UK energy market regulator Ofgem has opened a tender round to grant two offshore transmission licences to connect the Moray East and the Triton Knoll offshore wind farms to the UK grid. The tender process will consist of two stages for each project, an Enhanced Pre-Qualification (EPQ) stage, and an

Prysmian Group has signed a preferred bidder agreement with RWE Renewables for the development of the high voltage submarine and land export cable connection for the Sofia offshore wind project in the UK. Prysmian will be responsible for the design, supply, offshore route preparation, installation,

SSE, National Grid, and ScottishPower have started work to develop a multi-billion pound underwater super-highway expected to turn the North Sea into the hidden powerhouse of Europe. Subsea surveys have started on the Eastern Link project which will see the world’s longest subsea high voltage direct

Ofgem will open a tender round for the offshore transmission licences for the Moray East and Triton Knoll offshore wind farms on 30 November. The authority issued a notice on 12 November, informing that the projects fulfilled all necessary conditions in accordance with regulation, including the subm

Heerema Marine Contractors’ semi-submersible crane vessel Sleipnir has installed the jacket foundation for the reactive compensation station (RCS) at the Hornsea Two offshore wind project. Sleipnir installed the jacket foundation for the project’s offshore substation at the beginning of October. Aft

Hellenic Cables has secured a contract with DEME Offshore to supply the inter-array cables and accessories for the Dogger Bank offshore wind farm in the UK. Hellenic Cables will design, manufacture, test and supply approximately 650 km of 66 kV XLPE-insulated inter-array cables and associated access

EDS HV Group has won a five-year framework contract with RWE Renewables to provide cable fault response and repair services across the energy company’s wind farms offshore the UK. Under the framework agreement, EDS will manage all aspects of cable fault response by mobilising engineers to test and i

National Grid Ventures and TenneT have signed a cooperation agreement to explore the feasibility of connecting Dutch and British offshore wind farms to the energy systems of both countries via interconnectors. Under the terms of the cooperation agreement, TenneT and National Grid Ventures will explo

EDS HV Group has completed substation maintenance work at the Rhyl Flats offshore wind farm located off the coast of North Wales. Maintenance work was done for every electrical asset, including 132kV open mesh switches, power transformers, auxiliary transformers, battery systems, shunt reactors and

Great Britain’s National Grid ESO has selected DNV GL as the lead partner in the Offshore Coordination Project, which will advise and shape the future national strategy for offshore grid development. The aim of the project is to review and recommend ways to improve how offshore wind farms are connec

Cable pull-in for the Hornsea Two offshore wind farm’s export line has been completed at the project’s landfall site at Lincolnshire’s Horseshoe Point beach. The operation, carried out by Boskalis’ cable laying vessel Ndurance, involved installing 2.4 kilometres of cable under water and toward the c

JDR Cable Systems has secured a contract to provide the termination and testing of 100 inter-array cables and two offshore substation interconnector cables at the Moray East offshore wind farm. Under the contract signed with Boskalis, JDR will perform procedures for the stripping of the armor protec

The UK government has initiated a review of the country’s offshore transmission regime, as it is looking to tweak the existing regime to allow for significantly more offshore wind to be added to the UK’s energy mix in the future. The government, with input from the industry, will look into the way t

The jacket foundation for the second of the three Moray East’s Offshore Transformer Modules (OTMs) was installed on 10 August, according to the project’s Notice of Operations. Siemens Energy shipped out the first OTM, ME OSP2, on 30 June. However, this was not the first OTM to have been installed. A