Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Fixed-Bottom›First Hornsea 3 Offshore Substation Stands Complete
Fixed-Bottom

March 31, 2026 · about 5 months ago

First Hornsea 3 Offshore Substation Stands Complete

2 minutes read
  • LinkedIn
  • X
  • Email
First Hornsea 3 Offshore Substation Stands Complete
Hornsea 3 OCS1 installation; Photo source: Heerema Marine Contractors via LinkedIn

Heerema Marine Contractors, using its semi-submersible crane vessel (SSCV) Sleipnir , has completed the installation of the first of the two Hornsea 3 offshore converter stations.

As reported recently, Sleipnir started installing the jacket foundation for the Offshore Converter Station 1 (OCS1) at Ørsted’s Hornsea 3 project site offshore the UK on 19 March.

Related Articles

Featured

Sleipnir Installs First Hornsea 3 Offshore Substation Jacket Foundation

2 min read

According to a social media post from Heerema Marine Contractors on 31 March, both the jacket and the topside are now in place, with the project’s second substation (OCS2) to be installed later this year.

Heerema Fabrication Group, which was contracted in 2022 by Aibel to design and fabricate jackets for the two Hornsea 3 OCS platforms, said on 24 March that it had completed the foundation for the first offshore substation, and that the substructure was towed to SSCV Sleipnir on 18 March.

The topside for the first substation, built by Aibel and Hitachi Energy, arrived in Norway from Thailand in June 2025.

Heerema Fabrication Group is currently working on the OCS2 jacket foundation, which is scheduled to be completed in August 2026. The topside for OCS2 arrived in Norway in October last year.

Hornsea 3, located approximately 160 kilometres off the Yorkshire coast, is now gearing up for the installation of wind turbine foundations, which is scheduled to start in April.

Related Articles

Fixed-Bottom

Foundation Installation Coming Up at Hornsea 3

2 min read

The 2.9 GW offshore wind farm, which will feature 197 Siemens Gamesa’s 14 MW turbines, is expected to be operational in 2027.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Fixed-BottomGrid ConnectionOffshore PlatformsProject UpdatesWind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Ørsted and Nuveen Inaugurate 913 MW Offshore Wind Farm in Germany
  2. 2Stillstrom Signs Semco Maritime to Build Offshore Charging Equipment
  3. 3SLPE Secures Foundation Engineering Work on EnBW’s 1 GW Dreekant Offshore Wind Farm
  4. 4DeepOcean and TFKable Plan JV for Inter-Array Cable Projects with Dedicated Vessel

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free