Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Business development›EolMed Partners Switch On French Floating Wind Pilot Project
Business development

April 21, 2026 · about 5 months ago

EolMed Partners Switch On French Floating Wind Pilot Project

The EolMed floating wind pilot project in the south of France has been energised, according to Qair, which has been developing the project together with TotalEnergies and BW Ideol. “This marks the start of a critical phase of technical testing, paving the way for full commissioning and the first kil

2 minutes read
  • LinkedIn
  • X
  • Email
EolMed Partners Switch On French Floating Wind Pilot Project
EolMed; Photo source: Qair via LinkedIn

The EolMed floating wind pilot project in the south of France has been energised, according to Qair, which has been developing the project together with TotalEnergies and BW Ideol.

“This marks the start of a critical phase of technical testing, paving the way for full commissioning and the first kilowatt-hours of renewable electricity to be fed into the grid”, Qair said on 21 April via social media.

The 30 MW floating offshore wind farm is located some 20 kilometres off the coast of Port-La Nouvelle and Gruissan, in water depths of around 60 metres, and comprises three Vestas V164-10.0 MW wind turbines installed on BW Ideol’s Damping Pool floating foundations.

The first of the three floating wind turbines left the Port of Port-La Nouvelle for the project site in December 2025.

Related Articles

Featured

First EolMed Floating Offshore Wind Turbine Heads to Installation Site

1 min read

Fully consented in February 2021, EolMed reached financial close in March 2022 after the project partners secured EUR 85 million in financing from the European Investment Bank (EIB).

The construction of the floating foundations started in Spring 2023 in Port-La Nouvelle with the arrival of the first steel blocks that make up the three substructures. Later that year, Bourbon Subsea Services installed a floating electrical hub (FEH) at the EolMed pilot floating wind farm site.

Related Articles

Floating Wind

Floating Substation Installed at French Pilot Project Site

2 min read

The EolMed project entered its final phase with the launch of maritime operations in August 2025, with the installation of anchors and anchor lines, followed by the launch of floaters and the integration of wind turbines on the foundations in September last year.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Business developmentFloating WindFoundationsProject UpdatesResearch & DevelopmentSupply ChainWind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Njord Survey Inks Three-Year Agreement with RWE
  2. 2Jan De Nul Orders Another Newbuild Trenching Support Vessel
  3. 3DEHN Launches Digital Platform for Wind Turbine Lightning Monitoring
  4. 4Cadeler and Vattenfall to Explore Next-Gen Offshore Wind Major Component Exchange Solutions

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free