Advertisement

Cables

1 minute ago

Seaway7 Kicks Off Cable Installation Work at Ørsted's Hornsea 3

SK

Sara Kosmajac

1 minutes read
Seaway Phoenix cable-laying vessel
Credit: Flying Focus/Ørsted

Seaway7 has begun installing inter-array cables at Ørsted's Hornsea 3 offshore wind farm site in the UK.

The company will install 500 kilometres of cables to connect the project’s 197 offshore wind turbines to two offshore converter stations.

“After almost five years of hard work we’ve reached the key moment for our array cables. The installation programme is a significant milestone that underpins the construction of Hornsea 3 Offshore Wind Farm,” Luke Bridgman, Managing Director, Hornsea 3 at Ørsted, said.

As reported recently, Seaway7 has deployed its cable layer Seaway Phoenix for the operation, as well as the walk-to-work vessel Seaway Moxie to support the work.

Hellenic and Prysmian have been selected as inter-array suppliers, while JDR Cable Systems is in charge of array cable testing and termination.

Hornsea 3 is Ørsted’s first European HVDC project and its third gigawatt-scale project in the Hornsea zone, following the 1.2 GW Hornsea 1 and the 1.4 GW Hornsea 2.

The 2.9 GW offshore wind farm will feature 197 Siemens Gamesa’s SG 14-236 DD offshore wind turbines.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.