  • 10 June 2026
    Ports & Logistics, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    Towers, nacelles and blades for SG 14-236 DD wind turbines are arriving at Mukran Port on the German Baltic Sea coast, from where they will be installed at Iberdrola’s Windanker offshore wind farm. The 315 MW Windanker will comprise 21 turbines, equipped with Siemens Gamesa’s Power Boost, which will enable each turbine to deliver approximately […]

  • 4 June 2026
    Cables, Fixed-Bottom, Grid Connection, Project Updates, Wind Farm Update

    Van Oord has completed the inter-array cable installation campaign at the Windanker offshore wind farm site in the Baltic Sea. According to the project owner and developer, Iberdrola, the campaign involved the installation and burial of 21 inter-array cables with a combined length of 28 kilometres. The works were completed on schedule and without any […]

  • 3 February 2026
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Project Updates, Wind Farm Update

    Amazon has signed a Power Purchase Agreement (PPA) for 110 MW from Nordseecluster B offshore wind farm, the second phase of the Nordseecluster project in Germany, owned by RWE and Norges Bank Investment Management. The PPAbuilds on the Strategic Framework Agreement that RWE and Amazon signed in June 2025, under which RWE supports Amazon’s carbon-free […]

  • 7 January 2026
    Business & Finance, Floating Wind, Foundations, Manufacturing, Supply Chain

    Switzerland-headquartered Holcim has taken a minority equity ownership in the floating offshore wind technology developer BW Ideol. “This investment sends a powerful message to the floating offshore wind industry, confirming the maturity and deliverability of concrete foundation solutions. With Holcim by our side, we’re making significant strides in our large-scale, concrete serial fabrication strategy“, said […]

  • 12 December 2025
    Business & Finance, Contracts & Tenders, Supply Chain

    Jumbo Offshore has signed two contracts for the transport and installation of transition pieces (TPs) for an upcoming offshore wind farm development, the company said via social media on 12 December, leaving the project and the client unnamed. In addition to transport and installation (T&I), Jumbo will provide full management and operation of the marshalling […]

  • 11 February 2026
    Fixed-Bottom, Grid Connection, Wind Farm Update

    Germany’s total offshore wind power generation in 2025 amounted to 26.1 TWh, of which 20.8 TWh came from the North Sea and 5.38 TWh from the Baltic Sea, according to TenneT Germany, the transmission system operator (TSO) in charge of the country’s North Sea grid. In this article: With onshore wind farms contributing 106.5 TWh […]

  • 4 December 2025
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    All 21 monopile foundations at the Windanker offshore wind farm in the German Baltic Sea have been installed, according to a social media update posted by Iberdrola Deutschland. The work was carried out by Van Oord using the heavy-lift installation vessel Svanen, which installed the first monopile in September. According to Iberdrola, these are some […]

  • 2 December 2025
    Business & Finance, Ports & Logistics

    Abu Dhabi-based AD Ports Group and Masdar have signed a partnership agreement to collaborate on the development and delivery of offshore wind projects. Under the agreement, the two firms will identify opportunities for AD Ports Group to act as a partner and contractor on Masdar’s global offshore wind initiatives, and will jointly determine technical requirements […]

  • 3 March 2026
    Authorities, Floating Wind, Planning & Permitting, Project Updates, Wind Farm Update

    Ocean Winds has entered into an agreement for lease with the Crown Estate for a 1.5 GW floating offshore wind project, for which the developer secured a site in the Round 5 seabed auction last year. Offshore Wind Leasing Round 5, the UK’s first dedicated floating wind seabed leasing round, was launched in February 2024, offering three […]

  • 1 October 2025
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Vessels, Wind Farm Update

    The first monopile has been installed at the Windanker offshore wind project site in the German Baltic Sea, marking the start of construction on Iberdrola’s third large-scale offshore wind project in the region, the company said via social media on 1 October. The monopiles are being installed by Van Oord using its heavy-lift installation vessel […]

  • 10 July 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    The 476 MW Baltic Eagle offshore wind farm in Germany has reached full energisation, the joint venture between Iberdrola and Masdar said on 10 July, as they announced a joint investment in the East Anglia Three offshore wind farm in the UK. Baltic Eagle comprises 50 Vestas V174-9.5 MW wind turbines installed on monopile foundations. […]

  • 3 July 2025
    Business & Finance, Contracts & Tenders, Grid Connection, Offshore Platforms, Operations & Maintenance, Supply Chain

    Iberdrola has awarded Semco Maritime two offshore service contracts, with options for extension, on the above-water scheduled and unscheduled maintenance of electro-mechanical equipment at two offshore substations in the Baltic Hub. The Baltic Hub currently consists of two offshore wind farms, the 350 MW Wikinger and the 476 MW Baltic Eagle, near the island of […]

  • 6 August 2025
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    The consortium of Navantia Seanergies and Windar Renovables has delivered the last monopiles to Iberdrola for the 315 MW Windanker offshore wind farm in the German Baltic Sea. The monopile foundations have been produced at the factory that both companies operate jointly at the Navantia Seanergies shipyard in Fene, Spain. Each of the units measures […]

  • 23 July 2020
    Contracts & Tenders, Wind Farm Update

    Spanish energy company Iberdrola is finalizing the selection of the main contractors for the Baltic Eagle and Wikinger Süd offshore wind projects in the German Baltic Sea. The 476 MW Baltic Eagle and the 10 MW Wikinger Süd were selected in the second public tender organised by Germany’s Federal Network Agency (Bundesnetzagentur) in April 2018. As previously […]

  • 13 September 2023
    Fixed-Bottom, Project Updates, Wind Farm Update

    Van Oord’s installation vessel Svanen has installed all monopiles at the 476 MW Baltic Eagle offshore wind farm in Germany. All of the 50 monopiles were manufactured by the Rostock-based company EEW Special Pipe Constructions (EEW SPC). After completing the manufacturing, the units were transported floating from the Rostock Port to the Baltic Eagle offshore […]

  • 24 August 2021
    Ports & Logistics, Wind Farm Update

    Denmark’s Port of Roenne A/S has been selected as an installation port for the Baltic Eagle offshore wind farm in the German Baltic Sea. Iberdrola and Vestas have signed a contract to supply 50 units of the V174-9.5 MW offshore wind turbine for the Baltic Eagle project situated in German waters 40 kilometres west of […]

  • 24 July 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    Half of the 50 wind turbines that will make up the Baltic Eagle offshore wind farm in Germany have been installed, according to information in Iberdrola’s financial report for the first half of 2024. The 476 MW offshore wind farm, currently under construction in the German Baltic Sea, will comprise 50 Vestas V174-9.5 MW wind […]

  • 4 October 2023
    Fixed-Bottom, Project Updates, Wind Farm Update

    Van Oord has commenced inter-array cable installation activities at Iberdrola Deutschland’s 476 MW Baltic Eagle offshore wind farm in Germany. After Van Oord’s heavy lift installation vessel Svanen completed the installation of all 50 monopiles for the Baltic Eagle offshore wind farm, Van Oord now continues installing transition pieces and starts cable installation. According to […]

  • 6 October 2023
    Contracts & Tenders, Supply Chain

    Van Oord has contracted Jumbo Offshore to transport and install transition pieces (TPs) for Iberdrola’s Baltic Eagle offshore wind project in the German Baltic Sea. Operations on the project are to commence this month. Van Oord recently installed all monopiles and began inter-array cable installation activities at the Baltic Eagle site northeast of the Rügen […]

  • 26 February 2020
    Grid Connection, Wind Farm Update

    Preliminary agreements to ensure the grid connection for the Saint-Brieuc offshore wind project in France and the Baltic Eagle and Wikinger Süd projects in Germany have been concluded, Iberdrola said. For Saint-Brieuc, a preliminary agreement has been concluded with grid operator RTE to ensure the grid connection will be available in the second quarter of […]

  • 14 March 2022
    Wind Farm Update

    EEW Special Pipe Constructions (SPC) has completed the fabrication of the first monopile for the Baltic Eagle offshore wind farm in Germany, owned by the Spanish energy company Iberdrola. The monopile, which was completed on 18 February, weighs 1,363 tonnes and has a diameter of 9 metres, and will be followed by 49 more, manufactured […]

  • 11 February 2019
    Business & Finance, Contracts & Tenders, Wind Farm Update

    Iberdrola has selected MHI Vestas Offshore Wind as the preferred wind turbine supplier for the Baltic Eagle offshore wind project in the German Baltic Sea. According to MHI Vestas, the contract includes the supply of up to 52 V174-9.5 MW turbines for the 476MW project, which will be the first offshore wind farm to feature this model. […]

  • 16 October 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    All 50 turbines have been installed at the 476 MW Baltic Eagle offshore wind farm in the German Baltic Sea. The Baltic Eagle offshore wind farm comprises 50 Vestas V174-9.5 MW wind turbines installed on monopile foundations by Fred. Olsen Windcarrier’s jack-up vessel Blue Tern. The wind turbine installation at the Baltic Eagle project site […]

  • 26 February 2024
    Business & Finance, Fixed-Bottom, Project Updates, Wind Farm Update

    Iberdrola Deutschland and O2 Telefónica have signed a long-term power purchase agreement to supply renewable power from the 476 MW Baltic Eagle offshore wind farm in the German Baltic Sea. Under the 15-year agreement, Iberdrola will supply 3,000 GWh of renewable energy to O2 Telefónica from the Baltic Eagle offshore wind project, starting in 2025. […]

  • 5 July 2021
    Vessels, Wind Farm Update

    Vestas has contracted Fred. Olsen Windcarrier for the transportation and installation of 50 of its 9.5 MW wind turbines at Iberdrola’s Baltic Eagle offshore wind farm in Germany. This is one of the three new transport and installation contracts announced on 28 May 2021, Fred. Olsen Windcarrier said. The installation works, to be performed by […]

  • 25 April 2022
    Authorities, Wind Farm Update

    Spanish energy company Iberdrola has completed the planning approval process for the 476 MW Baltic Eagle offshore wind farm and received a positive decision from Germany’s Federal Maritime and Hydrographic Agency (BSH). Following the approval from BSH, Iberdrola is now moving forward with the construction phase of the company’s second wind farm project in the […]