UK-based XLCC has rebranded and relaunched as Aquora, with a focus on cable installation and manufacturing to address the “critical demand” for high-voltage cable supply in the UK and Europe. Aquora will focus first on installation, utilising a new, UK-flagged cable-lay vessel (CLV), which will also

National Grid Ventures (NGV) has published updated proposals for the LionLink interconnector, which will connect the future Nederwiek 3 offshore wind farm in the Netherlands to the UK and Dutch grids. NGV, responsible for building and operating the UK side of LionLink, has now opened an eight-week p

Cable-laying vessel (CLV) Seaway Aimery is en route from the US to Europe for work that the vessel has scheduled on the East Anglia Three offshore wind farm in the UK. According to a Notice to Mariners from the East Anglia Three project, inter-array cable installation is set to commence around 12 Ja

ScottishPower Renewables has selected Nexans as the supplier of 66 kV accessories for the East Anglia Three offshore wind project in the UK. Under the contract, Nexans will deliver T-connectors, bushings, junction boxes and cable lugs, and pre-terminated power cables, which the company says are all

Indeximate, a UK-based provider of fibre optic sensing technology for predictive maintenance of offshore wind subsea cables, has received a DNV Statement of Feasibility for its Scattersphere cable health monitoring platform, the company said on 3 December. The platform was granted the Statement of F

The Offshore Renewable Energy (ORE) Catapult, in partnership with the North East Combined Authority, is investing GBP 2.1 million (around EUR 2.4 million) in a new offshore wind cable testing rig at its facilities in Blyth in North East England. Funded by the North East Combined Authority, the inves

Hellenic Cables has been awarded a contract by Seaway7 for the supply of approximately 165 kilometres of 66 kV inter-array cables and associated accessories for the East Anglia Two offshore wind farm in the UK. Hellenic Cables’ scope of work includes the engineering, design, manufacturing, testing,

Van Oord has completed the installation of 109 inter-array cables, which marks the conclusion of its full scope of work on the 1.4 GW Sofia offshore wind farm in the UK. Approximately 360 kilometres of inter-array cables have been installed and tested, connecting the wind farms’ 100 14 MW turbines t

DEME’s cable-laying vessel (CLV) Viking Neptun is scheduled to start installing the first inter-array cables at the Dogger Bank C offshore wind farm site in the UK on or around 7 September. The vessel will lay the inter-array cable onto the seabed, where the cable will remain exposed until trenching

The first section of the export cable for the 1.4 GW East Anglia Three offshore wind farm has been pulled ashore, making landfall at Bawdsey in Suffolk. NKT, which is supplying and installing the export cable for the project under a turnkey contract secured in 2022, started working on East Anglia Th

NKT, using its vessel NKT Victoria, is scheduled to start installing the export cable for the 1.4 GW East Anglia Three offshore wind farm in the UK this month. The vessel is expected to mobilise from the port of Karlskrona in Sweden on 14 June and work on the East Anglia Three site 24/7, conducting

Preparation work for the installation of the Hornsea Three export cable is underway with boulder and debris relocation, and a geophysical survey starting this month, following the completion of UXO clearance work. An installation campaign to replace blanking plates from the horizontal directional dr

The Dutch company, N-Sea Group, has been awarded a contract to repair one of the four export cables that connect the 576 MW Gwynt y Môr offshore wind farm in the UK to the National Grid. N-Sea will be responsible for replacing a five-kilometre section of 132 kV export cable from the onshore transiti

Prysmian has completed the installation and HV testing of the export subsea cables that connect the Sofia offshore wind farm to the UK mainland. The 1.4 GW offshore wind farm comprises more than 440 kilometres of ±320 kV offshore export cables with XLPE insulation, manufactured in Prysmian’s Pikkala