Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Featured›First Turbine Up at Dogger Bank B Offshore Wind Farm
Featured

March 3, 2026 · about 6 months ago

First Turbine Up at Dogger Bank B Offshore Wind Farm

The first of the 95 GE Haliade-X 13 MW wind turbines has been installed at Dogger Bank B, the second phase of the 3.6 GW Dogger Bank Wind Farm in the UK. This is according to the information in a Notice to Mariners issued by the project on 2 March, which states the wind turbine installation [&hellip

1 minutes read
  • LinkedIn
  • X
  • Email
First Turbine Up at Dogger Bank B Offshore Wind Farm
Jan De Nul

The first of the 95 GE Haliade-X 13 MW wind turbines has been installed at Dogger Bank B, the second phase of the 3.6 GW Dogger Bank Wind Farm in the UK.

This is according to the information in a Notice to Mariners issued by the project on 2 March, which states the wind turbine installation vessel (WTIV) Voltaire continues to work within the array site, with the commissioning service operation vessel (CSOV) IWS Skywalker also at Dogger Bank B providing construction support.

Jan De Nul’s WTIV Voltaire completed the installation of wind turbines on Dogger Bank A in the second half of February and immediately moved on to the same work on Dogger Bank B.

Related Articles

Featured

All Wind Turbines Up at Dogger Bank A, WTIV Voltaire En Route to Dogger Bank B

2 min read

The installation of Dogger Bank B wind turbines will continue until approximately the second quarter of 2027.

All 277 foundations have been installed across the three 1.2 GW Dogger Bank Wind Farm sites, with inter-array cable work completed on the first two phases.

While Dogger Bank A and B each comprise 95 Haliade-X 13 MW turbines, the third phase , Dogger Bank C, will feature 87 GE Haliade-X 14 MW turbines.

The Dogger Bank Wind Farm project is owned by the consortium of SSE Renewables, Equinor, and Vårgrønn, which are also planning to build Dogger Bank D , the fourth phase of what is already set to become the world’s biggest wind farm.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

FeaturedHeadlinesFixed-BottomProject UpdatesSupply ChainVesselsWind Farm UpdateWind Turbines

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1US Gets New Offshore Wind Farm as All Turbines Installed at 704 MW Revolution Wind
  2. 2Vietnam-Made Cable Layer Enters Into Service in Taiwan
  3. 3Germany’s 960 MW He Dreiht Offshore Wind Farm Inaugurated
  4. 4200th Vestas V236-15.0 MW Wind Turbine Installed Offshore

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free