in the UK. The Sofia project will, therefore, be the first European project to install the 14 MW model that will be market-ready by 2024, on time f

The construction of the operations and maintenance base for the Triton Knoll offshore wind farm has been completed. UK-based contractor Tolent handed over the base at Grimsby’s Royal Dock this week, innogy said. Once fully fitted out, the O&M facility will accommodate a team of technicians and suppo

The consortium of Boskalis and NKT is set to work through the summer to install the offshore export cables at the Triton Knoll offshore wind farm in the UK. As reported, an initial 25km stretch of export cable has already been installed from the landfall north of Anderby Creek in Lincolnshire, estab

The second offshore substation platform (OSP) has been installed at the 857 MW Triton Knoll wind farm offshore Lincolnshire, the UK. The installation of OSP East, the last of the project’s two OSPs, was carried out by Seaway Strashnov overnight on Monday 15 June. “This is an important step in ensuri

Siemens Gamesa has awarded the Australian engineering company Worley with a contract to provide inspection and maintenance services of the lifting equipment at the London Array wind farm off the UK. Under the contract, Worley will carry out statutory inspections and general maintenance of the wind t

The topside for the Triton Knoll Offshore Substation Platform (OSP) East has left Vlissingen in the Netherlands and is en route to the installation site off Lincolnshire, UK. Once there, the topside will be lowered onto its monopile foundation by Seaway 7’s installation vessel Seaway Strashnov. Seaw

Fugro is set to begin geophysical surveys at innogy’s Awel y Môr offshore wind project in the UK. Survey works are expected to commence in mid-June, lasting up to eight weeks, a spokesperson from innogy told Offshore WIND. Three dedicated vessels will map the characteristics of the seabed and subsea

The second Triton Knoll offshore substation platform (OSP) topside has been loaded onto a barge and fastened in Vlissingen, the Netherlands. The Triton Knoll OSP East topside was seafastened onto the Greenbarge 3 at Damen Shiprepair Vlissingen. The Greenbarge 3 and the topside will be towed offshore

The UK Secretary of State for Business, Energy and Industrial Strategy (BEIS) has refused Vattenfall’s development consent order (DCO) application for the Thanet Extension offshore wind project. The conclusion behind the decision is that Vattenfall failed to demonstrate sufficient mitigation of risk