Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Featured›Maersk WTIV Completes Sea Trials, Delivery Scheduled for February
Featured

January 9, 2026 · about 9 months ago

Maersk WTIV Completes Sea Trials, Delivery Scheduled for February

The Maersk wind turbine installation vessel (WTIV), being built by Seatrium, has recently completed sea trials and is due for delivery at the end of February, according to the vessel owner. The new WTIV, which is planned to be deployed on Equinor’s Empire Wind offshore wind project in the US, was la

2 minutes read
  • LinkedIn
  • X
  • Email
Maersk WTIV Completes Sea Trials, Delivery Scheduled for February
Maersk Wind Turbine Installation Vessel; Photo source: Seatrium

The Maersk wind turbine installation vessel (WTIV), being built by Seatrium, has recently completed sea trials and is due for delivery at the end of February, according to the vessel owner.

The new WTIV, which is planned to be deployed on Equinor’s Empire Wind offshore wind project in the US, was launched to sea at Seatrium’s flagship Tuas Boulevard Yard in Singapore in May last year.

Related Articles

Vessels

Maersk Wind Installation Vessel Hits the Water

1 min read

The vessel was recently at the centre of a dispute between the vessel’s shipbuilder and its owner as Maersk terminated the USD 475 million (approximately EUR 409 million) shipbuilding contract with Seatrium in October 2025, after which both companies launched arbitration proceedings.

The companies settled their dispute in December, with Maersk agreeing to accept the delivery of the WTIV this year.

Related Articles

Featured

Maersk and Seatrium Settle Offshore Wind Dispute

2 min read

The new vessel, which underwent sea trials in the South China Sea, is part of Maersk Offshore Wind’s feeder solution, whereby the WTIV remains at a project site to carry out installations, while feeder vessels ferry the wind turbine components out to the site.

Both the Maersk WTIV and the feeder vessels are equipped with new locking and stabilising technology, enabling safe operations in harsh environments, reducing the number of days required to install the wind park. The Jones Act-approved concept is projected to reduce the number of days required to install an offshore wind farm by 30 per cent, according to Maersk Offshore Wind.

The vessel, which has an overall length of 145 metres, will sail under the Danish flag, according to information about the WTIV shared earlier.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

FeaturedHeadlinesBusiness & FinanceVessels

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Pacifico Energy Launches Survey Campaign for 1.8 GW Offshore Wind Projects in Vietnam
  2. 2Inter-Array Cable Installation About to Start at 2.9 GW UK Offshore Wind Farm
  3. 3Ørsted Orders Third Saab Seaeye Cougar ROV for Offshore Wind Operations
  4. 4Hampidjan Advant to Equip Cadeler's Wind Ace for East Anglia Two Job

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free